URDANETA CITY UNIVERSITY

COLLEGE OF ENGINEERING AND


ARCHITECTURE
CIVIL ENGINEERING DEPARTMENT

ON THE JOB TRAINING REPORT


ROXSAN
CONSTRUCTION AND SUPPLY

In Partial Fulfillment of the Requirements


in the Subject by:
MARRON JAMES P. TUMASAR

ENGR. EDSEL A. BALBERAN


Instructor

AUGUST 2023
TABLE OF CONTENTS

COMPANY DATA..................................................................................................I

BRIEF DESCRIPTION OF THE TRAINING PROGRAM..........................................II

COMPILED WEEKLY REPORTS…........................................................................III

PERSONAL EVALUATION OF THE TRAINING PROGRAM..................................IV

RECOMMENDATIONS..........................................................................................V

APPENDICES.........................................................................................................VI

PICTURES...........................................................................................................VII

OTHER PAPERS RELATED TO MY TRAINING......................................................VIII


I
COMPANY DATA
COMPANY DATA

A. Name/Address/Contact No.
Company Name: ROXSAN Construction and Supply
Address: Zone III, Brgy. Pedro T. Orata, Urdaneta City, Pangasinan
Mobile Number: 09175684170 / 09178527824

B. Inclusive Date of Training


Date Started: July 17, 2023
Date Finished: August 19, 2023

C. Names of Personnel
Engr. Theodore Emmanuel P. Roxas, RCE – Project Manager
Engr. Vanessa L. Garcia – Site Engineer
Mr. Melvin Sarmiento -- Leadman
BRIEF HISTORY AND BACKGROUND OF THE COMPANY

ROXSAN Construction and Supply is located in Zone III, Brgy. Pedro T. Orata,
Urdaneta City, Pangasinan. It was founded in the year 1990. The current president and
owner of this company is Engr. Theodore Emmanuel P. Roxas.

MISSION:
To create positive solutions through creative excellence by continuously delivering
the highest quality service to our clients and partners.

VISION:
To become efficient in planning, designing, and creating a sustainable environment
for everyone.

VALUES:
Creative. Commitment. Innovation. Teamwork. Safety. It is about the continuing
drive and goal of the company to institutionalize the values and infuse them into its culture.
II
BRIEF DESCRIPTION
OF THE
TRAINING PROGRAM
BRIEF DESCRIPTION OF THE TRAINING PROGRAM

The program gave students a hands-on method for learning new abilities and skills
required for a career in a real working environment, and it also gave interns a sense of the
duty and accountability of an engineer. The objectives that would steer the course from the
beginning to the finish were discussed at the outset of the training.

I. Objective:
1. General
Having the necessary background knowledge to learn new skills and
knowledge in a practical way before beginning the internship. It is essential
to put the academic theory you have studied to use in the real world of
employment. must have the ability to develop or build future high-quality
infrastructure

2. Specific
to become proficient in managing construction sites according to safety
standards and to become familiar with the various stages of construction. To
be able to receive partial training in order to gain experience with real-world
office/technical operations during the training time, to be ready to handle the
demands and challenges of employment, and to build positive work habits,
attitudes, and an appreciation for and respect for work.

II. Schedule / Timetable :


Monday to Saturday – 8:00 a.m. – 5:00 p.m.

III. Areas of Training:


Site Monitoring
Inventory
III
COMPILED WEEKLY
REPORTS
NAME OF COMPANY ROXSAN CONSTRUCTION AND SUPPLY
DATE STARTED JULY 17, 2023
DATE FINISHED AUGUST 19, 2023
NO. OF HOURS 240 HOURS
DATE TASKS ACCOMPLISHED
Project & Site: Construction of Landmark Tower (Alexander Street, Urdaneta City,
Pangasinan)
 Orientation
 Checking workers' attendance
 Monitoring on-going Projects of
Landmark tower, Urdaneta City,
Pangasinan
July 17, 2023 (8hrs)
 Site Inspection
 Monitoring the fabrication of column
ties

 Checking workers' attendance


 Installation of column Ties in third floor
July 18, 2023 (8hrs)  Site clearing

 Checking workers' attendance


 Continuation of the installation of
column ties in third floor
July 19, 2023 (8hrs)
 Continuation of fabrication of column
ties
 Inventory of fabricated and installed
column ties
 Checking workers' attendance
 Installation of formworks for columns in
third floor
July 20, 2023 (8hrs)  Monitoring the spacing of
installed column ties in third floor
 Continuation of installation of column ties
in third floor

 Checking workers' attendance


 Continuation of installation of column
ties in third floor for other columns
July 21, 2023 (8hrs)  Installation of column spacers
 Installation of additional scaffoldings

 Checking workers' attendance


 Installation of beam reinforcement at
third floor beam
July 22, 2023 (8hrs)
 Fabrication of column formworks
 Payroll of workers

 Checking workers' attendance


 Monitoring and observing the
installed column formworks
July 24, 2023 (8hrs)  Fabrication of beam stirrups
 Fabrication of extra bars for
beams in third floor
 Site clearance
 Checking workers' attendance
 Continuation of installation of
beam reinforcement in third
floor
 Splicing bars for third floor beam
July 25, 2023 (8hrs)
 Continuation of fabrication of beam
stirrups
 Monitoring onsite progress
 Monitoring the installation of beam
reinforcement in third floor

 Checking workers' attendance


 Observing and monitoring the
installed spacing for columns
July 26, 2023 (8hrs)
 Continuation of installation for beam
reinforcement in third floor
 Site Clearance
 Checking workers' attendance
 Continuation of fabrication of beam
stirrups
July 27, 2023 (8hrs)  Transferred to city hall for the demolition
of old city health center
 Checking workers' attendance
 Monitoring and inventory of
fabricated beam stirrups
July 28, 2023 (8hrs)  Monitoring and inventory of spliced
bars
 Continuation of demolition of Old city
health center
 Checking workers' attendance
 Monitoring the demolition of old city
health center
 Inventory
July 29, 2023 (8hrs)  Site clearance in old city health center
 Preparing the payroll of workers

