Perhitungan Harga Satuan Tebal Perkerasan

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 44

HARGA DASAR SATUAN UPAH

HARGA
No. URAIAN KODE SATUAN SATUAN KETERANGAN
( Rp.)

1. Pekerja (L01) Jam 12,857.14 11,142.86


2. Tukang (L02) Jam 12,857.14 15,285.71
3. Mandor (L03) Jam 17,162.86 15,285.71
4. Operator (L04) Jam 22,132.86 42,714.29
5. Pembantu Operator (L05) Jam 17,152.86 27,857.14
6. Sopir / Driver (L06) Jam 18,541.43 16,285.71
7. Pembantu Sopir / Driver (L07) Jam 14,235.71 12,142.86
8. Mekanik (L08) Jam 21,478.57 14,285.71
9. Pembantu Mekanik (L09) Jam 17,567.14 13,142.86
10. Kepala Tukang (L10) Jam 21,438.57 20,428.57
11.
12
13
26
27
28
29
30
31

Sumber : Penulis

DAFTAR
HARGA DASAR SATUAN BAHAN
HARGA
No. URAIAN KODE SATUAN SATUAN KETERANGAN
( Rp.)

1 Pasir Urug (ada unsur lempung) M01d M3 211,200.00 Base Camp


2 Agregat Kasar M03 M3 371,122.75 Base Camp
3 Agregat Halus M04 M3 371,122.75 Base Camp
4 Aspal M10 KG 17,500.00 Base Camp
6 Kerosen / Minyak Tanah M11 LITER 14,857.00 Base Camp
7 Semen / PC (40kg) M12 Zak 65,625.00 Base Camp
8 Semen / PC (kg) M12 Kg 1,640.63 Base Camp
9 Sirtu M16 M3 221,400.00 Lokasi Pekerjaan
10 Bensin M20 LITER 9,875.00 Pertamina
11 Solar M21 LITER 12,750.00 Pertamina
12 Minyak Pelumas / Olie M22 LITER 52,500.00 Pertamina
13 Bahan Agr.Base Kelas A M26 M3 368,801.14 Base Camp
14 Bahan Agr.Base Kelas B M27 M3 326,532.62 Base Camp
15 Minyak Fluks M53 Liter 10,000.00 Base Camp
16 Agregat Pecah Mesin 0-5 mm M91 M3 371,122.72 Base Camp
17 Agregat Pecah Mesin 5-10 & 10-20 mm M92 M3 371,122.72 Base Camp
18 Agregat Pecah Mesin 20-30 mm M93 M3 371,122.75 Base Camp
19 Batu Bara Kg 6,250.00 Base Camp
Sumber : Penulis
DAFTAR HARGA ALAT
NO JENIS ALAT HARGA ALAT HP KAPASITAS

1 Asphalt Mixing Plant 23,435,448.500 150.0 50.0 T/JAM


2 Asphalt Finisher 451,503.300 47.0 6.0 TON
3 Asphalt Sprayer/Distributor 167,705.000 15.0 800.0 LITER
4 Compressor 4000-6500 L\M 115,415.000 80.0 5,000.0 CPM/(L/m)
5 Dump Truck 3-5 Ton 321,436.500 100.0 6.0 TON
6 Dump Truck 10 Ton 442,154.750 125.0 8.0 TON
7 Generator Set 325,719.360 175.0 125.0 KVA
8 Motor Grader >100 Hp 1,596,806.250 125.0 10,800.0 JAM
9 WHEEL LOADER 1.0-1.6 M3 375,723.800 96.0 1.5 M3
10 TANDEM ROLLER 6-8 T 486,442.050 50.0 8.0 TON
11 TIREROLLER 8-10 T 574,121.058 60.0 10.0 TON
12 VIBRATORY ROLLER 5-8 T 763,591.250 75.0 7.0 TON
13 WATER TANKER 3000-4500 L 344,364.675 100.0 4,000.0 LITER
14 PEDESTRIAN ROLLER 133,502.775 11.0 0.98 TON
Sumber : penulis
URAIAN ANALISA ALAT
URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan ASPHALT MIXING PLANT #REF!
2. Tenaga Pw 150.0 HP
3. Kapasitas Cp 50.0 T/Jam
4. Alat a. Umur Ekonomis A 15.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,600.0 Jam
c. Harga Alat B 23,435,448.500 Rupiah

5 Kapastas tangki aspal Ca 30,000.00 liter

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 2,343,545 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.13147 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 1,733.15 Rupiah
W

b. Asuransi, dll = 0.002 x B F 29.29 Rupiah


W

Biaya Pasti per Jam = (E+F) G 1,762.44 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H1 248,625.00 Rupiah
Bahan Bakar Pemanasan Material = 12 ltr x Ms H2 5,355,000.00 Rupiah Khusus AMP
dan aspal (Oil Heater)
Bahan Bakar Pemanas Aspal = 1/1000 *Ca*Ms H3 382,500.00

2. Pelumas = (2.5%-3%) x Pw x Mp I 196,875.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 1,282


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 219.71 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 22,132.86 Rupiah
6 Pembantu Operator = ( 3 Orang / Jam ) x U2 M 51,458.58 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 6,258,092.77 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 6,259,855.00 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 22,132.86 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 17,152.86 Rp./Jam
4. Bahan Bakar Bensin Mb 9,875.00 Liter
5. Bahan Bakar Solar Ms 12,750.00 Liter
6. Minyak Pelumas Mp 52,500.00 Liter
7 PPN sudah diperhitungkan

8 Bahan bakar Batubara 6,250.00 Rp/kg


URAIAN ANALISA ALAT
URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan ASPHALT FINISHER #REF!
2. Tenaga Pw 47.0 HP
3. Kapasitas Cp 6.0 Ton
4. Alat Baru : a. Umur Ekonomis A 6.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,400.0 Jam
c. Harga Alat B 451,503.300 Rupiah
5.

