Professional Documents
Culture Documents
Section 3 - Earthworks WATER
Section 3 - Earthworks WATER
Section 3 - Earthworks WATER
SECTION 3: EARTHWORKS
ECOPF0514P 29
SECTION 3
EARTHWORKS
The whole of the excavation shown on the drawing for the several parts of the work
shall be carried out to the exact lines and levels, widths, lengths and depths
indicated on the drawings or to such other dimensions as may be directed.
No excavation, for any purpose whatever, shall be made on the site except as shown
on the drawings without the permission in writing of the Engineer.
The areas to be occupied by permanent work shall be cleared of all trees, brush,
stumps, roots, grass, weeds and decayed vegetable matter. Outside these areas or in
borrow areas the Engineer may require that selected trees or shrubs shall not be
disturbed.
Tree roots shall be grubbed up, and trees of girth greater than 1 metre measured 1
metre above the ground shall be logged and stacked. All timber shall remain the
property of the Employer, or alternatively the landowner where the work is being
carried out in a way-leave or easement.
Where directed, the excavations left by the removal of trees shall be backfilled and
consolidated to ground level. Such excavation, if they are below or contiguous to
structural foundations shall be filled with concrete as directed. Concrete so used
will be measured and paid for at rates given in the Bill of Quantities.
All vegetable debris shall be disposed of by burning and other debris shall be
disposed of as directed by the Engineer. Care shall be taken in the control and
lighting of fires to ensure that they do not spread. All surplus soil from site clearing
operations shall be left in windrows or spread as directed by the Engineer. Care
shall be taken to remove all grass and roots etc., which would, in the Engineer's
opinion adversely affect the consolidation and stability of completed earthworks.
ECOPF0514P 30
3.4 SOIL STRIPPING
Where directed by the Engineer, or shown on the drawings, the Contractor shall
remove all topsoil to average depths of 150 mm as and where directed by the
Engineer, and deposit this separately from all other excavated materials in neat
stock piles, where directed. Alternatively, the Engineer may direct that this soil be
spread evenly over the surrounding area.
a. Trench Excavation
All trench excavations and related quantities, including rock, shall be based
on the trench widths specified above, and the Contractor shall allow in his
rates for any additional working space required for the making of joints, and
for the trimming of trenches to the correct grades, all to the satisfaction of
the Engineer, and also for the provision of adequate bedding depths or
specially shaped trench bottoms in accordance with the requirements of
Section 5 of this Specification.
b. Back-filling
Backfilling shall be carried out as soon as possible after the pipework has
successfully passed the inspection and has been approved in writing by the
Engineer. Specially selected material without stones or other substances
that in the opinion of the Engineer might cause damage to the permanent
work shall be used for filling around the pipework and to the height of at
least 150 mm above it. This material shall be thoroughly and evenly
compacted to give the pipework maximum support from the trench sides
and shall be carried out in such a manner that the pipework be continued by
replacing selected excavated material in 150 mm layers measured after
compaction.
Each layer shall be well rammed and consolidated before the succeeding
layer is placed. Where ramming is done by hand the proportion of rammers
to fillers shall be three to one. If so directed by the Engineer, water shall be
ECOPF0514P 31
used, which the Contractor shall supply at his own cost. Backfilling of the
trench by mechanical excavator or bulldozer shall not be permitted. No
vegetation and fibrous material shall be included in the backfilling.
At the ground surface the filling shall be banked to about 150 mm above the
level of the adjacent ground surface and shall be maintained in this
condition until the completion of the period of maintenance.
The Contractor shall remove any excavated material, which the Engineer
considers to be unsuitable for backfill from site, and any subsequent lack of
excavated backfill material shall be made good with material as, ordered by
the Engineer in writing and paid for under Provisional Items in the Bill of
Quantities
c. Stabilised Backfill
The material shall be dry mixed by either mixer or hand so that all
aggregations of material are broken down into individual particles. The
correct mass of cement shall then be added and the material dry mixed until
a completely uniform tilth is obtained.
The excavation rates should include for backfilling above base slabs and
around foundation walls as shown on the drawings and generally in
accordance with Clause 3.5.1. (b) Above.
In general terms, this excavation shall be measured under two items. The
first is a cut or borrow to fill and compact item, which will be measured as
compacted fill, and the second is a cut to spoil item, which will be measured
as an insitu volume before excavation.
The Contractors tendered rates in the Bill of Quantities shall include for all
expenses necessary for complying with the Specification.
Fills shall be constructed on the lines, levels, side slopes, grades, densities,
etc., indicated and directed on the drawings. The material used for fill
construction shall be selected and approved as specified or shown on the
drawings and shall be free from all deleterious matter. The item in the Bill
of Quantities for fill is based on a free haul of one kilometre for all fills
measured. Overhaul instructed, shall be measured separately.
