Refrigerant Compressor Selection & Liquefaction Study - Original

Activity ID Activity Name Original Start Finish 2019 2020


Duration Nov Dec Jan Feb Mar Apr May Jun Jul Aug
60 61 62 63 64 65 66 67 68 69
Survey and Study
St
Study for FEED
FEE
Refrigerant Compressor
Comp Package & Liquefaction Licensor Selection Study
Refrigerant Compr
Compressor Package
LIQEXE-1000 Kick Off Meeting 1.0d 18-Nov-19* 18-Nov-19
LIQEXE-1011 Define and agree on a facility configuration 4.0d 19-Nov-19 22-Nov-19
LIQEXE-1020 Define and agree on cases to be simulated 4.0d 19-Nov-19 22-Nov-19
LIQEXE-1030 Develop technology novelty assessment plan 15.0d 25-Nov-19 13-Dec-19
LIQEXE-1040 Agree GT ISO/site rated power 4.0d 19-Nov-19 22-Nov-19
LIQEXE-1050 Process simulations for each configuration 25.0d 25-Nov-19 27-Dec-19
LIQEXE-1060 Prepare capacity report 10.0d 23-Dec-19 03-Jan-20
LIQEXE-1070 Prepare specifications - Rotating equipment 30.0d 25-Nov-19 03-Jan-20
LIQEXE-1080 Prepare datasheets - Rotating equipment 10.0d 23-Dec-19 03-Jan-20
LIQEXE-1090 Prepare Liquefaction BoD - for CTR-002 20.0d 16-Dec-19 10-Jan-20
LIQEXE-1100 Prepare RFQ for GTs/refrigerant compressors 15.0d 16-Dec-19 03-Jan-20
LIQEXE-1110 Issue RFQ for GTs/refrigerant compressors 0.0d 03-Jan-20
LIQEXE-1120 Engage with GTsuppliers and hold price and novelty meetings - includ 45.0d 03-Dec-19 03-Feb-20
LIQEXE-1130 Receive Vendors Proposals 0.0d 03-Feb-20
LIQEXE-1140 Review layout implications 10.0d 30-Dec-19 10-Jan-20
LIQEXE-1150 Review equipment /unit sizing - Preliminary Design 15.0d 30-Dec-19 17-Jan-20
LIQEXE-1160 Develop 'delta' equpiment lists 15.0d 06-Jan-20 24-Jan-20
LIQEXE-1170 Develop OOM 'delta' equipment cost estimates 15.0d 13-Jan-20 31-Jan-20
LIQEXE-1180 Issue refrigerant compressor package selection report 25.0d 20-Jan-20 21-Feb-20
LIQEXE-1190 Perform technical novelty assurance plan workshop 5.0d 17-Feb-20 21-Feb-20
LIQEXE-1200 Prepare Technology / Novelty Assessment Report & Plan for FEED/EP 10.0d 17-Feb-20 28-Feb-20
LIQEXE-1210 End of CTR-001 0.0d 28-Feb-20
LIQEXE-1220 Internal and stakeholder Alignment 20.0d 02-Mar-20 27-Mar-20
Liquefaction Licen
Licensor Selection Study
LIQEXE-2000 Confidentiality Agreements with Licensors 30.0d 25-Nov-19 07-Jan-20
LIQEXE-2010 Define and agree configuration and cases to be simulated 5.0d 09-Mar-20 13-Mar-20
LIQEXE-2020 Prepare liquefaction BoO to Licensors 20.0d 23-Dec-19 21-Jan-20
LIQEXE-2030 Update the liquefaction BoO to Licensors 5.0d 09-Mar-20 13-Mar-20
LIQEXE-2040 Issue the liquefaction BoO to Licensors 5.0d 16-Mar-20 20-Mar-20
LIQEXE-2050 Prepare SoW and RFQ to Licensors (Initial) 20.0d 08-Jan-20 04-Feb-20
LIQEXE-2060 Update SoW and RFQ to Licensors 20.0d 09-Mar-20 06-Apr-20
LIQEXE-2070 Kick off with Licensors 0.0d 06-Apr-20
LIQEXE-2080 Issue SoW and RFQ to Licensors 5.0d 07-Apr-20 14-Apr-20
LIQEXE-2090 Engagement with Licensors 50.0d 15-Apr-20 30-Jun-20
LIQEXE-2100 Receive Licensors proposals 0.0d 24-Jun-20
LIQEXE-2110 Review and evaluate Licensors packages 15.0d 24-Jun-20 14-Jul-20
LIQEXE-2120 Issue Licensor Selection Report 15.0d 08-Jul-20 28-Jul-20
LIQEXE-2130 End of CTR-002 0.0d 28-Jul-20

Remaining Level of Effort Date Revision Checked Approved

Actual Work
Forecast
Critical Remaining Work
Milestone