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 45,150 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.22961 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 66.64 Rupiah
W

b. Asuransi, dll = 0.002 x B F 0.65 Rupiah


W

Biaya Pasti per Jam = (E+F) G 67.29 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 74,906.25 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 61,687.50 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 28


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 48.38 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 22,132.86 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 17,152.86 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 175,956.06 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 176,023.00 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 22,132.86 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 17,152.86 Rp./Jam
4. Bahan Bakar Bensin Mb 9,875.00 Liter
5. Bahan Bakar Solar Ms 12,750.00 Liter
6. Minyak Pelumas Mp 52,500.00 Liter
7. PPN sudah diperhitungkan
URAIAN ANALISA ALAT
URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan ASPHALT SPRAYER #REF!
2. Tenaga Pw 15.0 HP
3. Kapasitas Cp 800.0 Liter
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 167,705.000 Rupiah

5 Kapastas tangki aspal Ca 850 Liter

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 16,771 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 19.91 Rupiah
W

b. Asuransi, dll = 0.002 x B F 0.17 Rupiah


W

Biaya Pasti per Jam = (E+F) G 20.08 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 23,906.25 Rupiah


Bahan Bakar Pemanas Aspal = 1/1000 *Ca*Ms H3 10,837.50 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 19,687.50 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 7 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 12.58 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 18,541.43 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 14,235.71 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 87,228.30 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 87,248.00 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator U1 18,541.43 Rp./Jam
3. Upah Pembantu Operator U2 14,235.71 Rp./Jam
4. Bahan Bakar Bensin Mb 9,875.00 Liter
5. Bahan Bakar Solar Ms 12,750.00 Liter
6. Minyak Pelumas Mp 52,500.00 Liter
7. PPN sudah diperhitungkan
URAIAN ANALISA ALAT
URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan COMPRESSOR 4000-6500 L\M #REF!
2. Tenaga Pw 80.0 HP
3. Kapasitas Cp 5,000.0 CPM/(L/m)
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 115,415.000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 11,542 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 13.70 Rupiah
W

b. Asuransi, dll = 0.002 x B F 0.12 Rupiah


W

Biaya Pasti per Jam = (E+F) G 13.82 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 127,500.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 105,000.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 5


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 8.66 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 22,132.86 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 17,152.86 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 271,799.43 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 271,813.00 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 22,132.86 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 17,152.86 Rp./Jam
4. Bahan Bakar Bensin Mb 9,875.00 Liter
5. Bahan Bakar Solar Ms 12,750.00 Liter
6. Minyak Pelumas Mp 52,500.00 Liter
7. PPN sudah diperhitungkan
URAIAN ANALISA ALAT
URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan DUMP TRUCK 3.5 TON #REF!
2. Tenaga Pw 100.0 HP
3. Kapasitas Cp 6.0 Ton
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 321,436.500 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 32,144 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 38.16 Rupiah
W

b. Asuransi, dll = 0.002 x B F 0.32 Rupiah


W

Biaya Pasti per Jam = (E+F) G 38.48 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 159,375.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 131,250.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 14


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 24.11 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 22,132.86 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 17,152.86 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 329,948.89 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 329,987.00 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Sopir U1 22,132.86 Rp./Jam
3. Upah Pembantu Sopir U2 17,152.86 Rp./Jam
4. Bahan Bakar Bensin Mb 9,875.00 Liter
5. Bahan Bakar Solar Ms 12,750.00 Liter
6. Minyak Pelumas Mp 52,500.00 Liter
7. PPN sudah diperhitungkan
URAIAN ANALISA ALAT
URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan DUMP TRUCK 10 TON #REF!
2. Tenaga Pw 125.0 HP
3. Kapasitas Cp 8.0 Ton
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 442,154.750 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 44,215 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 52.49 Rupiah
W

b. Asuransi, dll = 0.002 x B F 0.44 Rupiah


W

Biaya Pasti per Jam = (E+F) G 52.93 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 199,218.75 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 164,062.50 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 19 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 33.16 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 22,132.86 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 17,152.86 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 402,619.48 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 402,672.00 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Sopir U1 22,132.86 Rp./Jam
3. Upah Pembantu Sopir U2 17,152.86 Rp./Jam
4. Bahan Bakar Bensin Mb 9,875.00 Liter
5. Bahan Bakar Solar Ms 12,750.00 Liter
6. Minyak Pelumas Mp 52,500.00 Liter
7. PPN sudah diperhitungkan
URAIAN ANALISA ALAT
URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan GENERATOR SET #REF!
2. Tenaga Pw 175.0 HP
3. Kapasitas Cp 125.0 KVA
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 325,719.360 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 32,572 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 38.67 Rupiah
W

b. Asuransi, dll = 0.002 x B F 0.33 Rupiah


W

Biaya Pasti per Jam = (E+F) G 38.99 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 278,906.25 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 229,687.50 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 14 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 24.43 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 22,132.86 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 17,152.86 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 547,918.15 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 547,957.00 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 22,132.86 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 17,152.86 Rp./Jam
4. Bahan Bakar Bensin Mb 9,875.00 Liter
5. Bahan Bakar Solar Ms 12,750.00 Liter
6. Minyak Pelumas Mp 52,500.00 Liter
7. PPN sudah diperhitungkan
URAIAN ANALISA ALAT
URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan MOTOR GRADER >100 HP #REF!
2. Tenaga Pw 125.0 HP
3. Kapasitas Cp 10,800.0 -
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 1,596,806.250 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 159,681 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 189.56 Rupiah
W

b. Asuransi, dll = 0.002 x B F 1.60 Rupiah


W

Biaya Pasti per Jam = (E+F) G 191.15 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 199,218.75 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 164,062.50 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 70 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 119.76 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 22,132.86 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 17,152.86 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 402,756.59 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 402,947.00 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 22,132.86 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 17,152.86 Rp./Jam
4. Bahan Bakar Bensin Mb 9,875.00 Liter
5. Bahan Bakar Solar Ms 12,750.00 Liter
6. Minyak Pelumas Mp 52,500.00 Liter
7. PPN sudah diperhitungkan
URAIAN ANALISA ALAT
URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan WHEEL LOADER 1.0-1.6 M3 #REF!
2. Tenaga Pw 96.0 HP
3. Kapasitas Cp 1.5 M3
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 375,723.800 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 37,572 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 44.60 Rupiah
W

b. Asuransi, dll = 0.002 x B F 0.38 Rupiah


W

Biaya Pasti per Jam = (E+F) G 44.98 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 153,000.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 126,000.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 16 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 28.18 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 22,132.86 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 17,152.86 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 318,330.34 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 318,375.00 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 22,132.86 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 17,152.86 Rp./Jam
4. Bahan Bakar Bensin Mb 9,875.00 Liter
5. Bahan Bakar Solar Ms 12,750.00 Liter
6. Minyak Pelumas Mp 52,500.00 Liter
7. PPN sudah diperhitungkan
URAIAN ANALISA ALAT
URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan TANDEM ROLLER 6-8 T. #REF!
2. Tenaga Pw 50.0 HP
3. Kapasitas Cp 8.0 Ton
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 486,442.050 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 48,644 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 57.74 Rupiah
W

