Professional Documents
Culture Documents
Method Statement For Installation of CCTV Video Surveillance System
Method Statement For Installation of CCTV Video Surveillance System
Method Statement For Installation of CCTV Video Surveillance System
:
METHOD STATEMENT FOR REV. No.
Date :
Video surveillance system (CCTV) Installation
Page 1 of 13
REVISION RECORD
This cover page is a record of all revisions of the document identified above by number and title. All previous cover pages are
hereby superseded and are to be destroyed.
CONTENTS
1.0 PURPOSE
2.0 SCOPE
3.0 REFERENCES
4.0 DEFINITIONS
5.0 RESPONSIBILITIES
6.0 EQUIPMENT
7.0 PROCEDURE
8.0 ATTACHMENTS
TITLE Ref. No. :
METHOD STATEMENT FOR REV. No.
Date :
Video surveillance system (CCTV) Installation
Page 4 of 13
1.0 PURPOSE
- This Installation method statement covers the Guidance of Installation of CCTV System which will
installed in in accordance with the approved project quality plan and relevant system specification.
It is compiled by the specialist supplier and is extracted from their manuals for the installation of
the system.
- Supplier will depute an experienced commissioning engineer to thoroughly inspect the installation
prior to commissioning.
1.1 Installer Engineer will carry out the supply, Installation, Testing and Commissioning of the CCTV system
along and under supervision of the sub-contractor.
2.0 SCOPE
3.0 REFERENCE
4.0 DEFINITIONS:
5.0 RESPONSIBILITIES:
Responsibilities for ensuring that the steps in this procedure shall be carried out are specified at relevant
steps in the procedure:
- Project Manager.
- Construction manager
- QA/QC Engineer
- Site Engineer
- HSE officer
- SK
- Tecnician
5.1 Project Manager
- Project Manager is the overall responsible for the project in terms of work execution, safety, planning &
quality. The Project Manager will maintain the planning progress and coordination of works with the
main contractor.
- The work progress shall be carried out as per planned program and all the equipment’s required to
execute the works shall be available and in good condition as per project planned.
- Specific attention is paid to all safety measures and quality control in coordination with Safety
Engineer and QA/QC Engineer and in line with PSP and PQP.
- The method of statement to the system shall be implemented according to the Consultant project
TITLE Ref. No. :
METHOD STATEMENT FOR REV. No.
Date :
Video surveillance system (CCTV) Installation
Page 6 of 13
- The monitoring of executions of works at site and should be as per the approved shop drawings and
project specifications.
- Ensure WIRs and MIRs are being raised for activities in timely manner and inspected by the
Consultant.
- Check and insure that all activities / work done / completed prior to offer for consultant inspection.
- He will follow and carried out all the relevant tests as per project specifications.
- Obtain the required clearance prior to Consultant’s inspections.
- Should acquire any necessary civil works clearances and coordination.
- Coordinate with site construction team.
- One who will assist the Consultant Engineer / Inspector during inspection.
- The carrying-out of work and the proper distribution of all the available resources in coordination
with the Site Engineer on a daily basis.
- Daily reports of the works are achieved and coordinated for the future planning with the Site
Engineer.
- Incorporate all the QA/QC and Safety requirements as requested by the concerned Engineer.
- Meeting with any type of unforeseen incident or requirement and reporting the same to the Site
Engineer immediately.
- The implementation of all safety measures in accordance with the HSE plan and that the whole work
TITLE Ref. No. :
METHOD STATEMENT FOR REV. No.
Date :
Video surveillance system (CCTV) Installation
Page 7 of 13
- Responsible for overall Store operations in making sure to store the material delivery to the site and
keep it in suitable area that will keep the material in safe from rusty and damage.
- One who will acknowledge the receiving of materials at site in coordination with QA/QC and
concerned Engineer.
5.8 Technician
- The carrying-out of work and the proper distribution of all the available resources in coordination
with the sub-contractor Site Engineer on a daily basis.
- Daily reports of the works are achieved and coordinated for the future planning with the Site
Engineer.
- Complying with the sub-contractor basic design practices, particularly those related to safety and
engineering
- Meeting with any type of unforeseen incident or requirement and reporting the same to the Site
Engineer immediately.
