OJT - FINAL WRITTEN REPORT - Tipon, Angel Rose G.
OJT - FINAL WRITTEN REPORT - Tipon, Angel Rose G.
AUGUST 2023
TABLE OF CONTENTS
COMPANY DATA..................................................................................................I
RECOMMENDATIONS..........................................................................................V
APPENDICES.........................................................................................................VI
PICTURES...........................................................................................................VII
A. Name/Address/Contact No.
Company Name: ROXSAN Construction and Supply
Address: Zone III, Brgy. Pedro T. Orata, Urdaneta City, Pangasinan
Mobile Number: 09175684170 / 09178527824
C. Names of Personnel
Engr. Theodore Emmanuel P. Roxas, RCE – Project Manager
Engr. Vanessa L. Garcia – Site Engineer
Mr. Melvin Sarmiento -- Leadman
BRIEF HISTORY AND BACKGROUND OF THE COMPANY
ROXSAN Construction and Supply is located in Zone III, Brgy. Pedro T. Orata,
Urdaneta City, Pangasinan. It was founded in the year 1990. The current president and
owner of this company is Engr. Theodore Emmanuel P. Roxas.
MISSION:
To create positive solutions through creative excellence by continuously delivering
the highest quality service to our clients and partners.
VISION:
To become efficient in planning, designing, and creating a sustainable environment
for everyone.
VALUES:
Creative. Commitment. Innovation. Teamwork. Safety. It is about the continuing
drive and goal of the company to institutionalize the values and infuse them into its culture.
II
BRIEF DESCRIPTION
OF THE
TRAINING PROGRAM
BRIEF DESCRIPTION OF THE TRAINING PROGRAM
The program gave students a hands-on method for learning new abilities and skills
required for a career in a real working environment, and it also gave interns a sense of the
duty and accountability of an engineer. The objectives that would steer the course from the
beginning to the finish were discussed at the outset of the training.
I. Objective:
1. General
Having the necessary background knowledge to learn new skills and
knowledge in a practical way before beginning the internship. It is essential
to put the academic theory you have studied to use in the real world of
employment. must have the ability to develop or build future high-quality
infrastructure
2. Specific
to become proficient in managing construction sites according to safety
standards and to become familiar with the various stages of construction. To
be able to receive partial training in order to gain experience with real-world
office/technical operations during the training time, to be ready to handle the
demands and challenges of employment, and to build positive work habits,
attitudes, and an appreciation for and respect for work.
1. Significant Achievements
I picked up a few technical skills during my training that helped me become more
self-aware and acquainted with the workplace in my chosen sector of expertise. In
addition, we helped with finishing jobs including installing stirrups for columns and
beams and cutting wire for ties.
2. Technical skills and new technology learned
Throughout my site monitoring, I learned about and gained experience with the
technical aspects of each distinct scope of work. Additionally, during our site visits
to the other sites, we noticed how workers constructed footing and concrete
pouring. Additionally, we learned in actual the estimation of phenolic boards,
lumbers, and steel decks that would be used
3. Equipment, machinery, testing apparatus, etc., handled
I had the chance to use a steel cutter, a masonry trowel, and pliers during my
training. In addition, I witnessed how a concrete mixer and backhoe were used in
actual construction.
4. Experiences with the company personnel involved in the training
During my training period, I received a great deal of knowledge from the site
engineer, foreman, skilled workers, and even laborers as I attended my on-the-job
training in the office and on-site. All of them were eager to share their expertise on
the working procedures and details with us and were able to respond to our
inquiries about their jobs.
5. Strong points
One of the strengths of the training program is that it gives students the chance to
interact with and learn about the actual work that is done in their chosen area of
expertise, as well as to acquire knowledge that they can use in the future.
6. Weak points and suggested solutions
One thing that concerned me and was considered the company’s weak point was the
inability to prioritize site inspection and supervision on the project.
V
RECOMMENDATIONS
RECOMMENDATIONS
MANPOWER SCHEDULE
MANPOWER NO.