b. Asuransi, dll = 0.002 x B F 0.49 Rupiah


W

Biaya Pasti per Jam = (E+F) G 58.23 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 79,687.50 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 65,625.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 21 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 36.48 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 22,132.86 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 17,152.86 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 184,655.98 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 184,714.00 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 22,132.86 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 17,152.86 Rp./Jam
4. Bahan Bakar Bensin Mb 9,875.00 Liter
5. Bahan Bakar Solar Ms 12,750.00 Liter
6. Minyak Pelumas Mp 52,500.00 Liter
7. PPN sudah diperhitungkan
URAIAN ANALISA ALAT
URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan P. TIRE ROLLER 8-10 T. #REF!
2. Tenaga Pw 60.0 HP
3. Kapasitas Cp 10.0 Ton
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 574,121.058 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 57,412 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 68.15 Rupiah
W

b. Asuransi, dll = 0.002 x B F 0.57 Rupiah


W

Biaya Pasti per Jam = (E+F) G 68.73 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 95,625.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 78,750.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 25 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 43.06 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 22,132.86 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 17,152.86 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 213,728.90 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 213,797.00 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 22,132.86 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 17,152.86 Rp./Jam
4. Bahan Bakar Bensin Mb 9,875.00 Liter
5. Bahan Bakar Solar Ms 12,750.00 Liter
6. Minyak Pelumas Mp 52,500.00 Liter
7. PPN sudah diperhitungkan
URAIAN ANALISA ALAT
URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan VIBRATORY ROLLER 5-8 T. #REF!
2. Tenaga Pw 75.0 HP
3. Kapasitas Cp 7.000 Ton
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 763,591.250 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 76,359 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 90.65 Rupiah
W

b. Asuransi, dll = 0.002 x B F 0.76 Rupiah


W

Biaya Pasti per Jam = (E+F) G 91.41 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 11,953.13 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 98,437.50 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 33 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 57.27 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 22,132.86 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 17,152.86 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 149,767.02 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 149,858.00 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 22,132.86 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 17,152.86 Rp./Jam
4. Bahan Bakar Bensin Mb 9,875.00 Liter
5. Bahan Bakar Solar Ms 12,750.00 Liter
6. Minyak Pelumas Mp 52,500.00 Liter
7. PPN sudah diperhitungkan
URAIAN ANALISA ALAT
URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan WATER TANKER 3000-4500 L. #REF!
2. Tenaga Pw 100.0 HP
3. Kapasitas Cp 4,000.0 Liter
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 344,364.675 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 34,436 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 40.88 Rupiah
W

b. Asuransi, dll = 0.002 x B F 0.34 Rupiah


W

Biaya Pasti per Jam = (E+F) G 41.22 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 159,375.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 131,250.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 15 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 25.83 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 22,132.86 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 17,152.86 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 329,951.61 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 329,992.00 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator U1 22,132.86 Rp./Jam
3. Upah Pembantu Operator U2 17,152.86 Rp./Jam
4. Bahan Bakar Bensin Mb 9,875.00 Liter
5. Bahan Bakar Solar Ms 12,750.00 Liter
6. Minyak Pelumas Mp 52,500.00 Liter
7. PPN sudah diperhitungkan
URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan PEDESTRIAN ROLLER #REF!
2. Tenaga Pw 11.0 HP
3. Kapasitas Cp 0.980 Ton
4. Alat Baru : a. Umur Ekonomis A 3.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 133,502.775 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 13,350 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.40211 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 24.16 Rupiah
W

b. Asuransi, dll = 0.002 x B F 0.13 Rupiah


W

Biaya Pasti per Jam = (E+F) G 24.29 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 17,531.25 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 14,437.50 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 6 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 10.01 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 22,132.86 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 17,152.86 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 71,270.32 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 71,294.00 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 22,132.86 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 17,152.86 Rp./Jam
4. Bahan Bakar Bensin Mb 9,875.00 Liter
5. Bahan Bakar Solar Ms 12,750.00 Liter
6. Minyak Pelumas Mp 52,500.00 Liter
7. PPN sudah diperhitungkan
ITEM PEMBAYARAN NO. : 4.2 (2)
JENISLampiran P.1.1 Perhitungan
PEKERJAAN Koefisien
: Lps. Pond. Tenaga
Ag. Kls. Kerja,
B, CBR Bahan dan Peralatan Untuk Pekerjaan
Min 60% Lapisan Pondasi
Agregat
SATUAN Kelas B (bahu jalan)
PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUA

No. URAIAN KODE KOEF. SATUAN

I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi existing jalan : sedang
4 Jarak rata-rata Base Camp ke lokasi pekerjaan L 12.25 KM
5 Tebal lapis Agregat padat t 0.15 M
6 Berat isi padat Bip 1.81
7 Jam kerja efektif per-hari Tk 7.00 Jam
8 Lebar bahu jalan Lb 1.00 M
9 Proporsi Campuran : - Agregat Pecah Mesin 20 - 30 mm 20-30 18.00 %
- Agregat Pecah Mesin 5 - 10 & 10 - 20 mm 5-10&10-20 18.00 %
- Sirtu St 64.00 %
10 Berat volume agregat (lepas) Bil 1.51 ton/m3
- Agregat B Fh 1.05

II. URUTAN KERJA


1 Wheel Loader mencampur & memuat Agregat ke
dalam Dump Truck di Base Camp
2 Dump Truck mengangkut Agregat ke lokasi
pekerjaan dan dihampar dengan Motor Grader
3 Hamparan Agregat dibasahi dengan Water Tank Truck
sebelum dipadatkan dengan Tandem Roller
4 Selama pemadatan sekelompok pekerja akan
merapikan tepi hamparan dan level permukaan
dengan menggunakan alat bantu

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA


1. BAHAN
Agregat B = 1 M3 x (Bip/Bil) x Fh (M27) 1.2586 M3

2. ALAT
2.a. WHEEL LOADER (E15)
Kapasitas bucket V 1.50 M3
Faktor bucket Fb 0.85 -
Faktor Efisiensi alat Fa 0.83 -
Waktu siklus Ts1
- Memuat dan lain-lain T1 0.45 menit

Ts1 0.45 menit

Kap. Prod. / jam = V x Fb x Fa x 60 Q1 141.10 M3


Ts1
Koefisien Alat / M3 = 1 : Q1 (E15) 0.0071 Jam

2.b. DUMP TRUCK (E08)


Kapasitas bak V 6.00 ton
Faktor Efisiensi alat Fa 0.85
Kecepatan rata-rata bermuatan v1 40.00 KM / Jam
Kecepatan rata-rata kosong v2 60.00 KM / Jam
Waktu Siklus :
- Waktu memuat = (V x 60)/(Q1 x Bil) T1 1.69 menit
- Waktu tempuh isi = (L : v1) x 60 menit T2 18.38 menit
- Waktu tempuh kosong = (L : v2) x 60 menit T3 12.25 menit
- Lain-lain termasuk menurunkan Agregat T4 2.00 menit
Ts2 34.31 menit