 Checking workers' attendance


 Observing for the installation of extra
bars for beam reinforcement at third
floor
July 31, 2023 (8hrs)
 Cutting of GI wires for ties
 Continuous fabrication of beam
stirrups
 Continuation of installation od
beam Reinforcement at third floo
 Checking workers' attendance
 Monitoring and observing the installed
column formworks
 Continuation of installation of beam
August 01, 2023 (8hrs)
reinforcement at third floor
 Cutting of GI wire fir ties

 Checking workers' attendance


 Continuation of the unfinished
installation of beam
reinforcement at third floor
 Column formworks installation
August 02, 2023 (8hrs)  Monitoring and observing
the installed beam
reinforcement
 Monitoring the whole site progress

 Checking workers' attendance


 Inspecting the installation of extra bars
at third floor beam
 Continuation of installation of beam
reinforcement for third floor
 Observing the installation of
August 03, 2023 (8hrs)
beam reinforcement at third
floor
 Inventory of installed number of stirrups
per beam

 Checking workers' attendance


 Monitoring and observing
the fabrication of beam
stirrups and extra bars
 Installation of runners for ribbed beam
August 04, 2023 (8hrs) at third floor
 Continuation of the unfinished
installation of beam
reinforcement
 Payroll preparation
 Site Inspection
 Checking workers' attendance
 Inspection of installed ribbed
beam runners at third floor
 Continuation of fabrication of
beam stirrups
August 05, 2023 (8hrs)
 Splicing of bars for cantilever
beam reinforcement
 Site Inspection
 Payroll distribution
 Checking workers' attendance
 Continuous fabrication of beam stirrups
and extra bars
 Installation of additional scaffoldings
for cantilever beam
August 07, 2023 (8hrs)  Continuation of installation for ribbed
beam runners
 Continuation of beam reinforcement at
third floor
 Checking workers' attendance
 Continuation of the formwork
fabrication
August 08, 2023 (8hrs)  Installation of beam reinforcement
for cantilever beams
 Fabrication of stirrups for ribbed beams

 Checking workers' attendance


 Installation of temporary stairs for
city engineering inspection
 Fabrication of runners for arc beams
August 09, 2023 (8hrs)  Fixed and adjusted installed runners at
third floor
 Site clearance
 Site inspection

 Checking workers' attendance


 Continuation of runner fabrication for
arc beams
 Started installing the arc runner
August 10, 2023 (8hrs)
for third floor beam
 Continuation of installation of
beam reinforcement for
cantilever beam
 Spliced bars for cantilever beam
 Checking workers' attendance
 Continuation of installation of
cantilever beam reinforcement
August 11, 2023 (8hrs)
 Installed concrete spacers for beam at
third floor
 Site clearing at second floor
 Site Inspection
 Checking workers' attendance
 Continuation of installation of column
August 12, 2023 (8hrs) formworks
 Continuation of installation of
unfinished cantilever beam
reinforcement
 Site Inspection
 Checking workers' attendance
 Removal of installed 10mm bar columns
ties
August 14, 2023 (8hrs)  Installation of 12mm bar column ties
 Fabrication of stirrups using 12mm bar
 Site Clearance
 Site Inspection
August 15, 2023 (8hrs)  Checking the workers’ attendance
 Installation of diamond column ties
 Installation of extra bars for beam
reinforcement at cantilever beam
 Fabrication of diamond column ties
 Started to install siding formwork of
beam at third floor
 Checking workers' attendance
 Continuation of removal of 1o mm bars
column ties
 Installation of column formwork for
August 16, 2023 (8hrs) approved columns
 Installation of diamond ties for
column

 Checking workers' attendance


 Continuation of installation of column
formworks
 Replacement of column removed
August 17, 2023 (8hrs) column ties
 Fabrication of column ties
 Site clearing

 Checking workers' attendance


 Continuation of unfinished
installation of bean reinforcement
at third floor beam
 Continuation of formwork installation
for columns
August 18, 2023 (8hrs)
 Continuation of fabrication of stirrups
 Continuation of fabrication of column
ties and extra bars
 Continuation of site clearance
 Checking workers' attendance
 Site Inspection
 Continuation of installation of
runner for arc beam
August 19, 2023 (8hrs)  Continuation of installation of
beam reinforcement at third floor
overhang beam
 Continuation for final installation
of column formworks
 Payroll distribution of workers
IV
PERSONAL EVALUATION
OF THE
TRAINING PROGRAM
PERSONAL EVALUATION OF THE TRAINING PROGRAM

Reaction paper by the trainee to include comments on the following areas:

1. Significant Achievements
I picked up a few technical skills during my training that helped me become more
self-aware and acquainted with the workplace in my chosen sector of expertise. In
addition, we helped with finishing jobs including installing stirrups for columns and
beams and cutting wire for ties.
2. Technical skills and new technology learned
Throughout my site monitoring, I learned about and gained experience with the
technical aspects of each distinct scope of work. Additionally, during our site visits
to the other sites, we noticed how workers constructed footing and concrete
pouring. Additionally, we learned in actual the estimation of phenolic boards,
lumbers, and steel decks that would be used
3. Equipment, machinery, testing apparatus, etc., handled
I had the chance to use a steel cutter, a masonry trowel, and pliers during my
training. In addition, I witnessed how a concrete mixer and backhoe were used in
actual construction.
4. Experiences with the company personnel involved in the training
During my training period, I received a great deal of knowledge from the site
engineer, foreman, skilled workers, and even laborers as I attended my on-the-job
training in the office and on-site. All of them were eager to share their expertise on
the working procedures and details with us and were able to respond to our
inquiries about their jobs.
5. Strong points
One of the strengths of the training program is that it gives students the chance to
interact with and learn about the actual work that is done in their chosen area of
expertise, as well as to acquire knowledge that they can use in the future.
6. Weak points and suggested solutions
One thing that concerned me and was considered the company’s weak point was the
inability to prioritize site inspection and supervision on the project.
V
RECOMMENDATIONS
RECOMMENDATIONS

