DAILY REPORT

Project : Installation Equipment Machince Cutter Fujimaki Day : Friday


Location : PT Dayasa Aria Prima, Driyorejo, Kabupaten Gresik, Jawa Timur 61177 Date : November 3rd, 2023
Contractor : PT. ERATAMA DAYA KONSTRUKSI Hours : 08.00 - 16.00
P/O No. :-

MANPOWER DESCRIPTION WORK & LOCATION VOLUME PROGRESS


I. MANAGEMENT
Site Manager : Yopi Gunawan 1 Dismantle and Moving PM 1
PIC : Muhammad Rozaq 1 I. Moving
Safety Offiver : Eko Mulyadi 1 1. Moving DC Fujimaki Part 15 unit 100%
Supervisor : Syaiful R. 1 2. Moving Pulper Machine Part 2 unit 100%

Setting
Sub Total I 4 I. Setting
II. DIRECT 1. Continue Adjsting Soleplate 2 unit 100%
Construction : II. Installation
Abdul Kasib M. 1 1. Repair Rail Track 2 unit 50%
Al. Amin 1 2. Repair Fujimaki Part 4 unit 100%
Aryanto 1
Ahmad Rizki 1
Sukardi 1
Dwi Bagus S. 1
Sabidun 1
Heri Sumanto 1
Randik Yulianto 1
Adi Winarto 1
Edi Hari W. 1

PROBLEM
---

SOLUTION
---
Sub Total II 11
Total Man Power 15
Material Unit Qty Tools Unit Qty Tool Unit Qty
Oxygen Cylinder Unit 1 Cutter Grinding Set 1 Autolevel Set 1
Gas Cylinder Unit 1 Cutting Torch set 1
Wrench set 1
Welding Machine Set 1
Apar Unit 1
Rai Note :
Referensi (Drawing/Information) : Weather Bright Cloudy
n Material for Support and Anchor isnt ready yet
Morning ✔
Midday ✔
Afternoon ✔
Night
Prepared By, Approved By,

Muhammad Rozaq Yopi Gunawan


DOCUMENTATION DAILY REPORT

Project : Installation Equipment Machince Cutter Fujimaki Day : Friday


Location : PT Dayasa Aria Prima Driyorejo, Kabupaten Gresik, Jawa Timur 61177 Date : November 3rd, 2023
Contractor : PT. ERATAMA DAYA KONSTRUKSI Hours : 08.00 - 16.00
P/O No. :-

1. Daily TBM all team PT. ERATAMA DAYA KONSTRUKSI

2. Setting

3. Moving

4. Installing
MASTER SCHEDULE (03-11-23)
PROJECT : Installation Equipment Machine Cutter Fujimaki
P/O No. : -
VENDOR : PT. ERATAMA DAYA KONSTRUKSI
October 2023 until December 2023
PROGRESS Oct-23 Nov-23 Dec-23
NO DESCRIPTION QTY UNIT Weight
ACTIVITIES (%) W01 W02 W03 W04 W05 W06 W07 W08 W09 W10 W11 W12 W12
2-8 9-15 16-22 23-28 30-5 6-12 13-19 20-26 27-03 4-10 11-17 18-24 25-31
1,0

1 Installation
1 lot 0,256 Actual 28,00 0,014 0,014 0,014 0,014 0,014
1.1 Installation All Equipment Machine Cutter Fujimaki
Plan 12,50 0,032 0,032 0,032 0,032 0,032 0,032 0,032 0,032

1 lot 0,009 Actual 55,00 0,001 0,001 0,001 0,001 0,001


1.2 Dismantle and Installation Rail Track 2 Unit
Plan 55,00 0,001 0,001 0,001 0,001 0,001 0,001 0,001 0,001

1 lot 0,060 Actual 10,00 0,005 0,001


1.3 Installation Panel Box
Plan 12,50 0,007 0,007 0,007 0,007 0,007 0,007 0,007 0,007

1 lot 0,060 Actual 45,00 0,005 0,005 0,005 0,005 0,005


1.4 Allignment Sole Plate C/w Report
Plan 62,50 0,007 0,007 0,007 0,007 0,007 0,007 0,007 0,007

1 lot 0,026 Actual 0,00


1.5 Allignment C/w Report
Plan - 0,006 0,006 0,006 0,006

1 lot 0,043 Actual 0,00


1.6 Repainting Frame Machine "Nippon - Putih Tulang"
Plan - 0,043

1 lot 0,000 Actual #DIV/0!


1.7 Replace Seal Air Cylinder (27 pcs)
Plan #DIV/0!
1 lot 0,000 Actual #DIV/0!
1.8 Replace Seal Hydraulic Cylinder
Plan #DIV/0!
1 lot 0,043 Actual 0,00
1.9 Installation Piping Air Compressor And Hydraulic
Plan 12,50 0,005 0,005 0,005 0,005 0,005 0,005 0,005 0,005

1 lot 0,000 Actual #DIV/0!


1.10 Bolt & Nut - HTB 8.8 C/w Washer
Plan #DIV/0!

Relocate Broke Trik C/w Installation Ductiong Blower 1 lot 0,281 Actual 33,00 0,019 0,019 0,019 0,019 0,019
1.11
Cutter Plan 47,50 0,028 0,028 0,028 0,028 0,021 0,021 0,021 0,021 0,021 0,021 0,021 0,021

1 lot 0,045 Actual 38,46 0,003 0,003 0,003 0,003 0,003


1.12 Safety & Scaffolding
Plan 38,46 0,003 0,003 0,003 0,003 0,003 0,003 0,003 0,003 0,003 0,003 0,003 0,003 0,003

1 lot 0,162 Actual 41,67 0,013 0,013 0,013 0,013 0,013


1.13 Tool Set
Plan 41,67 0,013 0,013 0,013 0,013 0,013 0,013 0,013 0,013 0,013 0,013 0,013 0,013

1 lot 0,017 Actual 0,00


1.14 Commissioning Test
Plan - 0,017

GRAND TOTAL 1,0


CUM. ACTUAL 5,61 11,23 16,84 22,97 28,67 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00

CUM. PLAN 5,33 10,67 16,00 21,34 30,50 39,66 48,82 57,98 66,90 75,83 84,75 97,95 100,00

VARIANCE 0,28 0,56 0,84 1,63 -1,83 -39,66 -48,82 -57,98 -66,90 -75,83 -84,75 -97,95 -100,0

Diperiksa Oleh,
PT. ERATAMA DAYA KONSTRUKSI