STEEL MAN 1
CARPENTER 1
WELDER 1
MASON 3
Jr. MASON 2
LABOR 8
TOTAL 16
EQUIPMENT
NARRATIVE REPORT
On our first day, July 17, 2023, of our on-the-job training at the
construction of Landmark Tower of Urdaneta City, Province of Pangasinan,
it was cloudy and rainy. Engr. Leo has instructed us to start supervising our
designated sites. There were four trainees at the Landmark tower on our
first day. There were two workers present: Arnel Rosales and Melvin
Sarmiento. They started to cut 10mm and 12mm steel bars and formed into
lateral ties the size of 90cm x 90cm. Since it was our first day we looked
around and checked the measurements of columns and steel.
In the afternoon, Engr. Leo visited the site at 2:15 pm. He instructed us on
what to do and what not to do on the site to ensure quality results. We also
began to cut steel wires to be used as ties. It was not raining as heavily as it
was in the morning. At the end of the day about 70 pieces of lateral ties
were finished.
On July 18th, before 7:30 in the morning, employees and trainees
arrive in full PPE. The weather was sunny and additional workers were
assigned to the tower. There were also two additional trainees who joined
from the other site in Bactad. Workers started cutting steel bars, bending
steel bars for lateral ties, cutting steel wires for ties, and installing lateral
ties in the columns.
In the afternoon, around 2:14pm Engr. Leo called and requested extra
hands for their project. Therefore, seven workers from our site were
transferred to the project in the City Hall. We trainees were assigned to
monitor and help the workers with what they need. The cutting and
bending of steel bars continued throughout the day.
On day 3, July 19, 2023, it was still sunny, and more workers have
arrived ( to speed up the progress at the Landmark Tower. At 7:30 am they
started doing their work. We we’re divided into teams of two. Three people
on the second floor, supervising works in progress. The workers have
started to put formworks to be used for concrete. Then the other three
stayed on the ground floor to help make ties for the bars. The ties were for
different diameters of steel. Therefore, the cuts were a variation of lengths.
After our break, the workers immediately went back to work. At 11:26 am a
worker was tasked to get one 9mx16mm diameter deformed bar.
In the afternoon at 2:10 pm UCU instructor, Engr. Edsel A. Balbera, visited
the site and assessed the trainees on their ongoing project. At 3:22 pm, the
rain started to pour. We continued to make ties with steel wires.
On July 20, 2023, the fourth day of our on-the-job training,
employees and trainees arrived at the customary hour of 7:30 am. Because
it was a wonderful sunny day, Rodendo, Jimmy, and Argie just proceeded
installing formwork for two additional 900 x 900 mm columns. While
Melvin and Arnel continued to make column ties, Marlon and John
continued to install lateral ties that were the same size as the mentioned
column. 9:30 am or so, Engr. Vanessa visited the site and inquired about
the materials required for the job, Argie requests some nails to be used for
installing the formwork, and Melvin requests cutting discs for cutting the
bars.
During the afternoon work, together with Virgilio, who arrived at the site
for only a half-day of work, Marlon and John began placing lateral ties for
two columns during the afternoon shift. When it was about 4:30 p.m.,
Engr. Leo Roxas paid a visit to the location and requested our reports as
trainees stationed there.
Friday, July 21, 2023, the fifth day of work for the construction of
Landmark Tower. Foreman Orlando Manangan entered the site together
with 3 new labors namely, Michael Cuaresma, Angelo Zamora and Robert
Dumasin for additional manpower. Marlon, John, Dexter and Virgilio as
well as Juvy continued installing Column ties for 900 x 900 mm mm ties.
On the other hand, Rodendo installed spacers for columns to start
installation of formworks again and at the same time Argie and Jimmy
prepared the formworks and scaffoldings to be use. Engr. Vanessa Garcia
visited and delivered the requested materials such as nails and cutting discs
at 9:24. Angelo, Michael, Robert the 3 new labors together with Melvin
installing 3rd level Beam reinforcement along Gradeline of column A.
WORK ACCOMPLISHMENTS
Fabricated and cut 5 phenolic boards ¾”
Continuation at beam A
Installed 72 c-bars 10mm bar
Installed 48 pcs 70 cm vertical c-bars
Installed 24 pcs 50 cm horizontal c-bars
Beam B finished installation
Installed 45 column ties 70x50 cm
Installed 23 pcs 12 mm bars and 22 pcs 10 mm bars
Installed 3 column formworks 900x900 column
Finished column ties of 600x600 column
Beam C started to install
July 24, 2023 (Monday)
Early in the morning Engr. Vanessa Garcia visited for some
inspection at around 7:58 a.m. Engr. Vanessa checked the site's daily time
record. Rodendo leads for the construction of formwork installation for the
last 2 remaining 900x900mm columns together with Michael and Jimmy.