Kap. Prod. / Jam = V x Fa x 60 Q2 4.93 M3


Ts2 x Bip
Koefisien Alat / M3 = 1 : Q2 (E08) 0.2030 Jam

Berlanjut ke halaman berik


JENIS PEKERJAAN : Lps. Pond. Ag. Kls. B, CBR Min 60%
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUA

No. URAIAN KODE KOEF. SATUAN

2.c. MOTOR GRADER (E13)


Panjang hamparan Lh 50.00 M
Lebar efektif kerja blade b 2.40 M
Lebar overlap bo 0.30 M
Faktor Efisiensi alat Fa 0.83 -
Kecepatan rata-rata alat v 4.00 KM / Jam
Jumlah lintasan n 2.00 lintasan
Jumlah lajur N 1.00 lajur
Waktu Siklus Ts3
- Perataan 1 lintasan = (Lh x 60) : (v x 1000) T1 0.75 menit
- Lain-lain T2 1.00 menit
Ts3 1.75 menit

Kap.Prod. / jam = Lh x (N(b-bo)+bo) x t xFa x 60 Q3 256.11 M3


n x Ts3
Koefisien Alat / M3 = 1 : Q3 (E13) 0.0039 Jam

2.d. PEDESTRIAN ROLLER (E17)


Kecepatan rata-rata v 0.98 KM / Jam
Lebar efektif pemadatan b 1.00 M
Jumlah lintasan n 2.00 lintasan
Jumlah lajur lintasan N 1.00
Lebar overlap bo 0.30 m
Faktor Efisiensi alat Fa 0.83 -

Kapasitas Prod./Jam (v x 1000) x (N(b-bo)+bo) x t x Fa Q4 61.00 M3


n
Koefisien Alat / M3 = 1 : Q4 (E17) 0.0164 Jam

2.e. WATER TANKER (E23)


Volume Tangki air V 4,000.00 M3
Kebutuhan air / M3 agregat padat Wc 0.07 M3
Kapasitas pompa air pa 100.00 liter/menit
Faktor efisiensi alat Fa 0.83 -

Kap. Prod. / Jam = pa x Fa x 60 Q5 71.14 M3


1000 x Wc

Koefisien Alat / M3 = 1 : Q5 (E23) 0.0141 Jam

ALAT BANTU
diperlukan :
- Kereta dorong = 2 buah
- Sekop = 3 buah
- Garpu = 2 buah

3. TENAGA
Produksi menentukan : WHEEL LOADER Q1 141.10 M3/Jam
Produksi Agregat / hari = Tk x Q1 Qt 987.70 M3
Kebutuhan tenaga :
- Pekerja P 7.00 orang
- Mandor M 1.00 orang

Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 0.0496 Jam
- Mandor = (Tk x M) : Qt (L03) 0.0071 Jam

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

Berlanjut ke halaman berik


ITEM PEMBAYARAN NO. : 4.2 (2)
JENIS PEKERJAAN : Lps. Pond. Ag. Kls. B, CBR Min 60%
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUA

No. URAIAN KODE KOEF. SATUAN

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 412,236.46 / M3.

6. WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : . . . . . . . . . . . bulan

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 832.40 M3
Lampiran P.2 .1 Perhitungan Koefisien Tenaga Kerja, Bahan dan Peralatan Untuk Pekerjaan Lapis Resap Pengikat

No. URAIAN KODE KOEF. SATUAN

I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Jarak rata-rata Base Camp ke lokasi pekerjaan L 12.25 KM
4 Jam kerja efektif per-hari Tk 7.00 Jam
5 Faktor kehilangan bahan Fh 1.10 -
6 Komposisi campuran :
- Aspal Pen 60 atau Pen 80 As 56 %
- Kerosene K 44 %
7 Berat jenis bahan :
- Aspal Pen 60 atau Pen 80 D1 1.03 Kg / liter
- Minyak Flux / Pencair D2 0.80 Kg / liter
8 Bahan dasar (aspal & minyak pencair) semuanya
diterima di lokasi pekerjaan

II. URUTAN KERJA


1 Aspal dan Minyak Flux dicampur dan dipanaskan
sehingga menjadi campuran aspal cair
2 Permukaan yang akan dilapis dibersihkan dari debu
dan kotoran dengan Air Compressor
3 Campuran aspal cair disemprotkan dengan Asphalt
Sprayer ke atas permukaan yang akan dilapis.
4 Angkutan Aspal & Minyak Flux menggunakan Dump
Truck

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN
Untuk mendapatkan 1 liter Lapis Resap Pengikat
diperlukan : ( 1 liter x Fh ) PC 1.10 liter

1.a. Aspal = As x PC x D1 (M10) 0.6345 Kg.


1.b. Minyak Flux = K x PC (M11) 0.4840 liter

2. ALAT
2.a. ASPHALT DISTRIBUTOR (E41)
Lebar penyemprotan b 3.00 M
Kecepatan penyemprotan V 30.00 m/menit
Kapasitas pompa aspal pas 100 liter/menit
Faktor effisiensi kerja Fa 0.80

Kap. Prod. / jam = pas x Fa x 60 Q1 4,800.00 liter

Koefisien Alat / Ltr = 1 : Q1 (E03) 0.0002 Jam

2.b. AIR COMPRESSOR (E05)

Kap. Prod. / jam = Asphalt Distributor Q2 4,800.00 liter

Koefisien Alat / Ltr = 1 : Q2 (E05) 0.0002 Jam

3. TENAGA
Produksi menentukan : ASPHALT DISTRIBUTOR Q4 4,800.00 liter
Produksi Lapis Resap Pengikat / hari = Tk x Q4 Qt 33,600.00 liter
Kebutuhan tenaga :
- Pekerja P 10.00 orang
- Mandor M 2.00 orang

Berlanjut ke halaman berik


No. URAIAN KODE KOEF. SATUAN

Koefisien tenaga / liter :


- Pekerja = (Tk x P) : Qt (L01) 0.0021 Jam
- Mandor = (Tk x M) : Qt (L03) 0.0004 Jam

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 18,328.12 / liter.

6. WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : . . . . . . . . . . . bulan

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 6,659.20 Liter
Analisa EI-422
en Tenaga Kerja, Bahan dan Peralatan Untuk Pekerjaan Lapisan Pondasi
URAIAN ANALISA HARGA SATUAN

KETERANGAN

Gradasi harus
memenuhi
Spesifikasi

Pemuatan lepas
sedang

panduan

Berlanjut ke halaman berikut


URAIAN ANALISA HARGA SATUAN
Lanjutan

KETERANGAN

1 x pp

Lump Sum

Berlanjut ke halaman berikut


Analisa EI-422

URAIAN ANALISA HARGA SATUAN


Lanjutan

KETERANGAN
sien Tenaga Kerja, Bahan dan Peralatan Untuk Pekerjaan Lapis Resap Pengikat

KETERANGAN

100 bagian
80 bagian

Campuran

Asumsi
Panduan
Sedang

Berlanjut ke halaman berikut


Lanjutan

KETERANGAN
Analisa EI-422

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KEGIATAN :
No. PAKET KONTRAK #REF!
NAMA PAKET #REF!
Lampiran P.1 Perhitungan Biaya Untuk Pekerjaan Lapisan Pondasi Agregat Kelas B (bahu jalan)
#REF!
(M3)
PROP / KAB / KODYA #REF!
ITEM PEMBAYARAN NO. : 4.2 (2) PERKIRAAN VOL. PEK. :
JENIS PEKERJAAN : Lps. Pond. Ag. Kls. B, CBR Min 60% TOTAL HARGA (Rp.) :
SATUAN PEMBAYARAN : M3 % THD. BIAYA PROYEK :

HARGA JUMLAH
NO. KOMPONEN SATUAN KOEFISIEN SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.0496 12,857.14 637.85


2. Mandor (L03) Jam 0.0071 17,162.86 121.64

JUMLAH HARGA TENAGA 759.48

B. BAHAN

1. Agregat B (M27) M3 1.2586 326,532.62 410,976.98

JUMLAH HARGA BAHAN 410,976.98

C. PERALATAN

1 Wheel Loader E15 Jam 0.0071 - 0.00


2 Dump Truck E08 Jam 0.2030 - 0.00
3 Motor Grader E13 Jam 0.0039 - 0.00
4 Pedestrian Roller E17 Jam 0.0164 - 0.00
5 Water Tanker E23 Jam 0.0141 - 0.00
6 Alat Bantu Ls 1.0000 500.00 500.00

JUMLAH HARGA PERALATAN 500.00

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 412,236.46


E. OVERHEAD & PROFIT 10.0 % x D 41,223.65
F. HARGA SATUAN PEKERJAAN (D + E)(DIBULATKAN) 453,460.00
Lampiran P.2 Perhitungan Biaya Untuk Pekerjaan Lapis Resap Pengikat
(Liter)

HARGA JUMLAH
NO. KOMPONEN SATUAN KOEFISIEN SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.0021 12,857.14 26.79


2. Mandor (L03) Jam 0.0004 17,162.86 7.15

JUMLAH HARGA TENAGA 33.94

B. BAHAN

1. Aspal (M10) Kg 0.6345 17,500.00 11,103.40


2. Kerosene (M11) liter 0.4840 14,857.00 7,190.79

JUMLAH HARGA BAHAN 18,294.19

C. PERALATAN

1. Asp. Distributor E41 Jam 0.0002 - 0.00


2. Air Compresor (E05) Jam 0.0002 0.00 0.00

JUMLAH HARGA PERALATAN 0.00

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 18,328.12


E. OVERHEAD & PROFIT 10.0 % x D 1,832.81
F. HARGA SATUAN PEKERJAAN (D + E)(DIBULATKAN) 20,160.00
p
Lampiran P.3.1 Perhitungan Koefisien Tenaga Kerja, Bahan dan Peralatan Untuk Pekerjaan Lapis Pondasi Agregat Kelas A

No. URAIAN KODE KOEF. SATUAN KETERANGAN

I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi existing jalan : sedang
4 Jarak rata-rata Base Camp ke lokasi pekerjaan L 12.25 KM
5 Tebal lapis Agregat padat t 0.15 M
6 Berat isi padat Bip 1.81 -
7 Jam kerja efektif per-hari Tk 7.00 Jam
8 Lebar bahu jalan Lb 1.00 M
9 Proporsi Campuran : - Agregat Pecah Mesin 20 - 30 mm 20-30 28.00 % Gradasi harus
- Agregat Pecah Mesin 5 - 10 & 10 - 20 mm 5-10&10-20 42.00 % memenuhi Spec.
- Pasir Urug PU 30.00 %
10 Berat Isi Agregat (lepas) Bil 1.51 ton/m3
Faktor kehilangan - Agregat A Fh 1.05

II. URUTAN KERJA


1 Wheel Loader mencampur & memuat Agregat ke
dalam Dump Truck di Base Camp
2 Dump Truck mengangkut Agregat ke lokasi
pekerjaan dan dihampar dengan Motor Grader
3 Hamparan Agregat dibasahi dengan Water Tank Truck
sebelum dipadatkan dengan Tandem Roller
4 Selama pemadatan sekelompok pekerja akan
merapikan tepi hamparan dan level permukaan
dengan menggunakan alat bantu

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN
- Agregat A = 1 M3 x (Bip/Bil) x Fh (M26) 1.25861 M3

2. ALAT
2.a. WHEEL LOADER (E15)
Kapasitas bucket V 1.50 M3 (lepas)
Faktor bucket Fb 0.85 - kondisi sedang
Faktor Efisiensi alat Fa 0.83 -
Waktu Siklus :
- Memuat dan lain-lain Ts1 0.45 menit panduan

Kap. Prod. / jam = V x Fb x Fa x 60 Q1 141.10 M3


Ts1
Koefisien Alat / M3 = 1 : Q1 (E15) 0.0071 Jam

2.b. DUMP TRUCK (E08)


Kapasitas bak V 6.00 ton
Faktor Efisiensi alat Fa 0.85 -
Kecepatan rata-rata bermuatan v1 40.00 KM / Jam
Kecepatan rata-rata kosong v2 60.00 KM / Jam
Waktu Siklus :
- Waktu memuat = (V x 60)/(Q1 x Bil) T1 1.69 menit
- Waktu tempuh isi = (L : v1) x 60 menit T2 18.38 menit
- Waktu tempuh kosong = (L : v2) x 60 menit T3 12.25 menit
- Lain-lain termasuk menurunkan Agregat T4 2.00 menit
Ts2 34.31 menit

Kap. Prod./jam = V x Fa x 60 Q2 4.93 M3


bip x Ts2
Koefisien Alat / M3 = = 1 : Q2 (E08) 0.2030 Jam

Berlanjut ke halaman berikut


Lanjutan

No. URAIAN KODE KOEF. SATUAN KETERANGAN

2.c. MOTOR GRADER (E13)