A. Potential of the company as a training ground


 Availability and appropriateness of facilities, equipment and machinery
Due to the company's adequately controlled facilities, machinery, and
equipment, as well as the fact that everyone's safety is given top attention, I
can attest to its availability and suitability as a training ground as a trainee.
 Company personnel cooperation
Cooperation and positive relationships are significant in this company. Workers
in the company must share knowledge and ideas from their experience and
knowledge to help trainees advance in their chosen sector of competence in
order to learn new things and obtain more experience.
B. Duration of training (too long or too short)
The training period is brief, but it shouldn't be too brief because, as trainees, we
must gain a lot of knowledge and abilities in that time in order to use them
effectively as engineers.
C. Suggestions for the improvement of the training program
Increase the amount of time that on-the-job trainees spend receiving training, and
keep creating initiatives that can help students feel more at home in the
workplace.
D. Advise to future On-the-Job Trainees
As you enter a construction site or visit a site, be sure to pay great attention to
even the slightest things. Additionally, pick a business that fits your program and
will help you develop your talents, increase your confidence, and feel committed to
your work. As you begin your training in the field you're entering, be proactive and
self-assured. As a result, be brave and ask your site supervisor the questions you
want to know the answers to in order to learn new information that will enable
you to apply it successfully in your chosen field of expertise. While you're on the
practice field, pay attention and be open to learning. Additionally, treat everyone
equally and with kindness, especially the employees. Additionally, always be
friendly and extend a warm welcome to guests. Asking who they are and how you
can help them can help you assist them.
VI
APPENDICES
VII
PICTURES
VIII
OTHER PAPERS RELATED
TO MY TRAINING
CONSTRUCTION OF LANDMARK TOWER

MANPOWER SCHEDULE

MANPOWER NO.
STEEL MAN 1
CARPENTER 1
WELDER 1
MASON 3
Jr. MASON 2
LABOR 8
TOTAL 16

EQUIPMENT

CUT OFF MACHINE 1


WELDING MACHINE 1
CIRCULAR SAW 1
JIGSAW 1
TOTAL 4

NARRATIVE REPORT
On our first day, July 17, 2023, of our on-the-job training at the
construction of Landmark Tower of Urdaneta City, Province of Pangasinan,
it was cloudy and rainy. Engr. Leo has instructed us to start supervising our
designated sites. There were four trainees at the Landmark tower on our
first day. There were two workers present: Arnel Rosales and Melvin
Sarmiento. They started to cut 10mm and 12mm steel bars and formed into
lateral ties the size of 90cm x 90cm. Since it was our first day we looked
around and checked the measurements of columns and steel.
In the afternoon, Engr. Leo visited the site at 2:15 pm. He instructed us on
what to do and what not to do on the site to ensure quality results. We also
began to cut steel wires to be used as ties. It was not raining as heavily as it
was in the morning. At the end of the day about 70 pieces of lateral ties
were finished.
On July 18th, before 7:30 in the morning, employees and trainees
arrive in full PPE. The weather was sunny and additional workers were
assigned to the tower. There were also two additional trainees who joined
from the other site in Bactad. Workers started cutting steel bars, bending
steel bars for lateral ties, cutting steel wires for ties, and installing lateral
ties in the columns.
In the afternoon, around 2:14pm Engr. Leo called and requested extra
hands for their project. Therefore, seven workers from our site were
transferred to the project in the City Hall. We trainees were assigned to
monitor and help the workers with what they need. The cutting and
bending of steel bars continued throughout the day.
On day 3, July 19, 2023, it was still sunny, and more workers have
arrived ( to speed up the progress at the Landmark Tower. At 7:30 am they
started doing their work. We we’re divided into teams of two. Three people
on the second floor, supervising works in progress. The workers have
started to put formworks to be used for concrete. Then the other three
stayed on the ground floor to help make ties for the bars. The ties were for
different diameters of steel. Therefore, the cuts were a variation of lengths.
After our break, the workers immediately went back to work. At 11:26 am a
worker was tasked to get one 9mx16mm diameter deformed bar.
In the afternoon at 2:10 pm UCU instructor, Engr. Edsel A. Balbera, visited
the site and assessed the trainees on their ongoing project. At 3:22 pm, the
rain started to pour. We continued to make ties with steel wires.
On July 20, 2023, the fourth day of our on-the-job training,
employees and trainees arrived at the customary hour of 7:30 am. Because
it was a wonderful sunny day, Rodendo, Jimmy, and Argie just proceeded
installing formwork for two additional 900 x 900 mm columns. While
Melvin and Arnel continued to make column ties, Marlon and John
continued to install lateral ties that were the same size as the mentioned
column. 9:30 am or so, Engr. Vanessa visited the site and inquired about
the materials required for the job, Argie requests some nails to be used for
installing the formwork, and Melvin requests cutting discs for cutting the
bars.
During the afternoon work, together with Virgilio, who arrived at the site
for only a half-day of work, Marlon and John began placing lateral ties for
two columns during the afternoon shift. When it was about 4:30 p.m.,
Engr. Leo Roxas paid a visit to the location and requested our reports as
trainees stationed there.
Friday, July 21, 2023, the fifth day of work for the construction of
Landmark Tower. Foreman Orlando Manangan entered the site together
with 3 new labors namely, Michael Cuaresma, Angelo Zamora and Robert
Dumasin for additional manpower. Marlon, John, Dexter and Virgilio as
well as Juvy continued installing Column ties for 900 x 900 mm mm ties.
On the other hand, Rodendo installed spacers for columns to start
installation of formworks again and at the same time Argie and Jimmy
prepared the formworks and scaffoldings to be use. Engr. Vanessa Garcia
visited and delivered the requested materials such as nails and cutting discs
at 9:24. Angelo, Michael, Robert the 3 new labors together with Melvin
installing 3rd level Beam reinforcement along Gradeline of column A.

