Temporary Backfill Log

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 2

Project Title: Jafurah Gas Compression Plants (GCPs) and Produced Wat

GCP1- 769-PR-16B
Temporary Work Details
SI No. LOCATION DESCRIPTION OF ACTIVITY Referen

Use of un approved material details for temporary


230 KV GIS SS47(769-
access for crane movement to install precast
B-6930B) at GCP1
elements at Around the GIS Building

1 Approved Highlighted drawing

Use of un approved material details for temporary


access for crane and manlift movement to install
2 769-PR-16B structural steel at PR-16B Approved Highlighted drawing

Use of un approved material details for temporary


access for crane and manlift movement to install
3 769-PR-003B structural steel at PR-003B Approved Highlighted drawing

Use of un approved material details for temporary


access for crane and manlift movement to install
4 769-D-3053 A/B structural steel at FIRE WATER TANK 769-D-3053 A/B Approved Highlighted drawing
CPs) and Produced Water Injection Station (PWIS) (Package-1)
CP1- 769-PR-16B
orary Work Details
Reference Document Remarks

proved Highlighted drawing and Survey report, signed by SAPMT

proved Highlighted drawing and Survey report, signed by SAPMT

proved Highlighted drawing and Survey report, signed by SAPMT

proved Highlighted drawing and Survey report, signed by SAPMT