Panjang hamparan Lh 50.00 M
Lebar efektif kerja blade b 1.00 M
Lebar overlap bo 0.30 M
Faktor Efisiensi alat Fa 0.83 -
Kecepatan rata-rata alat v 4.00 KM / Jam
Jumlah lintasan n 2.00 lintasan 1 x pp
Jumlah lajur N 2.00 lajur
Waktu Siklus Ts3
- Perataan 1 lintasan = (Lh x 60) : (v x 1000) T1 0.75 menit
- Lain-lain T2 1.00 menit
Ts3 1.75 menit

Kap.Prod. / jam = Lh x (N(b-bo)+bo) x t xFa x 60 Q3 181.41 M3


n x Ts3
Koefisien Alat / M3 = 1 : Q3 (E13) 0.0055 Jam

2.d. TANDEM ROLLER (E17)


Kecepatan rata-rata v 1.50 KM / Jam
Lebar efektif pemadatan b 1.20 M
Jumlah lintasan n 8.00 lintasan
Jumlah lajur lintasan N 2.00
Lebar overlap bo 0.30 m
Faktor Efisiensi alat Fa 0.83 -

Kapasitas Prod./Jam (v x 1000) x (N(b-bo)+bo) x t x Fa Q4 49.02 M3


n
Koefisien Alat / M3 = 1 : Q4 (E17) 0.0204 Jam

2.e. WATERTANK TRUCK (E23)


Volume tangki air V 4,000.00 M3
Kebutuhan air / M3 agregat padat Wc 0.07 M3
Kapasitas pompa air pa 100.00 liter/menit
Faktor Efisiensi alat Fa 0.83 -

Kap.Prod. / jam = pa x Fa x 60 Q5 71.14 M3


1000 x Wc
Koefisien Alat / M3 = 1 : Q5 (E23) 0.0141 Jam

2.g. ALAT BANTU


diperlukan : Lump Sum
- Kereta dorong = 2 buah
- Sekop = 3 buah
- Garpu = 2 buah

3. TENAGA
Produksi menentukan : WHEEL LOADER Q1 141.10 M3/Jam
Produksi Agregat / hari = Tk x Q1 Qt 987.70 M3
Kebutuhan tenaga :
- Pekerja P 7.00 orang
- Mandor M 1.00 orang

Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 0.0496 Jam
- Mandor = (Tk x M) : Qt (L03) 0.0071 Jam

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

Berlanjut ke halaman berikut


Lanjutan

No. URAIAN KODE KOEF. SATUAN KETERANGAN

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 465,936.02 / M3.

6. WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : . . . . . . . . . . . bulan

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 2,098.00 M3
:

Lampiran P.3 Perhitungan Biaya Untuk Pekerjaan Lapis Pondasi Agregat Kelas A
(M3)

HARGA JUMLAH
NO. KOMPONEN SATUAN Koefisien SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.0496 12,857.14 637.85


2. Mandor (L03) Jam 0.0071 17,162.86 121.64

JUMLAH HARGA TENAGA 759.48

B. BAHAN

1. Agregat A (M26) M3 1.2586 368,801.14 464,176.53

JUMLAH HARGA BAHAN 464,176.53

C. PERALATAN

1 Wheel Loader E15 Jam 0.0071 - 0.00


2 Dump Truck E08 Jam 0.2030 - 0.00
3 Motor Grader E13 Jam 0.0055 - 0.00
4 Tandem Roller E17 Jam 0.0204 - 0.00
5 Water Tanker E23 Jam 0.0141 - 0.00
6 Alat Bantu Ls 1.0000 1,000.00 1,000.00

JUMLAH HARGA PERALATAN 1,000.00

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 465,936.02


E. OVERHEAD & PROFIT 10 % X D 46,593.60
F HARGA SATUAN PEKERJAAN 512,529.62
Lampiran P.4 Perhitungan Koefisien Tenaga Kerja, Bahan dan Peralatan Untuk Pekerjaan Lapis Resap Pengikat
(Prime Coat)

No. URAIAN KODE KOEF. SATUAN KETERANGAN

I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Jarak rata-rata Base Camp ke lokasi pekerjaan L 12.25 KM
4 Jam kerja efektif per-hari Tk 7.00 Jam
5 Faktor kehilangan bahan Fh 1.10 -
6 Komposisi campuran :
- Aspal Pen 60 atau Pen 80 As 64 % 100 bagian
- Kerosene K 36 % 80 bagian
7 Berat jenis bahan :
- Aspal Pen 60 atau Pen 80 D1 1.03 Kg / liter
- Minyak Flux / Pencair D2 0.80 Kg / liter
8 Bahan dasar (aspal & minyak pencair) semuanya
diterima di lokasi pekerjaan

II. URUTAN KERJA


1 Aspal dan Minyak Flux dicampur dan dipanaskan
sehingga menjadi campuran aspal cair
2 Permukaan yang akan dilapis dibersihkan dari debu
dan kotoran dengan Air Compressor
3 Campuran aspal cair disemprotkan dengan Asphalt
Sprayer ke atas permukaan yang akan dilapis.
4 Angkutan Aspal & Minyak Flux menggunakan Dump
Truck

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN
Untuk mendapatkan 1 liter Lapis Resap Pengikat
diperlukan : ( 1 liter x Fh ) PC 1.10 liter Campuran

1.a. Aspal = As x PC x D1 (M10) 0.7251 Kg.


1.b. Minyak Flux = K x PC (M11) 0.3960 liter

2. ALAT
2.a. ASPHALT DISTRIBUTOR (E41)
Lebar penyemprotan b 3.00 M
Kecepatan penyemprotan V 30.00 m/menit Asumsi
Kapasitas pompa aspal pas 100 liter/menit Panduan
Faktor effisiensi kerja Fa 0.80 Sedang

Kap. Prod. / jam = pas x Fa x 60 Q1 4,800.00 liter

Koefisien Alat / Ltr = 1 : Q1 (E03) 0.0002 Jam

2.b. AIR COMPRESSOR (E05)

Kap. Prod. / jam = Asphalt Distributor Q2 4,800.00 liter

Koefisien Alat / Ltr = 1 : Q2 (E05) 0.0002 Jam

3. TENAGA
Produksi menentukan : ASPHALT DISTRIBUTOR Q4 4,800.00 liter
Produksi Lapis Resap Pengikat / hari = Tk x Q4 Qt 33,600.00 liter
Kebutuhan tenaga :
- Pekerja P 10.00 orang
- Mandor M 2.00 orang

Berlanjut ke halaman berikut


Lanjutan

No. URAIAN KODE KOEF. SATUAN KETERANGAN

Koefisien tenaga / liter :


- Pekerja = (Tk x P) : Qt (L01) 0.0021 Jam
- Mandor = (Tk x M) : Qt (L03) 0.0004 Jam

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 18,606.91 / liter.

6. WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : . . . . . . . . . . . .bulan

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 16,548.00 Liter
Analisa EI-636a
Lampiran P.5.1 Perhitungan Koefisien Tenaga Kerja, Bahan dan Peralatan Untuk Pekerjaan Laston Lapis Antara
(AC-BC)
URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN KETERANGAN

I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi existing jalan : rusak
4 Jarak rata-rata Base Camp ke lokasi pekerjaan L 12.25 KM
5 Tebal Lapis (AC) padat t 0.05 M
6 Jam kerja efektif per-hari Tk 7.00 Jam
7 Faktor kehilanganmaterial : - Agregat Fh1 1.05 -
- Aspal Fh2 1.03 -
8 Berat isi Agregat (padat) Bip 1.81 ton/m3
9 Berat Isi Agregat (lepas) Bil 1.51 ton/m3
10 Komposisi campuran AC-BC :
- Agr Pch Mesin 5 - 10 & 10 - 20 mm 5-10&10-20 52.20 % Gradasi harus -
- Agregat Pecah Mesin 0 - 5 mm 0-5 40.80 % memenuhi -
- Semen FF 1.90 % Spesifikasi
- Asphalt As 5.10 %
- Anti Stripping Agent Asa 0.30 %As
11 Berat Isi bahan :
- AC-BC D1 2.32 ton / M3
- Agr Pch Mesin 5 - 10 & 10 - 20 mm D2 1.41 ton / M3
- Agr Pch Mesin 0 - 5 mm D3 1.57 ton / M3
12 Jarak Stock file ke cold bin l 0.05 km

II. URUTAN KERJA / METODE PELAKSANAAN


1 Wheel Loader memuat Agregat dan Asphalt ke dalam
Cold Bin AMP
2 Agregat dan aspal dicampur dan dipanaskan dengan
dengan AMP untuk dimuat langsung ke dalam
Dump Truck dan diangkut ke lokasi pekerjaan
3 Campuran panas AC dihampar dengan Finisher
dan dipadatkan dengan Tandem & Pneumatic
Tire Roller
4 Selama pemadatan, sekelompok pekerja akan
merapikan tepi hamparaan dengan menggunakan
Alat Bantu

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN
1.a. Agr 5-10 & 10-20 = ("5-10&10-20" x Fh1) : D2 (M92) 0.3887 M3
1.b. Agr 0-5 = ("0-5" x Fh1) : D3 (M91) 0.2729 M3
1.c. Asphalt 51.0000 Kg

2. ALAT
2.a. WHEEL LOADER (E15)
Kapasitas bucket V 1.50 M3
Faktor bucket Fb 0.85 -
Faktor efisiensi alat Fa 0.83 -
Waktu Siklus T1 + T2 + T3 Ts1 1.05 menit
- Kecepatan maju rata rata Vf 20.00 km/jam panduan
- Kecepatan kembali rata rata Vr 20.00 km/jam panduan
- Muat ke Bin = (l x 60) / Vf T1 0.15 menit
- Kembali ke Stock pile = (l x 60) / Vr T2 0.15 menit
- Lain - lain (waktu pasti) T3 0.75 menit
Ts1 1.05 menit

Kap. Prod. / jam = V x Fb x Fa x 60 x Bip Q1 109.45 ton


Ts1

Koefisien Alat/ton = 1 : Q1 (E15) 0.0091 Jam


Berlanjut ke hal. berikut.

0 0 Analisa EI-636a
JENIS PEKERJAAN 0
SATUAN PEMBAYARAN 0 URAIAN ANALISA HARGA SATUAN
Lanjutan

No. URAIAN KODE KOEF. SATUAN KETERANGAN

2.b. ASPHALT MIXING PLANT (AMP) (E01)


Kapasitas produksi V 50.00 ton / Jam
Faktor Efisiensi alat Fa 0.83 -

Kap.Prod. / jam = V x Fa Q2 41.50 ton

Koefisien Alat / ton = 1 : Q2 (E01) 0.0241 Jam

2.c. GENERATORSET ( GENSET ) (E12)


Kap.Prod. / Jam = SAMA DENGAN AMP Q3 41.50 ton
Koefisien Alat / ton = 1 : Q3 (E12) 0.0241 Jam

2.d. DUMP TRUCK (DT) (E08)


Kapasitas bak V 6.00 ton
Faktor Efisiensi alat Fa 0.80 -
Kecepatan rata-rata bermuatan v1 20.00 Km / Jam
Kecepatan rata-rata kosong v2 30.00 Km / Jam
Kapasitas AMP / batch Q2b 1.00 ton
Waktu menyiapkan 1 batch AC-BC Tb 1.00 menit
Waktu Siklus Ts2
- Mengisi Bak = (V : Q2b) x Tb T1 6.00 menit
- Angkut = (L : v1) x 60 menit T2 36.75 menit
- Tunggu + dump + Putar T3 15.00 menit
- Kembali = (L : v2) x 60 menit T4 24.50 menit
Ts2 82.25 menit

Kap.Prod. / jam = V x Fa x 60 Q4 3.50 ton


Ts2

Koefisien Alat / ton = 1 : Q4 (E08) 0.2856 Jam

2.e. ASPHALT FINISHER (E02)


Kecepatan menghampar V 6.00 m/menit
Faktor efisiensi alat Fa 0.83 - Normal
Lebar hamparan b 3.15 meter
Kap.Prod. / jam = V x b x 60 x Fa x t x D1 Q5 109.18 ton

Koefisien Alat / ton = 1 : Q5 (E02) 0.0092 Jam

2.f. TANDEM ROLLER (E17)


Kecepatan rata-rata alat v 1.50 Km / Jam
Lebar efektif pemadatan b 1.48 M
Jumlah lintasan n 6.00 lintasan 2 awal & 4 Akhir
Jumlah lajur lintasan N 3.00
Lebar overlap bo 0.30 m
Faktor Efisiensi alat Fa 0.83 - Normal

Kap. Prod./jam = (v x 1000) x (N(b-bo)+bo) x t x Fa x D1 Q6 92.43 ton


n
Koefisien Alat / ton = 1 : Q6 (E17) 0.0108 Jam

2.g. PNEUMATIC TIRE ROLLER (E18)


Kecepatan rata-rata v 2.50 KM / Jam
Lebar efektif pemadatan b 1.99 M
Jumlah lintasan n 6.00 lintasan
Lajur lintasan N 3.00
Lebar Overlap bo 0.30 M
Faktor Efisiensi alat Fa 0.83 -

Kap.Prod. / jam = (v x 1000) x (N(b-bo)+bo) x t x Fa x D1 Q7 215.43 ton


n
Koefisien Alat / ton = 1 : Q7 (E18) 0.0046 Jam
Berlanjut ke hal. berikut.