July 22, 2023 (Saturday)


The weather is sunny between 8 and 9 a.m., and cloudy between 9
and 10 a.m. On the sixth day of work, July 22, 2023, Rodendo, Jimmy, and
Argie continued to install formworks for the remaining 900 x 900 mm
columns, while Virgilio and Dexter began placing column ties for 600 x
600 mm columns along gradeline B, the same work as Juvy and John.
Marlon, on the other hand, planned the installation of the third-floor
reinforcement beam along gradeline B. Along gradeline A, Robert, Michael,
and Angelo fixed the reinforcement beam for 3 rd floor. By adding the extra
C-bars that the beam requires. Melvin and Arnel continue with their
normal work of fabricating stirrups and cutting bars. Rodendo, Jimmy and
Argie fabricated formworks for 900 x 900 mm columns in the afternoon
work.

WORK ACCOMPLISHMENTS
Fabricated and cut 5 phenolic boards ¾”
Continuation at beam A
Installed 72 c-bars 10mm bar
Installed 48 pcs 70 cm vertical c-bars
Installed 24 pcs 50 cm horizontal c-bars
Beam B finished installation
Installed 45 column ties 70x50 cm
Installed 23 pcs 12 mm bars and 22 pcs 10 mm bars
Installed 3 column formworks 900x900 column
Finished column ties of 600x600 column
Beam C started to install
July 24, 2023 (Monday)
Early in the morning Engr. Vanessa Garcia visited for some
inspection at around 7:58 a.m. Engr. Vanessa checked the site's daily time
record. Rodendo leads for the construction of formwork installation for the
last 2 remaining 900x900mm columns together with Michael and Jimmy.
While Argie, Arnel, Virgilio and Michael John started installing beam
reinforcement at beam D, 3rd level of the building. On the other hand,
Marlon, Juvy and Dexter prepared the bars to be installed in beam D,
Robert and John helps to lift bars for the installation of the beam
reinforcement.
Arnel and Jayson and Robert started the installation of beam
reinforcement along beam B2-C2, 3rd level, Arnel and Melvin bended
20mm bars for main bars. Arnel continued fabricating stirrups in the
afternoon, while Rodendo and Jimmy fabricates formworks for columns at
the same time.

WORK ACCOMPLISHMENT
Fabricated 9 formworks 900x900 columns
Installed beam D 3rd level
Installed 2 column formworks 900 x 900 columns
Installed 2 beams along B-C 3rd level
Fabricated beam stirrups – 31 pcs 10 mm and 36 pcs 12 mm
Fabricated C bar 84 cm – 70 pcs 10 mm
Fabricated C bar 64 cm – 31 pcs 10 mm

July 25, 2023 (Tuesday)


It’s a cloudy day, Arnel as a steelman continued fabricating stirrups
for 3rd level beam reinforcement. Melvin and Virgilio lead the installation
of beam reinforcement along gradeline A-B together with Argie and Angelo.
While Marlon and John as well as Michael John prepared the additional
torsion bars of beams reinforcement at 3rd level. Rodendo with Michael
and Jimmy fixed formwork installed for columns 900x900mm.On the
other hand, Robert, Dexter and Michael John lift up the additional tension
bars for beam A-B.

Afternoon work, Arnel and Melvin bends 20mm bars for tension bars of
beam and the same time Jimmy and Rodendo fabricated formworks for
600x600mm column. While the others continued the installation of beam
reinforcement.

WORK ACCOMPLISHMENT
Fabricated 4 formworks for 600 x 600 mm columns
Bend 40 pcs 20 mm bar – 7.5 meter long
Installed 2 beam reinforcement
Fabricated 55 stirrups for beam 12 mm
Fabricated 68 stirrups for beam 10 mm

July 27, 2022 (Thursday)


It’s a cloudy Thursday, Jimmy continued the preparation of
formworks for 600mmx600mm columns. While Arnel, Melvin, Argie,
Jayson, Juvy, and Robert started the installation of 2 beam reinforcement
along gradelines C-D at the 3rd level of the landmark tower. Rodendo on
the other hand, prepared the scaffoldings to be used for the installation of
column formworks for 600mmx600mm columns. Using a welding
machine, Melvin and Arnel repaired their bender in order to bend 20mm
diameter bars.
In the afternoon, the rain continued to pour and since the area is not safe to
work Engr. Leo told the workers to transfer to the city hall to help demolish
the old city health center together with the 3 OJT trainees for the
supervision of the workers.

WORK ACCOMPLISHMENT
Fabricated 100 pcs beam stirrups (12mm)
Fabricated 100 pcs beam stirrups (10mm)
Fabricated 140 pcs C bar for beam (10mm)
July 28, 2022 (Friday)
It’s a rainy Friday, Melvin and Arnel still let at the landmark tower
for the continuous fabrication of the beam stirrups and column ties. While
the others went to the city hall to continue demolish the old city health
center. Particularly, Juvy, Argie and John help the other workers for
concrete pouring of foundation and installation of column reinforcement
for the extension of the birthing facility.

