Professional Documents
Culture Documents
Consultant's Report For The Week Feb 6 To Feb11, 2023-Signed
Consultant's Report For The Week Feb 6 To Feb11, 2023-Signed
Consultant's Report For The Week Feb 6 To Feb11, 2023-Signed
11/F Ri-Rance Corporate Center 1, Block 2, Lot 16, Aseana City, Tambo, Paranaque City, Philippines 1701
MEMORANDUM
Hi Sir,
Good day!
Sharing Consultant’s Report for the Week
Feb 6
UDMC Project
Quality Control assessment works – Recommendation to Organize for T&C works
@Vince Abrigo @Alvin Ibo Adraneda @Jericho David @Patrick Tolentino
Please organize our engineers and tools(thermal imager, ampere, velocity meter, measuring tape)
and conduct QC works for UDMC. Get AlvinA, Jericho, PatrickT and Vince and CheloL to
complete the works within the day. To inspect all source of air infiltration
1. Measure the exit doors,
2. Measure the entrance doors
3. Measure the fresh air duct
4. Thermal scan all rooms, fresh air ducts, ac, lighting, people entry point, open ceiling and
picture of each thermal scan data.
5. Get all data for unconditioned fresh air supply even though not part of gree
6. Get electrical data, lighting, equipment, etc
7. Validate air velocity on all entry points and areas where there is presence of unconditioned.
8. Get sample of insulation material used
9. Get ambient room temperature and rh
10. Get outdoor air temperature and rh
11. Get inside ceiling temperature and Rh
12. Used our Gree GMV Commissioning laptop and get actual data. Informed Engr. Manuel on
all works needed to complete
1|Page
UNITECH PHILIPPINES INDUSTRIAL MACHINERY INC.
11/F Ri-Rance Corporate Center 1, Block 2, Lot 16, Aseana City, Tambo, Paranaque City, Philippines 1701
1.Initial inspection as per site visit conducted with Engr Romano and Engr Tan of TCR
1.1 Findings
1.1.1 Excessive amount of unconditioned air circulating at the following spaces
1.1.1.1 Emergency room
1.1.1.1.1 Adjacent exit stairs, use as interstitial access between floors
1.1.1.1.2 Adjacent toilet area
1.1.1.2 Hallway –cashier area
1.1.1.3 Philhealth area
1.1.1.4 Elevator Lobby
1.1.1.5 Ceiling interstitial spaces
1.2 Initial QC assessment to be done
1.2.1 Thermal scanning on the following spaces mentioned in item 1.1.1
1.2.2 Assessment on the amount of air infiltration on all mentioned spaces
1.2.3 Assessment on the amount of air leakage emanating from the unconditioned fresh air
adajacent to refrigerant piping installation
1.2.3 Assessment on the amount of air infiltration from main lobby/elevator entrance area
1.2.4 Assessment on the amount of air infiltration from the emergency entrance area
1.3 Conduct and submit GMV Computer simulation status on equipment performance. Use of
GMV debugging equipment with printed report
1.4 Conduct air flow testing/take off on all other spaces. Calculate air infiltrated
Please note that air infiltration should not exceed 5-10% of the total airflow of installed AC in
order not to experience presence of moisture and water condensation leaks on AC equipment and
piping reticulation. Submit all other findings afterwards for complete assessment.
Overall assessment
1. There is present stack effect conditions due to thermal difference between outside
temperature and indoor temperature specifically during cool season of the months
2. There is sufficient wind pressure pressure emanating from door opening and closing
3. There is an observable conditions combining tjhermal and wind pressure
4. There is observable presence of unconditioned forced air inside spaces and ceiling
5. Contributary nature of generator system will be an additional effect on the present
operation of airconditioning system.
6. The intent to provide unconditioned ducted fresh air for the whole space is a indicative
source of high humidity forced air infiltration affecting thermal gradient on installed
refrigerant piping
7. There is a need to validate the specifications of refrigerant piping insulation if the
insulation thickness and density can handle system requirement during full Ac load
operations.
8. TCR-GREE to provide GMV Computer Simulation report for the equipment performance
based on initial start-up and post construction operations
2|Page
UNITECH PHILIPPINES INDUSTRIAL MACHINERY INC.
11/F Ri-Rance Corporate Center 1, Block 2, Lot 16, Aseana City, Tambo, Paranaque City, Philippines 1701
Feb 7
Discussion with Albert of Bidworks for One Shang Tower
1. Equipment selection
2. Gree selection software available equipment
Feb 8
Discussion with AlbertFiel on Masagana Supermart
As discussed, please see recommended action.
Options that we can offer to Masagana based on available chillers for 50TR capacity
1. use of 2 units of 36tr LSQ 130, LSQ160 MODEL
2. use of 1-units - 22tr + 1 unit 36tr, 230v, 3phase, MODEL LSQ80 and LSQ130
3. use of 2 units 41.23tr LSQ 160
We can design the whole chiller plant including the chilled water pumps. Cost of design is at 1,220 pesos
per sqm deductible on the overall proposal should they award to us the project.
Feb 9
Discussion with Patrick M on 7th floor Server room
1. Three options presented
1.1 Option 1 – design of AC inside the IT server room
1.2 Option 2 - design of AC adjacent to IT room only
1.3 Option 3 – ducted design
2. Option presented, ducted will be the highest BOQ at Php223k
3|Page
UNITECH PHILIPPINES INDUSTRIAL MACHINERY INC.
11/F Ri-Rance Corporate Center 1, Block 2, Lot 16, Aseana City, Tambo, Paranaque City, Philippines 1701
Feb 10
1.Meeting with Pump supplier KSB, german brand
2.AHU Testing for Unitop Legaspi. To validate the actual airflow, power
2.1 To coordinate with Engr Ariel on the previous information for pulley size and belt size as per
installation completed for Unitop Dasmarinas
Feb 11
1. Discussion on the M&E T&C Standards
2. ASHRAE Journal for February 2023
Thank you.
/REC/File
4|Page