While Argie, Arnel, Virgilio and Michael John started installing beam
reinforcement at beam D, 3rd level of the building. On the other hand,
Marlon, Juvy and Dexter prepared the bars to be installed in beam D,
Robert and John helps to lift bars for the installation of the beam
reinforcement.
Arnel and Jayson and Robert started the installation of beam
reinforcement along beam B2-C2, 3rd level, Arnel and Melvin bended
20mm bars for main bars. Arnel continued fabricating stirrups in the
afternoon, while Rodendo and Jimmy fabricates formworks for columns at
the same time.
WORK ACCOMPLISHMENT
Fabricated 9 formworks 900x900 columns
Installed beam D 3rd level
Installed 2 column formworks 900 x 900 columns
Installed 2 beams along B-C 3rd level
Fabricated beam stirrups – 31 pcs 10 mm and 36 pcs 12 mm
Fabricated C bar 84 cm – 70 pcs 10 mm
Fabricated C bar 64 cm – 31 pcs 10 mm
Afternoon work, Arnel and Melvin bends 20mm bars for tension bars of
beam and the same time Jimmy and Rodendo fabricated formworks for
600x600mm column. While the others continued the installation of beam
reinforcement.
WORK ACCOMPLISHMENT
Fabricated 4 formworks for 600 x 600 mm columns
Bend 40 pcs 20 mm bar – 7.5 meter long
Installed 2 beam reinforcement
Fabricated 55 stirrups for beam 12 mm
Fabricated 68 stirrups for beam 10 mm
WORK ACCOMPLISHMENT
Fabricated 100 pcs beam stirrups (12mm)
Fabricated 100 pcs beam stirrups (10mm)
Fabricated 140 pcs C bar for beam (10mm)
July 28, 2022 (Friday)
It’s a rainy Friday, Melvin and Arnel still let at the landmark tower
for the continuous fabrication of the beam stirrups and column ties. While
the others went to the city hall to continue demolish the old city health
center. Particularly, Juvy, Argie and John help the other workers for
concrete pouring of foundation and installation of column reinforcement
for the extension of the birthing facility.
WORK ACCOMPLISHMENT
Fabricated 40 pcs 12 mm bar
Fabricated 10 pcs 10 mm bar
Bend 40 pcs 20 mm bar
July 29, 2023 (Saturday)
It’s a cloudy Saturday, with 15 workers present on the site, 1
steelman, 6 masons, and 8 labors, and since it is not raining in the area, the
workers fixed the rebars of beams installed in 3 rd level of the tower by
installing the necessary extra bars, at the same time Jimmy and Rodendo
the two masons with the help of Michael as labor installed formworks for
600x600 mm columns.
During the afternoon, the rain was continuously pouring which
started at around 12:30 up until 1:28 the workers transferred to the old city
health center as per Engr. Juster Ballesteros order. Particularly, Virgilio,
Rodendo, Jimmy, Marlon, John, Robert and Angelo assigned to demolish
the old city health center while Michael, Jayson, Michael John and Dexter
were assigned for site clearing, Juvy assigned for the installation of column
reinforcement while were assigned to help for concrete pouring of the
column foundation.
WORK ACCOMPLISHMENTS
Installed 2 formworks for columns 600x600mm column 1 along grade line
B and C.
Installed beam reinforcement for beam 1 along grade line C.
Site clearing Old City Hall building B 3rd and 4th floor.
Demolition of old city health center.
Helped to install column ties for extension of Birthing Home.
WORK ACCOMPLISHMENT
Installed extra C-bars for beam 2 along gradeline D.
Installed extra C-bars for beam 1 along gradeline C-D.
Installed extra C-bars for beam 1 along gradeline D.
Helped to install and fabricate formworks for tie beam (Old city health
center).
Spliced 20 pcs. 20mm diameter bars for beam reinforcement.
August 1, 2023 (Tuesday)
It’s a cloudy Tuesday for the first day of the month, August 1, 2023, with 13
members of manpower, 1 steelman, 6 masons and 6 labors. Jimmy and
Rodendo, the two mason started the day by fabricating formworks for
600x600mm columns using ½ inch thick phenolic boards. Marlon,
Michael John, Dexter and John started installing beam reinforcement
along gradeline C-D 3rd level of the tower.