The Engineer reserves the right to control excavation and to direct where
materials arising from cut shall be deposited and how and where they shall
be used, and also to direct where borrow materials, which may be essential
for fill, shall be obtained. This shall also include the control of the use of
rock spoil in rock fill embankment.
Before commencing work the Contractor shall ensure that he has adequate
instructions concerning the use of spoil from cut. No claims for double
handling will be considered.
The item in the Bill of Quantities for fill makes no distinction as to the
source of fill material, but fill material shall be obtained from cut when-ever
it is reasonable in the Engineer's opinion to do so.
b. Cut to Spoil
ECOPF0514P 33
Where any inferior material is encountered in the construction of the
earthwork, or where there is an excess of excavation over fill, the material
concerned shall, where directed, be cut to spoil in positions directed by the
Engineer.
Before replacing the selected fill, the anthill shall be poisoned with an
approved pesticide.
c. Method of Compaction
ii.) Any water required before the material is compacted shall be added
to the material in successive applications by means of water
sprinklers fitted with proper sprinkler bars, or by means of pressure
distributors, all capable of applying the water evenly and uniformly
over the area concerned.
ECOPF0514P 34
The material is to be compacted at the optimum moisture for MOD
AASHTO density with an allowable tolerance of plus-one (1)
percent or minus-two (2) percentage of moisture of weight of dry
material. Should the mixture be too wet, due to rain or any other
cause, it shall be harrowed and allowed to dry out to a moisture
content conforming to the above requirements before compaction
proceeds.
Rock fill embankments shall have all interstices filled with approved
fill material and shall be compacted to the maximum possible state
of consolidation with all rocks in contact with adjacent rocks on all
faces. This shall normally be achieved by subjecting each layer to at
least eight (8) passes of a towed vibrating roller weighing not less
than 3 tons dead weight, or other approved plant.
d. Tolerances
ECOPF0514P 35
Position, Dimensions, Levels, Etc.
The degree of accuracy of the finished work shall be within the following limits
[3] Foundation
(i.e. level of underside of concrete
except to floor slab) PD in level of surface of +75 +50 +25
excavation trimmed to receive concrete
[4] Level
PD from design level with reference to
+20 +15 +10
the nearest transferred bench mark
ECOPF0514P 36
[4] Slopes of top surfaces
PD from direction of slope
PD from rate of fall Nil Nil Nil
1 in 100 to 1 in 300 20% 10% 5%
1 in 400 and flatter 10% 5% 2%
The permissible deviation from OMC and density shall, except where otherwise
specified, be as given below, appropriate to the degree of accuracy specified for a
particular class of work
-2%
(1) OMC in field during compaction +2% -2% +1% +0%
(2) Specified density (where it does not 0% 0% 0%
conflict with the statistical control of No top No top +2%
acceptance) limit limit No top
limit
e) Soil Testing
i.) General
During the progress of the works, the Contractor shall have tests
taken and results submitted to the Engineer, on the materials and
workmanship in order to ensure compliance with the specification.
All testing shall comply with SAZS. 185 Part 1 and Part 2 Method
of Testing Soils for Civil Engineering Purposes'.
ECOPF0514P 37
After a visual acceptance of a completed section of the works, a
number of tests are to be carried out to ensure compliance with the
specifications. Frequency of these tests shall be as in the table
following: -
An approved laboratory shall carry out all testing and the Contractor
is to supply the name of the proposed soils laboratory for approval
before work commences.
Or
ECOPF0514P 38
ii. Solid unweathered crystalline material in bulk or in banks or ledges,
which in the Engineer's opinion, cannot be broken up or removed,
except by the use of explosives.
"Hard"
"Soft"
b. Measurement of Rock
In all cases excavation in "Rock" shall be paid for on the net volume to be
removed only and no payment will be made in respect of over-break.
Rock Excavation
Hard Excavation
Common Excavation
All material other than Rock and Hard Excavation is classified as Common
Excavation. Where it is estimated that less than 75% of any excavation
consists of boulder material, the excavation will be measured and paid for as
common excavation.
ECOPF0514P 39
3.7 EXCESS EXCAVATION
In the event of any excavation being carried out wider or deeper than authorised, the
Contractor, at his own expense, shall fill them in with approved fill, to the required
dimensions or levels to a density of at least equal to the density of the surrounding
soil. If the excess excavation occurs under structures, the backfill shall be concrete,
as directed by the Engineer, all at the Contractor's expense.
Water shall not be allowed to accumulate at any part of the workings. The
Contractor shall take all risks from water, clean or foul, whatever the source or
cause may be, and shall at his own expense, effectually drain and keep dry all the
works during construction and take due care to prevent surface water soaking in.
