Professional Documents
Culture Documents
Reactor - For Switchayrd
Reactor - For Switchayrd
Reactor - For Switchayrd
CLIENT : M/s.
PROJECT : Sheet No 1 of 10
2. Equipment Details :
LOA No :
Make :
Type :
Rating :
Sl. No. :
Voltage Class :
Cooling Type :
Type of neutral grounding :
Year of Manufacture :
1 Reactor and its auxiliaries are free from visible defects on physical inspection
2 All fittings as per our line general arrangement drawing
3 Check main tank has been provided with earthing
4 Check neutral I s grounding
5 Check tightness of terminal connectors
6 Bushings are clean and free from physical damages
7 Oil level is correct on all bushings
8 Check hermetically sealing is intact in all bushings
9 Check oil level in main tank and conservator tank
10 Check OTI and WTI pockets and replenish the oil, if required
11 Check the color of breaker silica gel (blue when dry)
12 Check availability of Oil in the breather cup
13 Check bushing test tap is grounded
14 Check door seals of marshalling box is intact and all unused holes are sealed
15 Check that pressure relief valve is correctly mounted
16 Ensure unused secondary cores of bushing CT’s, if any, has been shorted
17 Check CT star point has been formed properly and grounded at one end only as per
scheme
18 Check that permanent and adequate lighting arrangements are ready
19 Check that Buchholz relay is correctly mounted with arrow pointing towards
conservator
20 Check cables are properly fixed and ensure cable entry at the bottom
21 Ensure all power and control cable terminals are tightened
22 Check that all cables are correctly glanded
23 Check external cabling from junction box to relay / control panel completed
Test Performed by Witnessed by Witnessed by
Name : Name Name
Designation : Designation Designation
Signature & Signature & Signature &
Date Date Date
TEST REPORT FOR REACTOR
DOC. No. : VEPL/T&CF/SR/002 / Rev : 0
VOLTECH ENGINEERS PVT. JOB REF NO : VEPL/TR/ /
LTD. DATE : Page No.
Excellent Electrical Service
CLIENT : M/s.
PROJECT : Sheet No 2 of 10
24 Check all cables and ferrules are provided with number as per cable
schedule (cross feruling to be checked
25 Check that air has been released from the radiators and their headers /
Buchholz relay / main tank etc.
CLIENT : M/s.
PROJECT : Sheet No 3 of 10
Sample to be taken prior to changing of reactor and it should fulfill the Recommendations as per IS 1866
CLIENT : M/s.
PROJECT : Sheet No 4 of 10
Between HV Neutral
R ph Y ph B ph
Earth to Core-1
Earth to Core-2
Earth to Core-3
Earth to Core-4
Between HV
R ph Y ph B ph
Core-1 to Core-2
Core-1 to Core-3
Core-1 to Core-4
Core-2 to Core-3
Core-2 to Core-4
Core-3 to Core-4
CLIENT : M/s.
PROJECT : Sheet No 5 of 10
12. Secondary Winding Resistance of Bushing CT’s : (Values in Ohms) (Using Equipment Details)
A. HV Side
Core Between R ph Y ph B ph
Terminal Factory Site Factory Site Factory Site
Core-1 1S1-1S2
Core-2 2S1-2S2
Core-3 3S1-3S2
Core-4 4S1-4S2
B. Neutral Side
Core Between Neutral
Terminal Factory Site
Core-1 1S1-1S2
CLIENT : M/s.
PROJECT : Sheet No 6 of 10
Primary Injection through primary injection kit at primary terminal P1 – P2 measure current on the secondary
terminals
14.1. R – Phase
Core Primary Current Secondary Theoretical Actual % of
S1-S2 % Actual Current Ratio Ratio Error
Core-1 20 %
(1S1-1S2) 40 %
80 %
Core-2 20 %
(2S1-2S2) 40 %
80 %
Core-3 20 %
(3S1-3S2) 40 %
80 %
Core-4 20 %
(4S1-4S2) 40 %
80 %
14.2. Y – Phase
CLIENT : M/s.
PROJECT : Sheet No 7 of 10
80 %
Core-4 20 %
(4S1-4S2) 40 %
80 %
14.3. B – Phase
Core Primary Current Secondary Theoretical Actual % of
S1-S2 % Actual Current Ratio Ratio Error
Core-1 20 %
(1S1-1S2) 40 %
80 %
Core-2 20 %
(2S1-2S2) 40 %
80 %
Core-3 20 %
(3S1-3S2) 40 %
80 %
Core-4 20 %
(4S1-4S2) 40 %
80 %
(Not to be done for metering core) Knee Point Voltage (KVp) = _____________ Volt
CLIENT : M/s.
PROJECT : Sheet No 8 of 10
0.50 x KVp
0.75 x KVp
1.00 x KVp
1.10 x KVp
16. Contact Resistance Measurement : at 100 Amps (Values in Micro Ohms) (Using Equipment Details)
Note : The Value of Contact Resistance Should not be more than 5 Micro-Ohms Per Joint / Connector
Contact Resistance R ph Y ph B ph
Across HV Bushing Terminals Joint
Across Neutral Bus terminals
Details R ph Y ph B ph Neutral
Make
Type
Sl. No
CLIENT : M/s.
PROJECT : Sheet No 9 of 10
18. Tan Delta and Capacitance Measurement of Bushing : (Using Equipment Details)
19. Tan Delta and Capacitance Measurement of Winding : (Using Equipment Details)
CLIENT : M/s.
PROJECT : Sheet No 10 of 10
21. Remarks :