Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 18

METHOD OF STATEMENT FOR DRAINAGE PIPE

INSTALLATION INSIDE THE TOILET

(Hot and Cold) Installation

Table of Contents
 Scope
 References
 Abbreviations

 Responsibilities
 Handling, Storage and Transportation
 Material Inspection
 Methodology-Hot and cold water copper piping installation

This method statement for water piping copper (hot and cold) installation is to ensure that
all the area and other related activity is executed safely and in accordance with the project
specifications. This MST establishes all quality assurance/quality control activity is
conducted in a systematic manner, work is inspected and conformance is verified and
documented for the project as specified in specifications and instructions.

Scope
This method statement for water piping installation is applicable to ensure that all hot and
cold water piping copper installations with complete accessories and workmanship are
correct, acceptable, functional, and conform to the project specification and
manufacturer’s recommendation.

References
Project Specifications
Approved Shop Drawings/IFC Drawings
Approved Material Submittal
Abbreviations
QC Quality Control
QA Quality Assurance
HSE Health, Safety and Environment
MEP Mechanical, Electrical & Plumbing
ITP Inspection & Test Plan
MST Method Statement
PPE Personal Protective Equipment
MSDS – Material safety data sheets
RSK Risk Assessment
PQP Project Quality Plan
QCP Quality Control Procedure
INR Inspection Request

Responsibilities
General

1. The Project Manager (MEP) will be responsible to manage, execute, complete and
handover the construction activities within approved budgets and resources in
compliance with Project Requirements as specified in Project Specifications. He
will be overall in charge of implementing the Method Statement in accordance
with QA/QC and HSE requirements.
2. The Construction Manager will be responsible for managing construction
activities and will lead and communicate with site Supervision, Subcontractors,
and vendors to assist them in working on the project schedule by conforming to
QA/QC and HSE requirements at the site.
3. HSE Manager will be responsible for plan, coordinate, and implement issues and
directives within the organization. He ensures safe environmental working
conditions for all employees.
4. QA/QC Manager will be responsible for supporting the project team in
implementing and maintaining Quality Management System for the project
through PQP, ITP, MST, and Procedures in compliance with project
specifications, codes, and standards.
5. HSE Officer will ensure enforcement of safety procedures in accordance with the
approved HSE Plan. Will be closely monitoring the site engineer’s strict
implementation of the MS and Risk Assessment, the use of proper tools and
equipment to maintain safety certifications of equipment and their adherence to
safety regulations, reporting of any unsafe work, or stopping work that does not
comply with HSE procedures.
6. The Site Engineer will be responsible for carrying out all construction-related
activities with compliance to HSE and QA/QC requirements as per contract
specifications, drawings/documents, codes, and standards.

7. QA/QC Engineer will be responsible for conducting inspections as per PQP.


8. The supervisor/foreman will be responsible for coordinating all works and workers
related to the job.
9. Electrician/other tradesmen will be responsible for assisting his superiors during
all construction work-related activities following HSE and QA/QC requirements.
10. Store in-charge receives and inspects all incoming materials and reconciles with
documents; processes and distributes documentation; reports, documents, and
tracks damages and discrepancies.

Handling, Storage and Transportation


1. All materials shall be handled/transported/stored in an optimal way that will not
cause damage to them. Pipe shipping, storage, and handling shall comply with the
manufacturer’s recommendations. The material will be delivered at the site in
undamaged condition, in the manufacturer’s packaging, with identifying labels
intact and legible.
2. Each shipment must be blocked and securely fastened to avoid damages during
transportation.
3. Unloading at the site must be controlled by site management following the
manufacturer’s instructions.
4. Rubber gaskets should be kept clean and away from oil, grease, excessive heat,
and the direct rays of the sun.
5. Pipes are to be checked on unloading. Damaged and defective pipes shall not be
used at the site. The pipe shall be re-inspected just prior to installation. Possible
damages are reported on the delivery note.
6. Pipes or fittings will not be drop or drag.
7. Ensure that the material is stored in the shaded area to protect it from exposure to
direct sunlight.
8. Leave sufficient space between individual pipes.