WORK ACCOMPLISHMENT
Fabricated 40 pcs 12 mm bar
Fabricated 10 pcs 10 mm bar
Bend 40 pcs 20 mm bar
July 29, 2023 (Saturday)
It’s a cloudy Saturday, with 15 workers present on the site, 1
steelman, 6 masons, and 8 labors, and since it is not raining in the area, the
workers fixed the rebars of beams installed in 3 rd level of the tower by
installing the necessary extra bars, at the same time Jimmy and Rodendo
the two masons with the help of Michael as labor installed formworks for
600x600 mm columns.
During the afternoon, the rain was continuously pouring which
started at around 12:30 up until 1:28 the workers transferred to the old city
health center as per Engr. Juster Ballesteros order. Particularly, Virgilio,
Rodendo, Jimmy, Marlon, John, Robert and Angelo assigned to demolish
the old city health center while Michael, Jayson, Michael John and Dexter
were assigned for site clearing, Juvy assigned for the installation of column
reinforcement while were assigned to help for concrete pouring of the
column foundation.

WORK ACCOMPLISHMENTS
Installed 2 formworks for columns 600x600mm column 1 along grade line
B and C.
Installed beam reinforcement for beam 1 along grade line C.
Site clearing Old City Hall building B 3rd and 4th floor.
Demolition of old city health center.
Helped to install column ties for extension of Birthing Home.

July 31, 2023 (Monday)


Early in the morning at around 7:30 to 8:20 the rain poured but
right after at around 8:21 to 9:53 the rain stops and it’s another cloudy
weather. With only 7 workers for manpower in the area, specifically, 1
steelman, 3 masons and 3 labors.
To start the week and the working day, Virgilio was assigned to help
fabricate and install formworks of Tie beam for extended building at City
Hall. While Melvin, Jimmy, Juvy, Dexter and Argie were left at Landmark
Tower for the continuation of installation of C-bars for beam 2 at grade line
D, beam 1 along grade line C-D and beam 1 along grade line C. In the
afternoon, Arnel arrived at the site for only half day of work. Due to
unpredicted weather condition the four workers were transferred at the
City Hall, Arnel and Melvin left at Landmark Tower for splicing and
fabrication of tie bars for beam. Mr. Juvy and Jimmy assigned to demolish
while, Argie and Dexter are Clearing debris in old health center at City Hall.
And we as trainees are assisting and monitoring the workers if they need
help.

WORK ACCOMPLISHMENT
Installed extra C-bars for beam 2 along gradeline D.
Installed extra C-bars for beam 1 along gradeline C-D.
Installed extra C-bars for beam 1 along gradeline D.
Helped to install and fabricate formworks for tie beam (Old city health
center).
Spliced 20 pcs. 20mm diameter bars for beam reinforcement.
August 1, 2023 (Tuesday)
It’s a cloudy Tuesday for the first day of the month, August 1, 2023, with 13
members of manpower, 1 steelman, 6 masons and 6 labors. Jimmy and
Rodendo, the two mason started the day by fabricating formworks for
600x600mm columns using ½ inch thick phenolic boards. Marlon,
Michael John, Dexter and John started installing beam reinforcement
along gradeline C-D 3rd level of the tower.
On the other hand, Melvin together with Arnel installed reinforcement bars
for beam B while Juvy with the help of Robert Dumasin installed extra c-
bars for beam A-B/2 the same work with Virgilio and Argie with the
installation of extra c-bars for beam along A-B/4.

WORK ACCOMPLISHMENT
Fabricated 10 formworks for 600 x 600mm columns ½ thick phenolic
board
Installed beam reinforcement along gradeline C-D 80% done.
Installed beam reinforcing bars along beam B.
Installed extra c-bars vertical ang horizontal along beam A-B/2.
Installed extra c-bars vertical ang horizontal along beam A-B/4.

August 2, 2023 (Wednesday)


It’s still a nice weather for the workers and OJT trainees, 2 nd day of
August 2023, a cloudy Wednesday, with 14 workers present in the site
particularly, 7 labors, 1 steelman and 6 Masons.
Argie and Michael John did the site clearing to look for available
formworks that can be reuse. Marlon, Dexter and John prepared G.I. wires
for ties while Melvin and Arnel lift up the 20mm bars they spliced
yesterday for preparation of the installation. Juvy and Robert is up on the
installation of beam reinforcement along cantilever beam A, 3 rd level of the
tower. While Virgilio fixed the installed beam reinforcements by checking
the necessary extra bars needed. On the other hand, Michael, Angelo,
Jimmy and Rodendo were assigned for the installation of formworks for
columns 600x600mm.

WORK ACCOMPLISHMENT
Installed beam reinforcing bars at beam 1 along grade line A.
Installed 600x600mm column formworks at column 4 at grade line C.
Recycled wood planks to reuse for formworks.
Spliced and bended 20 pcs 20mm diameter bar for beam reinforcement.
Fabricated 10 formworks for 600x600mm columns ½ in. thick phenolic
boards.

August 3, 2023 (Thursday)


A cloudy Thursday morning for workers and trainees, with 14
workers present, 1 steelman, 6 masons and 7 labors. Juvy, Robert and
Dexter installed extra c-bars for beam 1 gradeline B 3 rd level of the tower,
while Virgilio and Angelo installed also extra c-bars for beam 3 gradeline D.
On the other hand, Rodendo, Marlon, Jimmy and John together with
Michael Cuaresma Installed scaffoldings for center beam along gradeline
B-C. Arnel Rosales as steelman, do the work for fabrication of Beam
stirrups 50x70cm.
For the afternoon work is the continuation of installation of beam
reinforcements as well as fabrication of beam stirrups since it is a sunny
afternoon for both the workers and OJT trainees.

WORK ACCOMPLISHMENT
Installed extra c-bars vertical and horizontal at beam 1 along grade line C.
Installed extra c-bars vertical and horizontal at beam 3 along grade line D.
Installed extra c-bars vertical and horizontal at beam 1 along grade line A.
Installed Beam reinforcement for beam 3 along grade line A.

