Professional Documents
Culture Documents
26 - Week 8 - Project Cost Management
26 - Week 8 - Project Cost Management
26 - Week 8 - Project Cost Management
Learning Objectives
“Excellence through Knowledge”
Because each project is unique, the PM may need to tailor the application of Project
Cost Management processes, not limited to:
• Knowledge management – EEF & OPA support (database) for technical and
financial information?
• Estimating and budgeting – existence of cost estimating and budgeting-related
policies, procedures, and guidelines?
• Earned value management – is EVM used in managing projects?
• Use of agile approach – are agile methodologies used in managing projects? What
is the impact on cost estimating?
• Governance – are there audit and governance policies, procedures, and guidelines?
“Excellence through Knowledge”
7 7.1 7.4
Cost Plan Cost Control Costs
Management
7.2
Estimate Costs
7.3
Determine
Budget
“Excellence through Knowledge”
• Influencing the factors that create changes to the authorized cost baseline;
• Ensuring that all change requests are acted on in a timely manner;
• Managing the actual changes when and as they occur;
• Ensuring that cost expenditures do not exceed the authorized funding by period, by WBS
component, by activity, and in total for the project;
• Monitoring cost performance to isolate and understand variances from the approved cost
baseline;
• Monitoring work performance against funds expended;
• Preventing unapproved changes from being included in the reported cost or resource usage;
• Informing appropriate stakeholders of all approved changes and associated cost; and
• Bringing expected cost overruns within acceptable limits
“Excellence through Knowledge”
EVM integrates the scope baseline with the cost & schedule
baselines to form the performance measurement baseline (by
way of the development and monitoring of 3 key dimensions
for each work package and control account:
“Excellence through Knowledge”
• Cost Variance CV = EV – AC
• Schedule Variance SV = EV – PV
• Variance at Completion VAC = BAC – EAC
“Excellence through Knowledge”
SPI = EV/PV
SPI < 1.0 indicates less work was completed than was planned
SPI > 1.0 indicates that more work was completed than was planned
• Cost performance index (CPI) - a measure of how efficiently the project team
is utilizing the resources.
CPI = EV/AC
CPI < 1.0 indicates a cost overrun for work completed
CPI > 1.0 indicates a cost underrun of performance to date
“Excellence through Knowledge”
“Excellence through Knowledge”
To Complete Performance
Index (TCPI)
- a measure of the cost
performance that is required to
be achieved with the remaining
resources in order to meet a
specified management goal.
- expressed as the ratio of the
cost to finish the outstanding
work to the remaining budget.
“Excellence through Knowledge”
To Complete Performance Index (BAC – EV) / (BAC – AC) How efficiently must we use our
(TCPI) remaining resources?
Estimate at Completion (EAC) BAC / CPI What is the project likely to cost?
Estimate to Completion (ETC) (BAC – EV) / CPI What will the remaining work cost?
KEY
PMP® Exam Prep 6th Edition
S Actual Start F Actual Finish
by Rita Mulcahy, p. 244
PS Planned Start PF Planned Finish
“Excellence through Knowledge”
Calculate:
1. Planned Value (PV)
2. Earned Value (EV)
3. Actual Cost (AC)
4. Budgeted at Completion (BAC)
5. Cost Variance (CV)
6. Cost Performance Index (CPI)
7. Schedule Variance (SV)
8. Schedule Performance Index (SPI)
9. To Complete Performance Index (TCPI)
10. Estimate at Completion (EAC)
11. Estimate to Completion (ETC)
12. Variance at Completion (VAC)
“Excellence through Knowledge”
Answers:
1. PV $3,000
2. EV $2,500
3. AC $2,800
4. BAC $4,000
5. CV -$300
6. CPI 89.3%
“Excellence through Knowledge”
Answer:
CV = $80,000
“Excellence through Knowledge”
Description Value
Budget At Completion
Planned Value
Earned Value
Actual Cost
Cost Variance
Schedule Variance
Cost Performance Index
Schedule Performance Index
Estimate At Completion
Estimate To Completion
Variance At Completion
“Excellence through Knowledge”
Description Value
Budget At Completion $100,000
Planned Value 2w/5w = 40%*100,000= $40,000.
Earned Value 2r/6r=33.3% *100,000=33,333.33
Actual Cost $17,500*2r = $35,000.
Cost Variance (EV-AC) $33,333.33-$35000 = -$1,666.67
Schedule Variance (EV-PV) $33,333.33-$40,000= -$6,666.67
Cost Performance Index (EV/AC) $33,333.33/$35,000= 0.95
Schedule Performance Index (EV/PV) $33,333.33/$40,000 = 0.83
Estimate At Completion (BAC/CPI) $100,000/0.95 = $105,263.15
Estimate To Completion (EAC-AC) 105263.15-35000 = $70,263.15
Variance At Completion (BAC-EAC) 100000 – 105263.15=-$5,263.15
“Excellence through Knowledge”