9. The storage area shall be cleaned and is at an appropriate height from the ground
level. Separate areas in the storage zone must be marked for different materials.
10. Whenever heavy or bulky material is to be moved, the material handling needs
will be evaluated in terms of weight, size, distance, and path of movement.

Material Inspection
For materials to be inspected after receiving at the site, the following points are to be
followed:

Each material item shall be allotted a distinct and separate reference number and
mentioned on the material requisition. Make sure that material is approved/examined by
the consultant and QA/QC and associated documents/test certificates are approved.

 The store in-charge shall ensure that all approved supplies be delivered to the site
as per the approved material submittal; with the manufacturer’s seals, labels, or
other proof of origin intact. These labels and seals shall not be removed until the
material is required for use and shall be retained for inspection by the consultant
and QA/QC.
 The store in-charge shall initiate material inspection for all incoming material to
QA/QC and the material shall be inspected against reference documents and as per
approved material submittal. Moreover, the physical condition of the material shall
be checked. Afterward, an INR shall be raised by QA/QC to the consultant and an
inspection will be carried out by the consultant.

 Materials that do not conform to the given specification/approved material


submittal, shall be rejected. Any discrepancy or damages will be notified and
reported for further action.
 For any materials inspection (especially pipes, fittings, other accessories), the
items shall be segregated as per their type/sizes and placed items separately in
racks or on different pallets.
 Each rack/pallet shall have an identification posted on a laminated paper with the
description of the items clearly written on it.
 There shall be appropriate spaces between the pallets so that the engineer/inspector
can freely go around them and inspect the materials thoroughly.
 Staking the materials all over each other & in one corner is strictly not allowed.

Resources
A. Tools and Equipment
The job will be carried out by manual means. The following are the types of tools
identified for works:

 Measuring Tape.
 Pipe cutter
 Marker

 Copper soldering unit


 Copper threading tool
 Jointing Torch
 Scaffolding and ladder
 Plumber standard toolbox kit.
 PPE (Hand gloves, face masks, safety goggles)
 Safety harness (for high-level work)

All testing equipment and measuring tools to be used shall have a valid calibration
certificate prior to usage.
All lifting equipment and machines shall be 3rd party verified with valid certificates

B. Materials
Material includes but is not limited to the following.
• Copper tubes and fitting as per BSEN 1057, class X
• Approved copper pipes and fittings for Hot and Cold water supply.
• ERW sleeves
• Pipe support

Item Description:
Copper pipes: size range from 15 dia. to 159 dia. mm
Fittings: size range from 15 dia. to 67 dia. mm
Fittings: Size range above 67 dia. mm

Brazing and soldering


a. The material shall be used after being approved through Material Submittals.
b. All material to be used shall conform to the project specification and authorities’
regulations (where required).

C. List of Manpower
 Construction Manager
 Site Engineer
 QA/QC Engineer
 HSE Officer

 Supervisor
 Foreman
 Pipefitters/Installers

 Surveyor
 Helpers
 Forklift Operator
 Certified welders

Note: Certificate shall be presented at the time of commencing installation.

Mobilization
A. Preparation and Planning

Precautions, manpower, and equipment are available before the commencement of work.
The Site Team shall make sure that access roads are always clear from any obstruction
and the site is always accessible.

B. Site clearance

Before commencing the work, the area shall be cleared of all debris, materials, or other
obstructions.

C. Traffic Management

The Site Team with the assistance of the Safety Officers shall coordinate logistics and
materials movement through the site following the direction and road signs displayed on
site. The required diversion routes shall be marked on drawings including the required
traffic signs.

The Work Permits and Operator Certificates shall be compiled and files for reference by
authorized personnel.
Temporary traffic signs, barriers, and flagmen will be deployed to control traffic flow in
accordance with and Traffic Management of the HSE Plan.