August 4, 2023 (Friday)


It’s a sunny weather on Friday for both workers and OJT trainees,
with the usual call time at 7:30 to 8:00 a.m. the workers and trainees
arrived on site with 14 workers for manpower, 6 masons, 1 steelman and 7
labors.
To make the day a productive one, Melvin started the work by
cutting 10mm diameter bars for the fabrication of beam stirrups for rib
beams of 3rd level of the Landmark tower. Arnel on the other way around
started fabricating the said stirrups. Rodendo and Jimmy the two mason
fabricates also formworks specifically runners for rib beams at 3 rd level of
the tower.
Going up to the 3rd floor of the landmark tower, Virgilio and Argie
fixed the destroyed runners for arc beams while Robert and John, with the
lead of two masons Jimmy and Rodendo prepared and installed the
runners for rib beams at 3rd floor. Marlon, Dexter, Juvy, Angelo, Michael
and Michael John prepared the necessary materials like lifting up Plywoods
to be installed as formworks, installed concrete spacers for beams,
preparing clamps for additional supports scaffoldings and clearing the
unnecessary debris that distracts them to work more efficiently.

WORK ACCOMPLISHMENT
Fabricated 200 x 400mm beam stirrups for rib beam at 3rd floor.
Fabricated 8 pcs. Formworks for rib beam 200 x 400mm at 3rd floor.
Installed 10 runners for rib beam at 3rd floor.
Installed arc runners for 3rd floor beam.
Completely installed scaffoldings for ribbed beam at gradeline B-C
-Installed 10pcs(201x22cm) runners for ribbed beam
-Installed new runner at beam 1 gradeline C (60x277cm), beam 1 gradeline
D (60x210cm),
-installed new runner at rectangular curved beam 1 at gradeline C-D and
rectangular curved beam 1 gradeline A-B
-Installed rock spacer in the beams
-Fabricated 6pcs (201x22cm) runners for ribbed beam
August 5, 2023 (Saturday)
Rodendo, Jimmy, Marlon and Michael start the installation of
ribbed beams while Juvy, Dexter, Angelo, and Michael John, are assisting
by lifting bars and stirrups. While Vergilio, Robert and Argie are replacing
unnecessary installed clamp and scaffolding to reuse. Melvin cut bars while
Arnel fabricating stirrups for ribbed beams.
In the afternoon while continuing the installation of ribbed beams,
they start the installation of beam 3 at gradeline B.

WORK ACCOMPLISHMENTS
Installed 2 ribbed beams (18x35cm)
Installed 1 ribbed beam (25x55cm).
Fabricate 98 pcs stirrups (18x35cm), 49 pcs 10mm bar, 49 pcs 12mm bar.
Fabricated 46 pcs stirrups (25x55cm), 23 pcs 10mm bar, 23 pcs 12mm bar.
Bend 40 pcs splice 20mm x 6mm.
August 7, 2023 (Monday)
Early in the morning at around 7:30 to 8:20 the rain poured but
right after at around 8:21 to 9:53 the rain stops and it’s another cloudy
weather. With only 7 workers for manpower in the area, specifically, 1
steelman, 3 masons and 3 labors.
To start the week and the working day, Virgilio was assigned to help
fabricate and install formworks of Tie beam for extended building at City
Hall. While Melvin, Jimmy, Juvy, Dexter and Argie were left at Landmark
Tower for the continuation of installation of C-bars for beam 2 at grade line
D, beam 1 along grade line C-D and beam 1 along grade line C. In the
afternoon, Arnel arrived at the site for only half day of work. Due to
unpredicted weather condition the four workers were transferred at the
City Hall, Arnel and Melvin left at Landmark Tower for splicing and
fabrication of tie bars for beam. Mr. Juvy and Jimmy assigned to demolish
while, Argie and Dexter are Clearing debris in old health center at City Hall.
And we as trainees are assisting and monitoring the workers if they need
help.

WORK ACCOMPLISHMENT
Installed 3 pcs ribbed beams (18x35cm).
Installed beam 3 at gradeline C.
Fabricated 32 pcs stirrups (18x35cm), 16 pcs 10mm bar, 16 pcs 12mm bar.

August 8, 2023 (Tuesday)


A sunny day from 8:00 am to 5:00 pm for workers and trainees, with 15
workers on site and 4 OJT trainees, 7 masons, 1 steelman and 6 laborers.
Using the newly delivered materials yesterday particularly the phenolic
boards, 2x3 and 2x2 lumbers and the assorted sizes of nails, Rodendo,
Marlon, Jimmy and Mang Dominador, the four masons fabricated
formworks for arc beams at 3rd floor beam while Melvin and Arnel spliced
20mm diameter bars for beam rebars while John prepared the stirrups and
the spliced 20mm bars for installation.
Going up to the 3rd level of the tower, Michael, Michael John, Dexter and
Arnel started installing beam reinforcement for overhang beam 2 along
gradeline A. While Robert, Angelo and Virgilio were assigned for adjusting
the runners for arc beams using a level hose. Argie and Juvy on the other
hand extra C-bars for beam C/3-4.
At 2:20 in the afternoon, Engr. Leo Roxas requested for 20 pieces of 2x2
lumbers which transferred by Dexter, Argie and Michael.

WORK ACCOMPLISHMENT
Completely installed beam reinforcement for beam C-/3-4.
Fabricated 2 arc beams runners for 3rd level.
Spliced and installed 40 pcs of 20mm bars.
Installed beam reinforcement for overhang beam 2 Gade line A.

