Hot mix To less space between scale and fixed other

cooling L12 parts.

Pelletizer / Grecon sensors not installed yet on several


Bigbag filling places (Picture is just an example). Remark:
Installed bot not connected

Kahl Tower Cables not connected (grecon)

Kahl Tower Cables not connected (grecon)

Cooling tower The sprinkler head is directly in the area of


Line 1&2 the explosion pot of the filter.
In the event of an explosion, a hot pressure
wave is generated in the area of 2.5m, which
will supposedly trigger the sprinkler, which
would be a false alarm, as there is no fire and
would cause more problems.
Cooling tower General: Grecon sensors not connected
Line 1&2

Cooling tower bolts are not tight


Line 1&2

Cooling tower Bearing bolt not tightend


Line 1&2

Cooling tower Motor bolts not tightend


Line 1&2

Cooling tower Motor bolts not tightend


Line 1&2
Cooling tower Bad workmanship for air hoses at filter
Line 1&2

Finegrinding The gap between the rolling gates should be


closed.

Finegrinding In some cases, anchor bolts are missing from the


feet of the Nollmills.

Finegrinding Sound cabinet should be sealed as much as


possible. Foto serves as an example.

AZO Electrically not connected


finegrinding
AZO Electrically not connected
finegrinding

AZO Electrically not connected


finegrinding

AZO Electrically not connected


finegrinding

AZO Electrically not connected


finegrinding

Azo N2 & ODA Blower motor not connected


Azo N2 & ODA Instrumentation not electrically connected

Azo N2 & ODA Instrumentation not electrically connected

Azo N2 & ODA Instrumentation not electrically connected

Azo N2 & ODA Instrumentation not electrically connected

Azo N2 & ODA Instrumentation not electrically connected


Azo N2 & ODA Instrumentation not electrically connected

Azo N2 & ODA Instrumentation not electrically connected

Azo N2 & ODA Instrumentation not electrically connected

Hot mix cooling Fit piping/hoses to vaccuum breaker valves on hot


L12 mix tower. Connect electrically. Bolt to structure
(2x)

Grinding Rotating parts, no safety placed


Tower 1