At the end of each ramp, there will be a transition area to give the driver the opportunity
to watch the access roads before joining thereto.

D. Pre-construction Safety Meetings:

The meeting shall be scheduled prior to the beginning of the work and before any
Subcontractor starts on the project.

Safety awareness meetings will be conducted every working day morning/every other
day to brief the workforce on the safety prevention measures. The equipment check for
safety shall be recorded/ documented during the daily Safety Awareness Meeting.

Traffic safety will be discussed to emphasize these meetings.

Each worker will be instructed to follow specific safety requirements related to his trade.
They will be required to follow installed safety signs, observe barricades and use PPEs.
The safety team will perform hazard risk analysis by identifying all steps, hazards
identified in those steps, with a focus on the relationship between the work task, the tools,
and the work environment. After identifying uncontrolled hazards; The contractor will
take steps to eliminate or reduce them to an acceptable risk level.

General Contractual Safety, Health, and Environmental requirements:

Roles of the contractor, subcontractors, authorized representatives, and all project


workers.
Accident reporting requirements.
Specific details of the work to be performed along with the use of personal protective
equipment.
Emergency procedure.

E. Operating Procedures:

A site investigation has to be carried out to develop safety precautions and measures prior
to the commencement of the work. After such investigation, relevant signboards will be
displayed and barricades will be installed where and as necessary, such as but not limited
to the following:

Relevant information, advanced signs, warning, and mandatory signs will be placed as
required.
A radio communication system would be used where normal communication is
impossible.
After completion of the work, safety cones and barricades have to be removed
accordingly.

Methodology-Hot and cold water copper


piping installation
The below methodology is based on the manufacturer’s method statement which is
included in the approved material transmittal:

Supervisor/Foreman will carry out the marking routing of copper pipe for hot and cold
water supply pipes as per approved drawings. If there is any discrepancy or difficulty in
executing the work, it is to bring to the notice of the Engineer for corrective action.

Cutting and chasing of pockets for copper pipes, to be done by means of the cutter. If a
hacksaw is used to cut the pipe, a fine-toothed blade shall be used.

Jointing of copper pipes; Clean the outside surface of the pipe and inside surface of the
fitting socket, the reliability of the soldered joint is influenced by the type of flux
used. Yorkshire flux and traditional craftsman flux are specially formulated for jointing
copper pipes with Yorkshire integral solder ring fitting.

Insert the pipe into the fitting until it reaches the pipe stop, then wipe off any excess flux.
Then heat the assembled joint until a complete ring of solder appears at the mouth of the
fittings.

After jointing allows the joint to cool without disturbance, clean the joint generally,
wiping off any external flux residues, this will prevent unsightly stains or corrosion of
pipework.

Threaded connection; jointing washer should be used when installing fittings with
parallel connector thread, a male thread connector a small quantity of inert jointing
compound or PTFE tape should be applied to the male thread before installing the
fittings. As per the manufacturer’s recommendation, the jointing compound should
comply with
BS 6956 Part 5 and be WRAS listed. PTFE tape for water and general application should
comply with BS 7786.
The copper pipes and fittings for hot and cold water supply to be assembled in position
using the torch.

The assembled copper hot and cold water supply pipes and fitting assembly are to be
placed in position by means of a clamp and supports at a specified interval and at the
change of direction. The hydro test will be done in coordination with the consultant prior
to starting the wall packing.

The entire assembly is to be tested with a head of 1.5 times the working pressure of the
system.

Due care to be taken to ensure that the level of the hot and cold water pipes assembly is
not disturbed during packing, plastering, and tiling, and contractors representative will
ensure, throughout the mortar packing process, that no pipes get damaged.

In case of the hot and cold water pipes assembly is running expose above the false ceiling
or on the roof, the copper pipe will be used and proper access for maintenance is to be
provided.