August 9, 2023 (Wednesday)


A nice sunny Wednesday for both trainees and workers. With the
usual time in of 7:30 to 8:00, 14 workers and 4 OJT trainees arrived at site,
1 steel man which is Arnel Rosales, masons and 7 labors.
To start a productive day, as skilled or mason, Jimmy, Rodendo,
Marlon and Dominador continued the fabrication of formworks for arc
runners. While Melvin and Arnel installed additional scaffolding support
for the extension of formworks for canopy at overhang beam 2and installed
also stairs using scaffoldings as per requested by City engineering for
inspection. Virgilio and Angelo adjusted the elevation and fixed the runners
for beam B-C/1. On the other hand, Michael, Michael John, Juvy, Dexter
and John installed beam reinforcement for overhang beam 3 at grade line
A, while Robert at the same time installed necessary extra bars for installed
beam reinforcement bars.
For the afternoon work is the continuation of morning tasks and
Argie Cuaresma came in for a half day of work.

WORK ACCOMPLISHMENT
Installed completely beam rebars for beam 3 along grade line A.
Fabricated 4 arc runners (manual fabrication).
Fixed and adjusted runner for beam B-C/1.
Installed scaffolding stairs as per requested by City Engineering.
Installed beam reinforcement for beam 3-4 grade line B.
Installed runner for beam B-C along gradeline 4.

August 10, 2023 (Thursday)


The same weather as yesterday, a sunny day for workers: 1
steelman, 7 labors and 7 masons and OJT trainees with a complete number
of workers. Melvin leading the time in, Dominador and Marlon continued
the fabrication of arc beam runners, same with Jimmy, Rodendo and
Michael. While John, Juvy and Michael fixed the scaffoldings prior to the
installation of runner at overhang beam B-C. They also installed necessary
C-bars at overhang beam B and C.
Angelo on the other hand, together with Virgillio, and Dexter installed
extra C-bars and fixed the installed beam reinforcement along beam C-D/2.
Melvin and Arnel continued with their usual work on cutting, and splicing
20mm bars with the help of Robert. Around 9:22 am OJT trainees from
City Hall Building A got 1 pc of 10mm diameter 4m long bar. At 10:24 am
Engr. Vanessa and Engr. Leo visited the site for some inspection.
After the morning break, Arnel led the installation of beam stirrups
at overhang beam 2 gradeline B. At 11:00 am City Engineering visited the
site for inspection of rebars prior to concrete pouring. During the afternoon
work, the labor cleared the debris in the second floor as per ordered by City
Engineering Office.

WORK ACCOMPLISHMENT
Fabricated 2 pcs of arc runners.
Fabricated 2 runners for overhang beam.
Installed runners for overhang beam B.
Installed runners for overhang beam B-C.
Fabricated and installed runners for beam B diagonal cut.
Splice 20mm bars.
Installed extra C-bars at beam C-D/2.
Installed overhang beam reinforcement, beam 2 gradeline D.

August 11, 2023 (Friday)


The weather is cloudy on Friday, 14 workers with 4 OJT trainees, 1
steelman, 7 labors and 6 masons.
Since the delivered 10mm and 12mm bars already approved by
inspectors and lab test, Melvin cut the bars prior to the fabrication of Arnel
for rib beam stirrups. After inspection, Rodendo, Jimmy, with the help of
Michael John installed the last part of column formworks. While Angelo
and Michael Cuaresma continued clearing the debris on the second floor.
With the lead of Mang Virgilio as mason together with Argie and Dexter
installed the arc beams at runners and adjusted the elevation at arc beam
C-D/3-4. Same task for Dominador and Marlon working on the opposite
site of the tower for the adjustment and installation of arc beam runner.
John, Robert and Juvy installed overhang beam reinforcement along
gradeline D beam 3.

WORK ACCOMPLISHMENT
Installed beam reinforcement at overhang beam 3 gradeline D.
Cleare the second floor debris and unnecessary things like used forms,
clamps, scaffolds, wires etc.
Rebar spacer
August 12, 2023 (Saturday)
On this day, the weather is sunny and the workers came in early.
There are 15 workers present: 1 steelman, 1 carpenter, 6 masons, and 7
labors.
Dominador, Virgilio, and Argie continued working on the formworks.
While Rodendo, Jimmy, with the help of Michael John closed off the
formworks for column D-2 and D-3. Melvin, Arnel, Dexter, John, and
Robert started installing beam B-C/4. In addition, installed necessary
reinforcement at 2nd arc beam at gradeline D. Michael and Angelo fixed the
beam reinforcement of arc beam at gradeline A and applied beam and
column spacers for the formworks. Marlon adjusted and fixed the
reinforcement at beam B/2-3 while Juvy worked at the opposite side at
beam C/2-3.

WORK ACCOMPLISHMENTS
Installed formworks for column D-2.
Installed formworks for column D-3.
Installed concrete spacers for beams.
Installed concrete spacers for columns.
Installed beam stirrups for B-C/4 50%.

August 14, 2023 (Monday)


A total of 16 workers and 4 OJT trainees were present on Monday with a
nice sunny day, particularly 1-steelman, 1 carpenter, 5 masons, and labors
including the new one named Armando Santos Jr.
For the final installation of column formworks for both 600x600 and
900x900mm columns, Dominador, Virgilio, Rodendo and Jimmy with the
help of Michael John as labor did the work. For the installation of beam
reinforcement for beam 3-4/B, Argie, Juvy, Marlon and Robert did the
work, while for the installation of rebars for both overhang beams along
gradeline 2 with opposite sides, Arnel, Melvin, Angelo and Armando did
the said work. Michael on the other hand installed concrete spacers for
beams.
At around 9:00 a.m., Engr. Leo Roxas came into the site and requested to
remove all the 10 mm bars column ties of all columns as per order by City
Engineering and change it with 12mm diameter bars instead. So, Arnel and
Melvin continued the cutting and fabrication of 12mm bars for both sizes of
columns while the other workers removed all the installed formworks and
installed 10 mm Column ties. The workers and trainees worked up until
7:00 p.m. considering it as overtime of work.