0 0 0
JENIS PEKERJAAN 0
SATUAN PEMBAYARAN 0 URAIAN ANALISA HARGA SATUAN
Lanjutan

No. URAIAN KODE KOEF. SATUAN KETERANGAN

2.h. ALAT BANTU


diperlukan : Lump Sum
- Kereta dorong = 2 buah
- Sekop = 3 buah
- Garpu = 2 buah
- Tongkat Kontrol ketebalan hanparan

3. TENAGA
Produksi menentukan : AMP Q2 41.50 ton
Produksi AC-BC / hari = Tk x Q5 Qt 290.50 ton
Kebutuhan tenaga :
- Pekerja P 10.00 orang
- Mandor M 1.00 orang

Koefisien Tenaga / ton :


- Pekerja = (Tk x P) / Qt (L01) 0.2410 Jam
- Mandor = (Tk x M) / Qt (L03) 0.0241 Jam

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 516,231.72 / TON

6. WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : . . . . . . . . . . . .bulan

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 2,693.96 ton
Lampiran P.4 Perhitungan Biaya Untuk Pekerjaan Lapis Resap Pengikat (Prime Coat)
(Liter)

HARGA JUMLAH
NO. KOMPONEN SATUAN KOEFISIEN SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.0021 12,857.14 26.79


2. Mandor (L03) Jam 0.0004 17,162.86 7.15

JUMLAH HARGA TENAGA 33.94

B. BAHAN

1. Aspal (M10) Kg 0.7251 17,500.00 12,689.60


2. Kerosene (M11) liter 0.3960 14,857.00 5,883.37

JUMLAH HARGA BAHAN 18,572.97

C. PERALATAN

1. Asp. Distributor E41 Jam 0.0002 - 0.00


2. Air Compresor (E05) Jam 0.0002 0.00 0.00

JUMLAH HARGA PERALATAN 0.00

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 18,606.91


E. OVERHEAD & PROFIT 10.0 % x D 1,860.69
F. HARGA SATUAN PEKERJAAN (D + E)(DIBULATKAN) 20,467.00
Analisa EI-636a

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KEGIATAN : Rehabilitasi/Pemeliharaan Jalan (DAK)


No. PAKET KONTRAK
NAMA PAKET

PROP / KAB / KODYA Lampiran P.5.


: Aceh Tamiang
Perhitungan Biaya Untuk Pekerjaan Laston Lapis Antara (AC-BC)
ITEM PEMBAYARAN NO. 0 (Ton) PERKIRAAN VOL. PEK. : #NAME?
JENIS PEKERJAAN 0 TOTAL HARGA (Rp.) : 1,743,633,838.99
SATUAN PEMBAYARAN 0 % THD. BIAYA PROYEK : 16.36

HARGA JUMLAH
NO. KOMPONEN SATUAN KOEFISIEN SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.2410 12,857.14 3,098.11


2. Mandor (L03) Jam 0.0241 17,162.86 413.56

JUMLAH HARGA TENAGA 3,511.67

B. BAHAN

1. Agr 5-10 & 10-20 (M92) M3 0.3887 371,122.72 144,264.09


2. Agr 0-5 (M91) M3 0.2729 371,122.72 101,266.86
3. Asphalt (M10) Ton 0.051 17,500.00 892.50

JUMLAH HARGA BAHAN 246,423.45

C. PERALATAN
1. Wheel Loader E15 Jam 0.0091 318,375.00 2,908.78
2. AMP E01 Jam 0.0241 6,259,855.00 150,839.88
3. Genset E12 Jam 0.0241 547,957.00 13,203.78
4. Dump Truck E08 Jam 0.2856 329,987.00 94,241.08
5. Asphalt Finisher E02 Jam 0.0092 176,023.00 1,612.21
6. Tandem Roller E17 Jam 0.0108 184,714.00 1,998.45
7 P. Tyre Roller E18 Jam 0.0046 213,797.00 992.44
8 Alat Bantu Ls 1.0000 500.00 500.00

JUMLAH HARGA PERALATAN 266,296.60

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 516,231.72


E. OVERHEAD & PROFIT 10.0 % x D 51,623.17
F. HARGA SATUAN PEKERJAAN (D + E)(DIBULATKAN) 567,854.00
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan termasuk PPN
dan biaya-biaya lainnya.
DESKRIPSI HASIL PERHITUNGAN

Harga (Rp) Jumlah Harga Selisih


No Uraian Pekerjaan Satuan Kuantitas
Kontrak Penulis Kontrak Penulis Rupiah
DIVISI 4. PELEBARAN PERKERASAN DAN BAHU JALAN
1 Lapis Pondasi Agregat Kelas B M3 832.40 491,890.19 412,236.46 409,449,394.16 343,145,633.04 66,303,761.12
2 lepas resap pengikat Liter 6659.20 18,496.64 18,328.12 123,172,825.09 122,050,649.33 1,122,175.75
DIVISI 5. PERKERASAN BERBUTIR
2 Lapis Pondasi Agregat Kelas A M3 2098.00 533,060.03 465,936.02 1,118,359,942.94 977,533,760.84 140,826,182.10
DIVISI 6. PERKERASAN ASPAL
4 Lapis Resap Pengikat-Aspal Cair Liter 16,548.00 18,752.77 18,606.91 310,320,837.96 307,907,128.48 2,413,709.48
5 Laston Lapis Antara (AC-BC) Ton 2,693.96 546,588.44 516,231.72 1,472,487,393.82 1,390,707,610.24 81,779,783.58
Jumlah 3,433,790,393.97 3,141,344,781.94 292,445,612.03
sumber : Penulis
Selisih
Bobot (%)

2.11
0.04

4.48

0.08
2.60
9.31
REKAPITULASI HARGA TEBAL PERKERASAN
NO PEKERJAAN VOLUME SATUAN HARGA SATUAN JUMLAH HARGA SATUAN
1 LPB 585 M3 Rp 453,460.00 Rp 265,274,100.00
2 LPA 525 M3 Rp 512,529.62 Rp 269,078,049.04
3 PENGASPALAN 420 M3 Rp 567,854.00 Rp 238,498,680.00
JUMLAH KESELURUHAN Rp 772,850,829.04

Terbilang

Buket rata 30 /05 / 2017

MUHDA GAYO
1522302073