Cut tube square


Cut to the exact length required using a tube cutter or hacksaw If a hacksaw is used, a
sawing fixture should be used to ensure square cuts. Remove all inside and outside burrs
with a reamer, file, or other sharp-edge scraping tool. If the tube is out of round it should
be brought to true dimension and roundness with a sizing tool.

Clean tube end and inside surface of the fitting


The joint surface areas should be clean and free from oil, or oxide contamination.
Surfaces may be properly cleaned for brazing by brushing with a stainless steel wire
brush or by a stiff rubbing with an emery cloth.

If oil or grease is present clean it with a commercial solvent. Remember to remove small
foreign particles such as emery dust, by wiping them with a clean dry cloth. The joint
surface must be clean.

Select brazing alloy


Brazing filler metal selection. When brazing copper to copper, alloys such as Dynaflow,
stay-silv®, or stay-silv® 15 are recommended. These alloys contain phosphorus and are
self-fluxing on copper. When brazing brush or bronze fittings, stay-silv® white flux is
required with these alloys.

When brazing iron, steel, or other ferrous metals, select one of the safety-silv® Brazing
alloys such as safety-silv®45 or safety-slv®56 with stay-silv® with flux. Do not use
phosphorus-bearing alloys as the joint may be brittle.

Perform proper fluxing


Proper fluxing is important because the flux absorbs oxides formed during heating and
promotes the flow of the filler metal. When using Stay-silv® while flux applies it only
with a brush. To prevent excess flux residue inside refrigeration lines, apply a thin layer
of flux to only the male tubing.

Insert the tube into the fitting and, if possible, rotate the fitting once or twice on the tube
to ensure uniform coverage.

Flux application
While flux is used for most applications. Black flux is helpful for long heating cycles or
localized heating with induction. It is also used when brazing stainless steel.

Flux goes through physical changes during heating and turns clear at about
1100°F/593°C. This is an indication that parts are close to the brazing temperature. Stir
Flux before use. If the flux is dried out add a small amount of water unit flux reaches a
paste consistency

Adjust torch flame


Oxygen/acetylene- For most brazing jobs using oxy-acetylene gases, a slightly
carburizing or neutral flame should be used. The neutral flame has a well-defined inner
core. Avoid an oxidizing flame.

Air/acetylene using inferno® swirl Combustion Tips-Brazing with air/acetylene is a


popular alternative to oxygen-mixed fuel gas. The fuel gas flow aspirates air into a mixer
that contains an internal vane that spins the gas to improve combustion and increase
flame temperature.
If the tank has a delivery pressure gauge, set the delivery pressure to 14-15 psi. If the tank
has only a contents gauge delivery pressure is preset at the factory. Open the regulator
adjusting screw all the way by turning it clockwise until it bottoms.

Open the torch valve-opening the torch valve for about ¾ of a turn will provide sufficient
fuel gas delivery. Do not try to meter pressure (reducing the flame) by using the torch
handle valve. If a higher or lower flame is required, change to a different tip size.

Other fuel gases-alternate fuel gases such as propane, propylene, and neutral gas can be
mixed with oxygen for brazing. Refer to the Harris equipment catalog or website for
equipment and setting information.

Heating the joint


Always keep the torch in short motion.

Start heating the tube, by first applying the flame to a point just adjacent to the fitting.

Work the flame alternately around the tube and fitting until both reach brazing
temperature, before applying the brazing filler metal.

When the flux is used. it will be a good temperature guide. Continue heating the tube
until the flux passes the “bubbling” temperature range and becomes quiet, completely
fluid, and transparent. Watch for this on both sides of the joint to ensure even heating

Direct the flame from the tube to the fitting. When the alloy is applied it should quickly
melt and flow into the joint.

Sweep the flame back and forth along the axis of the assembled joint, tube, and fitting to
reach and then maintain uniform heat in both parts.