WORK ACCOMPLISHMENT
Removed 45 pcs 10 mm bars (5 columns) 900x900 mm columns.
Removed formworks for 5 columns 900x900 mm.
Installed 12mm bars column ties for 3 columns (9 pcs each col.)
900x900mm.
Installed concrete spacers for beams.
Fabricated 60 pcs 800x800 stirrups.

August 15, 2023 (Tuesday)


A sunny day from 8:00 am to 5:00 pm for workers and trainees, with 16
workers on site and 4 OJT trainees, 1 carpenter,1 welder, 6 masons, 1
steelman and 7 laborers. As per Engr. Vanessa told the workers to install
diamond column ties using 12mm diameter bars, Arnel Fabricated the said
diamond ties immediately prior to installation of the other workers
particularly for 900x900 mm column size. Jimmy, Rodendo installed also 1
siding formwork at beam A-B/2, While Juvy installed extra c-bars of
beams. Virgilio and Argie came into the site at around 12:30 for a half day
of work to help for the installation of 12mm diameter bars column ties,
some workers including OJT trainees work up until 6:00 p.m. considering
it as overtime of work again.

WORK ACCOMPLISHMENT
Installed 15 pcs of diamond ties 900x900 column A-2
Installed 1 siding formwork beam A-B/2.
Installed spacers for columns 900x900 mm.
Installed 13 pcs of diamond ties 900x900 column B-3.
Installed 14 pcs of diamond ties 900x900 column C-2.
Installed 45 pcs of extra C-bars 10mm for beams.
Fabricated 80 column diamond ties 12mm columns 900x900mm.
Installed diamond ties for column A-3 50% accomplished.
Installed diamond ties for column C-3 50% accomplished.
Installed diamond ties for column B-2 50% accomplished.

August 16, 2023 (Wednesday)


A nice sunny Wednesday for both trainees and workers. With the
usual time in of 7:30 to 8:00, 15 workers and 4 OJT trainees arrived at site,
1 steel man which is Arnel Rosales, 1 carpenter, 1 welder, 4 masons and 7
labors.
To start a productive day, Robert, Marlon and Dexter continued the
installation of diamond ties using 12mm fabricated diamond ties for
column D-3. Melvin removed 10mm columns ties for 600x600 columns
using the welding machine at the same time Michael removed also column
ties 10mm bars at column C-1 600x600mm column. While on the other
hand, Jimmy, Rodendo together with Michael John installed formworks
for columns 900x900 mm.
For the afternoon work is the continuation of morning tasks and
Argie Cuaresma came in for a half day of work.

WORK ACCOMPLISHMENT
Removed 10 mm diamond ties column D-3 900 x 900mm column.
Installed diamond ties 12 mm column D-3 900 x 900mm column.
Removed 10 mm diamond ties column C-1 600 x 600mm column.
Installed 12mm diamond ties column C-1 900 x 900mm column.
Removed 10mm diamond ties for 600 x 600mm columns.
Installed formworks for 900 x 900mm column A-2 (80% done).
Installed formworks for 900 x 900mm column B-2 (80% done).
Installed formworks for 900 x 900mm column C-2 (80% done).

August 17, 2023 (Thursday)


A cloudy Thursday from 8-10 a.m., a good start weather for 15
workers and OJT trainees. 1 steel man, 1 carpenter, 1 welder, 5 masons and
7 labors.
Robert, Dexter, Juvy, and Marlon started the removal of 10mm
columns ties on the 900x900mm column D-2. At the same time, they
began to install 12mm diamond ties. On the other hand, Armando,
Dominador, and Michael continued the installation of formworks for
900x900mm columns.
At around 9:00 a.m., a delivery of materials by Engr. Bianca De
Guaman arrived. Melvin and Arnel continued the fabrication of 12mm bars.
While Michael John, Rodendo, and Jimmy installed the formworks for
9000x900mm columns. Labors Angelo and Argie were tasked to remove
10mm bars at beams.

WORK ACCOMPLISHMENT
Installed formworks for 900 x 900mm column A-3.
Installed formworks for 900 x 900mm column B-3.
Installed formworks for 900 x 900mm column C-3.
Installed formworks for 900 x 900mm column D-3.
Installed column ties for column A-3.
Installed column ties for column B-3.
Installed column ties for column C-3.
Installed column ties for column D-3.

August 18, 2023 (Friday)


The weather is sunny on Friday, with 16 workers and 4 OJT trainees
present on site, 1 usual steel man, 1 carpenter, 1 welder 5 masons and 8
labors. Arnel continued the fabrication of diamond ties using 12mm bars
for 600 x 600mm columns. Jimmy, Rodendo, Michael John and Michael
installed the column formworks for columns D-2 and D-3 both 900 x
900mm columns. While Angelo and Melvin installed rebars for beam C/3-
4. For the installation of diamond ties 600 x 600mm column, Argie, and
Virgilio did the work. The same work but opposite side Marlon and Robert
were there for the task. While Juvy installed necessary C-bars for beam 3-
C.
For the afternoon work is the continuation of installation of column
ties using 12 mm fabricated bars for both column sizes and girders. At
around 2:30 Engr. Vanessa came in to the site for some inspection followed
by Engr. Leo Roxas.
WORK ACCOMPLISHMENT
Installed Column ties using 12mm fabricated bars 600 x 600mm column 1-
B.
Installed Column ties using 12mm fabricated bars 600 x 600mm column 4-
B.
Installed formworks 900 x 900mm column D-3.
Installed formworks 900 x 900mm column D-2.
Installed rebars at beam C/3-4 70% done.
Fabricated 70 column ties for600 x 600mm columns.
Installed column ties 12mm fabricated bars at column 1-C