On the other hand, Melvin together with Arnel installed reinforcement bars
for beam B while Juvy with the help of Robert Dumasin installed extra c-
bars for beam A-B/2 the same work with Virgilio and Argie with the
installation of extra c-bars for beam along A-B/4.
WORK ACCOMPLISHMENT
Fabricated 10 formworks for 600 x 600mm columns ½ thick phenolic
board
Installed beam reinforcement along gradeline C-D 80% done.
Installed beam reinforcing bars along beam B.
Installed extra c-bars vertical ang horizontal along beam A-B/2.
Installed extra c-bars vertical ang horizontal along beam A-B/4.
WORK ACCOMPLISHMENT
Installed beam reinforcing bars at beam 1 along grade line A.
Installed 600x600mm column formworks at column 4 at grade line C.
Recycled wood planks to reuse for formworks.
Spliced and bended 20 pcs 20mm diameter bar for beam reinforcement.
Fabricated 10 formworks for 600x600mm columns ½ in. thick phenolic
boards.
WORK ACCOMPLISHMENT
Installed extra c-bars vertical and horizontal at beam 1 along grade line C.
Installed extra c-bars vertical and horizontal at beam 3 along grade line D.
Installed extra c-bars vertical and horizontal at beam 1 along grade line A.
Installed Beam reinforcement for beam 3 along grade line A.
WORK ACCOMPLISHMENT
Fabricated 200 x 400mm beam stirrups for rib beam at 3rd floor.
Fabricated 8 pcs. Formworks for rib beam 200 x 400mm at 3rd floor.
Installed 10 runners for rib beam at 3rd floor.
Installed arc runners for 3rd floor beam.
Completely installed scaffoldings for ribbed beam at gradeline B-C
-Installed 10pcs(201x22cm) runners for ribbed beam
-Installed new runner at beam 1 gradeline C (60x277cm), beam 1 gradeline
D (60x210cm),
-installed new runner at rectangular curved beam 1 at gradeline C-D and
rectangular curved beam 1 gradeline A-B
-Installed rock spacer in the beams
-Fabricated 6pcs (201x22cm) runners for ribbed beam
August 5, 2023 (Saturday)
Rodendo, Jimmy, Marlon and Michael start the installation of
ribbed beams while Juvy, Dexter, Angelo, and Michael John, are assisting
by lifting bars and stirrups. While Vergilio, Robert and Argie are replacing
unnecessary installed clamp and scaffolding to reuse. Melvin cut bars while
Arnel fabricating stirrups for ribbed beams.
In the afternoon while continuing the installation of ribbed beams,
they start the installation of beam 3 at gradeline B.
WORK ACCOMPLISHMENTS
Installed 2 ribbed beams (18x35cm)
Installed 1 ribbed beam (25x55cm).
Fabricate 98 pcs stirrups (18x35cm), 49 pcs 10mm bar, 49 pcs 12mm bar.
Fabricated 46 pcs stirrups (25x55cm), 23 pcs 10mm bar, 23 pcs 12mm bar.
Bend 40 pcs splice 20mm x 6mm.
August 7, 2023 (Monday)
Early in the morning at around 7:30 to 8:20 the rain poured but
right after at around 8:21 to 9:53 the rain stops and it’s another cloudy
weather. With only 7 workers for manpower in the area, specifically, 1
steelman, 3 masons and 3 labors.
To start the week and the working day, Virgilio was assigned to help
fabricate and install formworks of Tie beam for extended building at City
Hall. While Melvin, Jimmy, Juvy, Dexter and Argie were left at Landmark
Tower for the continuation of installation of C-bars for beam 2 at grade line
D, beam 1 along grade line C-D and beam 1 along grade line C. In the
afternoon, Arnel arrived at the site for only half day of work. Due to
unpredicted weather condition the four workers were transferred at the
City Hall, Arnel and Melvin left at Landmark Tower for splicing and
fabrication of tie bars for beam. Mr. Juvy and Jimmy assigned to demolish
while, Argie and Dexter are Clearing debris in old health center at City Hall.
And we as trainees are assisting and monitoring the workers if they need
help.
WORK ACCOMPLISHMENT
Installed 3 pcs ribbed beams (18x35cm).
Installed beam 3 at gradeline C.