Apply the brazing alloy


Feed the alloy into the joint between the tube and the fitting. Only after the base metals
have been heated to brazing temperatures should the filler metal be added. At the time
flame may be deflected momentarily to the tip of the filler metal to begin the melting
process.
Always keep both the fitting and the tube heated by playing the flame over the tube and
the fitting as the brazing alloy is drawn into the joint. The brazing alloy will diffuse into
and completely fill all joint areas.

Do not continue feeding brazing alloy after the joint area is filled. Excess fillets do not
improve the quality of the dependability of the braze and are a waste of material.

Making vertical alloy up joints


Heat the tube first, then apply heat to the fitting. It is important to bring both pieces up to
temperature evenly. Keep the flame directed towards the fitting. If the tube is overheated,
the brazing alloy may run down the tube rather than into the joint.

Clean after brazing


All flux residue must be removed for inspection and pressure testing immediately after
the brazing alloy has set quench or apply a wet brush or swab to crack and remove the
flux residue. Use an emery cloth or a wire brush, if necessary.

Separate a brazing joint


First, clean the joint thoroughly, then flux the visible alloy and all adjacent areas of the
tube and fittings. Next, heat the joint (tube and fittings) evenly, especially the flange of
the fitting. When brazing alloy becomes fluid throughout the joint area, the tube can be
easily removed. To re-braze, the joint, clean the tube end and the inside of the fitting
and proceed as directed to make a new brazed joint.

Nitrogen purge
During braze heating, an oxide scale forms on the inside of the copper tube. These dark
scales flake off and are carried by refrigerant and can potentially clog small orifices.

For HVAC/R and medical gas, installations flow nitrogen through the tube during
brazing to prevent internal scale information. Use a low flow rate to avoid excess
pressure inside the tube. A small hole at the line end will allow the nitrogen to escape.

Pipe penetrating the walls and slab


Where pipe passes through floor, slabs, walls, the roof, or penetrate any other form of
construction, pipe sleeve shall be supplied and accurately placed in the building surface.
The pipe sleeve shall be sized to provide 15 mm clearance around the pipe to be installed
or, where the pipe is to be thermally insulated or otherwise covered, 15 mm clearance
around the covering surface. This clearance space shall be packed with approved fire
resisting material and sealed at both ends with waterproof and fire retardant mastic.

Sleeves shall be of material compatible with the pipe and of length to finish flush with the
finished wall and were passing through floors of length to protrude 6mm above and
below the finished floor and the underside level (soffit).

Roof sleeves shall be provided with water-shedding external cowls and flashing.

Water-protecting pipe sleeves through floors shall be supplied and fixed in the following
location:
In mechanical plant rooms
In kitchen areas, toilets and cleaners’ rooms
In slabs over mechanical and electrical plant rooms
On all floors have a waterproof membrane

The pipe sleeves shall be galvanized mild steel pipe set to extend for the full thickness of
the structural element and 50mm minimum above the finished level.

Wall and floor plates:

Where pipe penetrates walls, floors, or ceilings, (except at plant, equipment, and cleaners
rooms or other storage areas) split type chromium-plated steel wall plates shall be fixed
to closely fit the building surface and provide a neat appearance.

Supports and hangers


All supports system shall be of the correct size, and strength and allow for expansion,
contraction, and anchoring of the piping systems. Full details of hangers and supports
proposed for use shall be submitted before fixing commences.

Vertical drop shall be properly restrained and supported to prevent offset and sway.
Piping at all equipment and valve positions, and at main junctions, shall be adequately
supported to prevent any distortion or transmission of the train to connected equipment or
valves.

Brackets and supports shall be so arranged and set out to allow sufficient access for
adjustment, maintenance, and removal of equipment, valves, and accessories with the
minimum of dismantling and without the need for additional temporary supports after
items are removed.
A proprietary support system for all pipework may be used to achieve technical and
visual compatibility of supports subject to acceptance by the Engineer.

