Professional Documents
Culture Documents
CM04 - LOFTY Variation Report Structure V1
CM04 - LOFTY Variation Report Structure V1
1.1. Overview of the Claim 1.2. Key Conclusions 1.3. Summary of Recommended Actions
Section 2: Introduction
2.1. Background of the Project 2.2. Purpose of the Report 2.3. Scope of the Variations
3.1. Contract Review 3.2. Variation Clauses and Conditions 3.3. Parties' Obligations and
Rights
4.1. Chronology of Variation Orders 4.2. Detailed Description of Each Variation 4.2.1.
Variation in Quantities 4.2.2. Scope Changes 4.2.3. Specification Alterations
5.1. Impact on Project Schedule 5.2. Effect on Project Scope and Quality 5.3. Resource
and Material Implications 5.3.1. Labor Impact 5.3.2. Material Requirement Changes 5.3.3.
Equipment Utilization
6.1. Overview of Variation Costs 6.2. Direct Cost Analysis 6.2.1. Additional Labor Costs
6.2.2. Additional Material Costs 6.2.3. Equipment and Plant Costs 6.3. Indirect Cost and
Overhead Analysis 6.3.1. Administrative Expenses 6.3.2. Financing Costs 6.3.3. Other
Related Indirect Costs
8.1. Preparation of Claim Documentation 8.2. Evidence and Supporting Documents 8.2.1.
Variation Orders and Correspondence 8.2.2. Cost Records and Invoices 8.2.3.
Photographic and Video Evidence
9.1. Approach for Claim Negotiation 9.2. Dispute Resolution Mechanisms 9.2.1.
Mediation and Arbitration 9.2.2. Legal Proceedings
10.1. Final Assessment of the Variations 10.2. Recommendations for Settlement 10.3.
Lessons Learned and Future Guidelines
Appendices
References