Fabricated 32 pcs stirrups (18x35cm), 16 pcs 10mm bar, 16 pcs 12mm bar.
WORK ACCOMPLISHMENT
Completely installed beam reinforcement for beam C-/3-4.
Fabricated 2 arc beams runners for 3rd level.
Spliced and installed 40 pcs of 20mm bars.
Installed beam reinforcement for overhang beam 2 Gade line A.
WORK ACCOMPLISHMENT
Installed completely beam rebars for beam 3 along grade line A.
Fabricated 4 arc runners (manual fabrication).
Fixed and adjusted runner for beam B-C/1.
Installed scaffolding stairs as per requested by City Engineering.
Installed beam reinforcement for beam 3-4 grade line B.
Installed runner for beam B-C along gradeline 4.
WORK ACCOMPLISHMENT
Fabricated 2 pcs of arc runners.
Fabricated 2 runners for overhang beam.
Installed runners for overhang beam B.
Installed runners for overhang beam B-C.
Fabricated and installed runners for beam B diagonal cut.
Splice 20mm bars.
Installed extra C-bars at beam C-D/2.
Installed overhang beam reinforcement, beam 2 gradeline D.
WORK ACCOMPLISHMENT
Installed beam reinforcement at overhang beam 3 gradeline D.
Cleare the second floor debris and unnecessary things like used forms,
clamps, scaffolds, wires etc.
Rebar spacer
August 12, 2023 (Saturday)
On this day, the weather is sunny and the workers came in early.
There are 15 workers present: 1 steelman, 1 carpenter, 6 masons, and 7
labors.
Dominador, Virgilio, and Argie continued working on the formworks.
While Rodendo, Jimmy, with the help of Michael John closed off the
formworks for column D-2 and D-3. Melvin, Arnel, Dexter, John, and
Robert started installing beam B-C/4. In addition, installed necessary
reinforcement at 2nd arc beam at gradeline D. Michael and Angelo fixed the
beam reinforcement of arc beam at gradeline A and applied beam and
column spacers for the formworks. Marlon adjusted and fixed the
reinforcement at beam B/2-3 while Juvy worked at the opposite side at
beam C/2-3.
WORK ACCOMPLISHMENTS
Installed formworks for column D-2.
Installed formworks for column D-3.
Installed concrete spacers for beams.
Installed concrete spacers for columns.
Installed beam stirrups for B-C/4 50%.
WORK ACCOMPLISHMENT
Removed 45 pcs 10 mm bars (5 columns) 900x900 mm columns.
Removed formworks for 5 columns 900x900 mm.
Installed 12mm bars column ties for 3 columns (9 pcs each col.)
900x900mm.
Installed concrete spacers for beams.
Fabricated 60 pcs 800x800 stirrups.
WORK ACCOMPLISHMENT
Installed 15 pcs of diamond ties 900x900 column A-2
Installed 1 siding formwork beam A-B/2.
Installed spacers for columns 900x900 mm.
Installed 13 pcs of diamond ties 900x900 column B-3.
Installed 14 pcs of diamond ties 900x900 column C-2.
Installed 45 pcs of extra C-bars 10mm for beams.
Fabricated 80 column diamond ties 12mm columns 900x900mm.
Installed diamond ties for column A-3 50% accomplished.
Installed diamond ties for column C-3 50% accomplished.
Installed diamond ties for column B-2 50% accomplished.
WORK ACCOMPLISHMENT
Removed 10 mm diamond ties column D-3 900 x 900mm column.
Installed diamond ties 12 mm column D-3 900 x 900mm column.
Removed 10 mm diamond ties column C-1 600 x 600mm column.
Installed 12mm diamond ties column C-1 900 x 900mm column.
Removed 10mm diamond ties for 600 x 600mm columns.
Installed formworks for 900 x 900mm column A-2 (80% done).
Installed formworks for 900 x 900mm column B-2 (80% done).
Installed formworks for 900 x 900mm column C-2 (80% done).
WORK ACCOMPLISHMENT
Installed formworks for 900 x 900mm column A-3.
Installed formworks for 900 x 900mm column B-3.
Installed formworks for 900 x 900mm column C-3.
Installed formworks for 900 x 900mm column D-3.
Installed column ties for column A-3.
Installed column ties for column B-3.
Installed column ties for column C-3.
Installed column ties for column D-3.