Piping shall be supported by the use of rollers and chairs, guides, clips, or hangers fixed
at intervals scheduled. Where two or more pipes are to be carried out by a single support,
the support spacing shall be for the shorter interval.

All mild steel sections, plates, clamps, and fixing devices for fastening hangers and
supports shall be provided by the contractor.

Hangers for cold piping required to be thermally insulated shall be provided with high-
density foam insulation (reinforced where necessary) bearing inserts capable of
withstanding the clamp compression and allowing the hanger to support the pipe without
metal-to-metal contact.

Insert shall be of the same thickness as the thermal insulation required and valve
extended cylindrical insulation shield of galvanized sheet steel or glass fiber reinforced
plastic of not less than 2mm thickness with adequately sealed joints to maintain vapor
barrier where applied.

Support and hangers for mild steel piping shall be ferrous. Supports and hangers for
copper piping shall be non-ferrous, or alternatively may be ferrous with an insert
separation liner to prevent electrolytic action. Supports and hangers for chromium-plated
or stainless steel piping shall be chromium-plated.

Spacing for piping support shall be as follows:

Pipe Material Pipe Size (Diameter in mm) Horizontal (m)

uPVC 25-40 1.1

50-80 1.4

100 1.9

150 2.3
Copper & Stainless Steel 15-22 1.2

28 1.5

35-54 1.8

65-108 2.4

133 3.0

159 3.7

Table for Support Distance

Pipe Size (DN mm) Rod Diameter (mm)

15-25 6

32-80 10

100-150 12

200-250 16

300 20

400-450 24

500-600 30
Pipe Rod Sizes

Health, Safety, and Environment


I. Risk Assessment:

Risk Assessment/Job Hazard analysis as provided/attached in the method statement for


water piping copper (hot and cold) installation.

II. Protective and Safety Equipment

All workers involved shall be equipped with adequate PPE as stated below:

• Safety helmet with company logo


• Safety boots, safety goggles, hand gloves
• High visibility vest
• Welding specific PPE (Welding vest, mask, gloves, visor)
• Twin tail harness, max 1 m long (when working on height)

All special PPE (Harness) is considered as a last resort when it cannot engineer,
administratively eliminate, or guard against hazards.

III. Information to Personnel


• Safety Induction
• Job Training
• Superintendents
• Notices/Memos
• Toolbox Talks
• Briefings before starting work

IV. Emergency Procedures :

The contractor shall provide first aid kits on site for handling light injuries.

In the event of an emergency, all workers will be asked to evacuate and assemble at the
“ASSEMBLY POINT” and wait for further instruction from supervisors.
Quality Assurance and Quality Control for
Method Statement for Water Piping Copper
(Hot and Cold)
a. Quality Assurance Requirements
The contractor shall provide the required documents for the consultant’s approval prior to
initiating the execution of this activity as per project specification.

The quality control requirement shall include related QCP’s, ITP’s and other related
documents as applicable.

Applicable codes and standards for materials are project specifications and contract
requirements.

Quality Assurance Process


The contractor shall notify the engineer prior to the start of the activity and comments
from the site Instruction will be complied with the satisfaction of the consultant.

Follow up and Evaluation


Follow up on quality performance shall be carried out through an in-house monitoring
system such as progress reporting to the planning department, daily, weekly and monthly
reports generated by the planning department to closely
monitor site performance in general and reflect on quality performance in specific.

All the above shall be conducted in close coordination with the quality department to
monitor any deviations from the normal quality requirement and induce corrective
actions whenever required to eliminate non-conformance or
quality deviations.

All remedial actions to be taken, if any, shall take into account the official schedule
which is to be used as a guideline for performance and most importantly under the close
supervision of the quality control department.

Records
• Checklists (CL)
• Inspection Request (INR)
• Inspection and Test Record (ITR)

How to solder copper pipe the correct way (Method Statement for Water Piping (Hot & Cold)
Installation)

You might also like