6.0 EQUIPMENTS
Ferules and ferruling tool for dressing the ends of cables (if stranded conductors are used),
Pulling Spring
Hammer
Measuring Wheel.
Drilling tools.
Ladders.
Scaffolding (to be provided by the contractor for the High level Area).
Safety requirements tools such as safety shoes, safety helmet, safety glasses, fluorescent vest,
and safety gloves to insure maximum ability of safe work and dust mask when required.
7.0 PROCEDURE
Any discrepancies, damage etc., found will be notified and reported for further action.
Site Engineer has to ensure that all delivered material used at site are of free from any damage or
deformity of any kind. Any minor damages observed shall be repaired suitably and in case if the
repairs could not be done properly, the panel boards are to be sent to assembler for rectification, after
all formalities carried on.
- Civil Clearance before start the installation of the CCTV system (Cameras & Panels).
- Check that all conduits for the Data of the camera installed as per approved shop drawings.
- Check that all panels installed as per manufacturer recommendations and all wires Identified.
- Check that the CCTV system and its Accessories approved as per material submittal.
- Check that the location of the camera/ panels and the position set as per approved shop drawings and
manufacturer recommendations.
- Check that the Installed Camera is the correct type other (PTZ or Dome type).
- Al specific CCTV camera locations shall be selected to provide a view of the maximum amount of
space.
- Refer to relevant CCTV drawing layouts and schematic diagrams for all active and passive
components provided in this section for exact location and details of integration with other sub-
systems.
- Check that Integration between the camera and the Access control system done as per approved
schematic diagram and manufacturer recommendations.
- Check that the cameras setting and programmed as per project requirements and manufacturer
recommendations.
- Install cables in raceways and cable trays except within consoles, back boxes, desks, and counters.
Conceal raceway and cables except in unfinished spaces.
- Using CAT-6A type cable the maximum length of the cable not exceeds more than 90 mtrs. Of
manufacturer recommendation, which will provided from structural cabling system supplier.
- Comply with requirements for raceways and boxes specified in Division 26 Section "Raceways,
Boxes, Cable Tray, Cable Ladder and Trunking".
- Conceal conductors and cables in accessible ceilings, walls, and floors where possible.
- Bundle, lace, and train cables within enclosures. Connect to terminal points with no excess and
without exceeding manufacturer's limitations on bending radius.
TITLE Ref. No. :
METHOD STATEMENT FOR REV. No.
Date :
Video surveillance system (CCTV) Installation
Page 10 of 13
C.Grounding
- Comply with requirements in Division 26 Section "Grounding and Bonding for Electrical Systems."
for grounding conductors and connectors.
- Comply with ADDC Electricity Wiring Regulations, Section 5, and 6.
- Bond metallic equipment to the system grounding bus bar, using not smaller than the specified
equipment grounding conductor by ADDC Electricity Wiring Regulations, Section 5 and 6.
D.Identification
- Identify system components, wiring, and cabling complying with ADDC Electricity Wiring
Regulations. Comply with requirements for identification specified in Division 26 Section
"Identification for Electrical Systems."
1. Label each cable within 4 inches (100 mm) of each termination and tap, where it is accessible in a
cabinet or junction or outlet box, and elsewhere as indicated.
2. Exposed Cables and Cables in Cable Trays and Wire Troughs: Label each cable at intervals not
exceeding 15 feet (4.5 m).
3. Label each terminal strip and screw terminal in each cabinet, or consoles.
4. Individually number wiring conductors connected to terminal strips and identifies each cable or
wiring group being extended from a cabinet or console to a building-mounted device with name and
number of particular device as shown on the drawing.
- WIR to be provided for Inspection after making sure that all Installation done correctly and
check by Electrical Engineer & QA/QC Engineer.
- After making sure all the system installed in correct way from Subcontractor and supplier,
programming of the system must take place before final testing and commissioning
accourding to Consultant requirement and senario of the system.
- Testing and commissioning of the system submitted separetly for this system mentioned all the
procedure of Testing of the system and commissioning it.
8.0 ATTACHMENTS