METHOD STATEMENT
Method Statement for Construction Block Paving
Department: Date: Document Ref.: Revision:
02
Project/Contract:
Principal Contractor:
Site Address:
Project Start Date:
Expected Duration:
Completion Date:
Name Job Title Signature Date
Prepared by:
Authorised by
Client Approval:
Table of Contents
Scope:..........................................................................................................................................................4
Objectives....................................................................................................................................................4
Personal, Tools, Plants and Equipment.......................................................................................................4
References Tools, Plants, Equipment and Machinery..............................................................................4
References/Supporting Documents.............................................................................................................5
Details of Health & Safety Arrangements Include:......................................................................................5
Scope and Procedures.................................................................................................................................5
Scope of Works and Pre-Activities...........................................................................................................5
Methodology/Procedures...........................................................................................................................5
Laying of Kerbs....................................................................................................................................5
Placing of Fill/Sub-Base Material.........................................................................................................6
Laying of Interlock Paviors/Stones (60 mm & 80 mm Thick)...............................................................6
Key Materials Required...............................................................................................................................6
List of Key Materials Required.................................................................................................................6
Residual Hazards and Safety Requirement..................................................................................................7
Specific Identified Residual Hazards....................................................................................................7
List of Safety Requirements.................................................................................................................7
Risk Management for Work:........................................................................................................................7
Summary of Activities with Potential Hazards and Risks:............................................................................7
Controls Initiatives:..................................................................................................................................7
Communication and Training of Health and Safety:................................................................................8
Checks and Inspections:..........................................................................................................................8
Induction and Permits to Work:..........................................................................................................8
Method Statement details...................................................................................................................8
Security:...............................................................................................................................................8
Rules:...................................................................................................................................................8
Smoking:..............................................................................................................................................8
Services:...............................................................................................................................................8
Unloading Details:...............................................................................................................................8
Access:.................................................................................................................................................9
HSE Documents-HSE-Method Statement for Gutter Cleaning
DOCUMENT NUMBER:
Page 3 of 11
METHOD STATEMENT
Method Statement for Construction Block Paving
Department: Date: Document Ref.: Revision:
02
Tools:...................................................................................................................................................9
Welfare facilities:.........................................................................................................................................9
Emergency Arrangements:..........................................................................................................................9
Housekeeping:.............................................................................................................................................9
Job Safety Analysis (JSA):...........................................................................................................................10
The Sequence of Work:.............................................................................................................................10
Dependent on the Work:...........................................................................................................................10
On Completion of Work:........................................................................................................................10
Use of Equipment:.................................................................................................................................10
When working at Height (General):.......................................................................................................11
When Working Alone:...............................................................................................................................11
Accidents, Incidents and Near Misses:......................................................................................................11
Scope:
Block Paving Method Statement Objectives
Objectives
Per Block Paving Method Statement Objectives
This Method Statement describes the Methodology and procedures for Block Paving Works.
This Method Statement (MS) is however to be read, apply and compliance in association with
the attached
Job Safety Analysis.
The Project Health and Safety Plan (Approved HSE Plan).
References/Supporting Documents
List of References/Supporting Documents:
Project Approved for Construction Drawing
Approved Site Survey Plan & Survey Report
Approved Project HSE Plan
Attached Job Safety Analysis
[State/Country] Construction Standard
Activities and Tasks Described in this Method Statement Include the Following:
Laying of Kerbs.
Placing of Fill/Sub-base Material.
Laying of Interlock Paviors/Stones.
Pre-Activities
Ensure approval and release of Work Area and Temporary Land Lease Area by [Client/Facility]
and or other relevant departments before the commencement of work on-site as required.
Before the commencement of work contained herein, [ Organization/ Company] shall obtain
the relevant work permits from [Client/Main Contractor].
Toolbox shall be conducted by the Supervisor.
The use of mandatory PPE (Safety Glass, Safety Shoe, Helmet, Coverall, etc.). Shall be
inspected and implemented by the safety engineer.
Methodology/Procedures
Laying of Kerbs
Upon reaching the Site Sub-grade formation level, the Surveyor shall set out the proposed
Kerbs Line according to the approved drawings.
Wooden/metal forms for the Kerbs concrete base construction shall be installed and securely
and tightly braced to limit any deflection during the concrete placement.
Concrete of specified grade and the mix would be placed in erected formwork after wetting
to aid bonding.
Steel Dowel Bars (SBD) shall be installed in the concrete base slab if needed as per approved
drawings
Kerbs shall be placed on Cement Mortar (1:4) bedding, not more than 25 millimetres
thickness on the concrete base to adjust the levels of the Kerbs with a maximum tolerance of
3 millimetres.
In arching/curving locations and corners, Kerbs shall be tailor cut as per the shape and
dimensions.
As soon as Kerbs have been laid, bordering Concrete backing of pre-determined and specified
grade shall be poured behind laid Kerbs for hardness.
Joints between the Kerbs (Not more than 4 millimetres) shall be filled with fluid cement
mortar at the ratio of (1:4).
At every 10 to 20 meters intervals, a moment joint of 20 millimetres thick shall be formed
through the concrete bed and backing as well as the Kerbs. Impregnated fiberboard shall be
used to fill the movement joints.
Curing shall be done for the entirely Kerbs, base and backing for seven days.
Placing of Fill/Sub-Base Material
The area is to be levelled, watered and compacted by the means of a roller or plate
compactor in small areas where a big roller cannot reach.
The level of the formation is to be closely observed, verified, inspected and approved
properly.
Approved Sub-base material shall be collected from the stockpile and placed in a maximum
of 200 mm compacted layers as applicable.
The material is to be properly mixed and oversize or lump materials shall be removed by
labours.
Laying of Interlock Paviors/Stones (60 mm & 80 mm Thick)
Sand material bedding of approved quality shall be placed in a 50 millimetres layer, levelled
and watered.
Interlock paviors (100 x 200 x 60 millimetres or 100 x 200 x 80 millimetres) shall be collected
from an approved source and laid in an approved pattern as per approved construction
drawings.
Interlock paviors shall be neatly trimmed/cut to fit perfectly into Kerb's edges as applicable.
Fine/dune sand material shall be placed on top of laid Interlock paviors to fill in the joints.
The laid Interlock pavior is then compacted utilizing a Plate compactor.
The dune sand shall be hand brushed and removed after the compaction works are
completed to the satisfaction of the Site engineer.
Welfare facilities:
• Before work commencing [Organization/Company] will liaise with Client’s local management for
use of toilets and wash facilities.
• Eatables/meals will be provided by the team/ operatives themselves.
Emergency Arrangements:
• The exact location of First Aid (FA) arrangements will be required to be provided by the Client
before work started.
• Fire arrangements will need to be provided by Clients before work commencing including the
location of assembly points, location of fire exits and fire equipment; procedures to follow.
• More details on [Organization/Company] Emergency Arrangements can be provided in the
attached risk assessments and safety arrangements.
Housekeeping:
• All work areas will be kept clean and tidy where possible; [Organization/Company] operate a
“clean as you go policy”.
• All tools, equipment and waste will be removed from the site after the job has been completed.
• Any (non-hazardous) waste will be disposed of using the Client’s facilities or where necessary by
the team/operative.