Professional Documents
Culture Documents
Unit Rate Build - Up Excavation
Unit Rate Build - Up Excavation
Unit Rate Build - Up Excavation
EXCAVATION
0.2 14 10 -
0.5 43 30 23
0.8 66 47 37
1.0 80 55 44
EXCAVATION
Output of a scraper depends on capacity, length of haul, haul speed and return
speed.
Plant
Scraper hourly hire rate @ $200 / hr
EXCAVATION
Example 3
Excavate over surface of site to reduce levels 150 m3
Plant
Scraper hourly hire rate @ $200 / hr = 200.00
Utilization allowance ( 10/90) % = 11% = 22.00
=222.00
Assume 0.2 m3 excavator, in heavy clay 75% estimated utilization and 10% hand excavation.
Labour
From example 2 rate per m3 @ $47.00
Heavy clay multiplier @ 1.50
Plant
Excavator hourly rate @ $80/hr
Output 10 m3 / hr
0.6 multiplier
Plant proportion 90%
EXCAVATION
Example 4
Excavate trench for foundations 0 to 1.5 m below reduced level 100 m3
Assume 0.2 m3 excavator, in heavy clay 75% estimated utilization and 10% hand excavation.
Labour
From previous example 2 = 47.00
Heavy clay multiplier = 1.50
=70.50 @ 10% = $7.05
Plant
Excavator hourly rate @ $80/hr = 80.00
Utilization allowance ( 25/75) % = 33.33% = 26.66
=106.66
It is a temporary support and normally it will not be detailed on the drawings, but
it must comply with all the requirements of codes of practice.
Planking and strutting normally done by timber but steel shield planking and
strutting is getting more popular now.
Steel shield planking and strutting have longer life and it provides more safety to
the workers. They are readily placed and removed by mobile crane. These can be
hired.
EXCAVATION
PLANKING AND STRUTTING
EXCAVATION
PLANKING AND STRUTTING
Timber used for planking and strutting is normally used to destruction. Its normal
life expectancy ranges between 5 and 10 uses. A material usage factor of 10% to
20% therefore occurs each time the planking and strutting is used and
dismantled.
Erecting and dismantling planking and strutting for reuse is usually done with an
equal carpenter / labourer combination.
Although the planking and strutting is usually done in m2, the labour outputs are
based on m3 of timber used owing to the variable nature of the size and length of
poling boards, walings and struts.
Normally the allowance for overhead, profit and risk will be 20%
EXCAVATION
HARDCORE FILLING
The cost of placing hardcore may vary. The estimator must allow whatever the
conditions prevail.
The delivery truck may tip the hardcore directly into the final position
It may be moved and placed by a front loader
On confined sites, the hardcore may have to be tipped and barrowed and filled by hand
Hardcore consolidates approximately 20% when compacted into position. To
cover for this a 25% consolidation factor should be allowed. For example, a 10 m3
hole requires (10 m3 + 25%) 12.5 m3 material to fill. (12.5 m3 – 20% = 10 m3)
Compaction of hardfill is generally done with mechanical plate compactors for
small areas and with hand or machine driven vibrating rollers weight up to several
tonnes for large areas.
EXCAVATION
Example 5
Hardcore filling under ground floor slab, compacted in layers not exceeding 150mm thick 100 m3
Materials
Delivered to site @ $15.00 / m3
Consolidation 25%
Labour
1.25m3 x 0.8 hour / m3
labour rate $ 20.00 / hr
Plant
Hire of plate compactor @ $47/day
Fuel, say $5 / day
Say 7 hours per day
EXCAVATION
Example 5
Hardcore filling under ground floor slab, compacted in layers not exceeding 150mm thick 100 m3
Materials
Delivered to site @ $15.00 / m3 = 15.00
Consolidation 25% = 3.75
= 18.75
Labour
1.25m3 x 0.8 hour / m3 1 hr x $ 20.00 / hr = 20.00
Plant
Hire of plate compactor @ $47/day
Fuel, say $5 / day
Cost per day $ 52/day
Say 7 hours per day = 52/7 = $7.43 / hr @ 1 hr/m3 = 7.43
Labour
0.06 hr / m2 @ $20.00/hr $1.20