Professional Documents
Culture Documents
L2 3 Concrete Works Note
L2 3 Concrete Works Note
Lesson Overview
This lesson discusses the process of quantifying and costing of Concrete works
which includes the materials for Concrete, Formworks, Falseworks, Scaffolding,
Reinforcements.
By the end of this lesson, the student must be able to apply the skills necessary for
estimating concrete works.
Concrete Works cover a large scope, however, this usually use the following
materials:
a. Concrete refers to the stone-like material that consists of a binder and
aggregates. In a regular concrete, the materials used are usually cement, as the
binder, and Sand and Gravel, as your aggregate.
1. Cement, usually Hydraulic Cement, is a power compound that reacts with
water and solidifies to bind the aggregates. Cement are usually sold in 40 kg
bags but may also be sold in 1 ton bags.
2. Sand to be used for concrete works are usually river sand. These are
normally sold by cubic meters.
3. Gravel to be used for concrete works may be natural gravel, usually 1” in
size, or crushed gravel, usually ¾” in size. These are normally sold by cubic
meters.
Mixtures of Concrete
Concrete mixtures are based on the required strength for a member. The table
below shows the most common proportions of the materials to achieve specific
strengths.
Proportion
Potential Mixture
Fine Coarse
Strength, psi Class Cement
Aggregate Aggregate
4000 AA 1 1½ 3
3500 A 1 2 4
3000 B 1 2½ 5
2500 C 1 3 6
1
CEng 134n: Quantity Surveying
Module 02: Bill of Quantities
Hooks
Bends
2
CEng 134n: Quantity Surveying
Module 02: Bill of Quantities
2. Tie Wire is a material that is used to affix two intersecting rebars. These tie
wires are usuall Galvanized Iron (G.I.) wires that are catergorized by wire
gauge and are cut at 400 mm lengths in preparation for installion. In the
construction, the usual tie wire to be used is usually Ga. 16 G.I. Tie wires
which are sold in kilograms and has an approximate length of 50-53 meters.
Note:
• Lapping is based on the thickness of the
form but us usually set at 50 mm
3
CEng 134n: Quantity Surveying
Module 02: Bill of Quantities
Note:
• Ideal Spacing for both
vertical and horizontal
stud spacing is at 400
mm maximum.
Note:
• Lapping is based on the thickness of the form but us usually set at 50 mm
• Ideal Spacing for both vertical and horizontal stud spacing is at 400 mm
maximum.
4
CEng 134n: Quantity Surveying
Module 02: Bill of Quantities
Note:
• Ideal Spacing for both vertical and horizontal stud spacing is at 400 mm
maximum.
2. Falseworks are materials that supports the forms in place. These are usually
made using wood or steel tubes.
3. Scaffolding are materials that supports the personnel and equipment during
the casting/pouring, setting, and curring of concrete. These are usually made
the same way as the falseworks.
5
CEng 134n: Quantity Surveying
Module 02: Bill of Quantities
B. Quantity Take-off
Quantifying Concrete Works depends on the materials being used. Below are the
different methods in quantifying the materials presented on the previous section.
a. Quantifying Concrete
1. Determing the Volume of Concrete (VC) to be quantified.
2. Multiply the Volume of Concrete (VC) with the required materials per cubic
meters of concrete to determine the Quantities for each Material.
Quantity of Materials
Proportion
Mixture
Cement Sand Gravel
Class
40 kg. Bags (cu.M.) (cu.M.)
AA 12 0.50 1.00
A 9 0.50 1.00
B 7.5 0.50 1.00
C 6 0.50 1.00
Source: Simplified Construction Estimates, M.B. Fajardo Jr.
6
CEng 134n: Quantity Surveying
Module 02: Bill of Quantities
f. Quantifying Falseworks
1. Calculate the quantity required for Flaseworks using the table below.
Columns Beams (bd ft per Floor (bd ft
Lumber
(bd ft per Meter of Height) Meter of Length) per Sq. M)
Size
Vert. Hor. Brace Vert. Hor.
2” x 2” 4.70 21.00 11.70 4.00 4.70 6.10
2” x 3” 7.00 31.67 17.50 6.00 7.00 9.10
2” x 4” 9.35 42.25 23.35 8.00 9.35 12.10
7
CEng 134n: Quantity Surveying
Module 02: Bill of Quantities
C. Cost Computation
Cost for Concrete Works will vary based on the units based on the commercially
available material. As a general process, the quantities determined are then
multiplied by the cost per unit of the material to determine the total cost.
End of Lesson