All side channels, sumps or temporary excavations for dewatering shall be formed,
maintained and used, outside of and clear of the man works, and shall be properly
filled in when their use ceases.
3.9 BLASTING
Should any damage occur, the Contractor shall, at his own expense, carry out such
work of repair or restoration as the Engineer may direct and shall be fully and solely
responsible for such damage or any claims that may arise there from. Care shall be
taken that no undischarged cartridges are left in the excavation. The Contractor's
attention is drawn to the explosive regulations outlined - Zimbabwe Government
Notice 531 to 535 inclusive and 1271.
Should blasting be likely to interfere with the operations of any other Contractors,
times will be set by the Engineer for such blasting, if authorised. The Contractor
shall give adequate warning to such other Contractors or to road users or any other
persons in the neighbourhood that blasting is about to take place. Careless or
indiscriminate use of explosives will result in the Engineer withdrawing permission
for their use, and, under such circumstances the Contractor shall resort to other
methods of excavation.
The unit rates quoted in the Bill of Quantities for excavation shall include for the
use of all timber and for all labour in placing and withdrawing the timber required
for properly supporting and timbering the works in such a manner as to ensure the
safety of workmen shall be complied with. The Contractor shall be held entirely
responsible for any accident, subsidence, slip or damage caused by defective or
insufficient timbering, careless workmanship or any other cause whatsoever and for
all costs involved, including reinstatement. The Contractor’s attention is drawn to
the relevant clauses in the Factory’s Act. I.e.
Factory and Works (Building, Structural and Excavation Works) Regulations RGN
264/76
Material from excavation shall be used or disposed of under the direction of the
Engineer. Surplus material from trench or other construction or material such as
refuse and anthills, which is unsuitable for backfilling and/or the construction of
fills, shall be disposed of by stockpiling adjacent to borrow pits for future use as
backfilling in rehabilitating the pits where applicable or as directed by the Engineer.
Excavated material shall not be wasted indiscriminately and the Contractor shall
first obtain the Engineer's approval before spoiling any material arising from
excavations.
Should the Engineer decide that local spreading of surplus spoil is not desirable, the
Contractor shall load up, cart, unload, spread and level to the approval of the
Engineer, all included in the basic excavation rate.
In the case of trench excavation, the Engineer reserves the right to direct the
Contractor to stack spoil on one side of the trench only in existing business and
residential areas and to provide gaps in the windrows so formed for pedestrians and
vehicular crossings.
Spoil heaps shall be such as to cause a minimum of inconvenience to the public and
traffic and to disrupt kerb line parking for as short a period as possible, and shall be
of such a height as will not interfere with driver vision.
Where the use of outside shutters is made necessary through any action of the
Contractor, which is contrary to the Specification, then no payment shall be made
for either the working space or the outside shuttering.
Where shown on the drawings or instructed by the Engineer, top soiling and
grassing of earthworks shall be carried out.
The Contractor shall ensure that the earthworks are correct, as regards density,
shape, line and level before starting top soiling operations.
Topsoil shall be taken from approved stockpiles and spread uniformly over the
designated area to a depth of 100 mm measured normal to the slope after light
rolling. The layer of topsoil shall be rolled with a hand roller to seal the surface.
Care shall be taken that no soil is allowed access to any embankment surface drain.
Grass shall be planted in clumps or drills, according to the habit of the grass. Drills
and lines of clumps shall be 200 mm apart measured down the slope of the bank
ECOPF0514P 41
and shall be located horizontally. Clumps shall be not more than 200 mm apart.
The runners shall be staggered on lines normal to the top of the bank to prevent the
formation of erosion channels.
The grass shall be of a runner variety, Starr No. 2 (Couch) or Kikuyu, of a type
suited to local conditions capable of giving a dense ad well-knit sward. The source
and type of grass shall be to the approval of the Engineer.
Plantings shall be kept damp until such time as the grass is properly established.
Should the bank be damaged by rain, wash ways shall be re-paired and the grass be
replanted at the Contractor's expense.
Providing the top soiling and grassing have been properly carried out in accordance
with the Specification and to the satisfaction of the Engineer, the Contractor shall
not be held responsible for any failure of the grass to grow, spread or cover the
surface effectively after the end of the rainy season. Should the Engineer then
decide that any area requires replanting with grass; such replanting shall be
measured as new work.
The Contractor may be called upon to supply fertiliser to the embankment after
planting grass if the rate of growth is unsatisfactory. The fertiliser to be used shall
be an approved proprietary brand, which promotes root development. Fertiliser
shall be applied by placing carefully measured amounts in "dibble" holes punched
into the topsoil. These holes shall be laid out in a square pattern with 300 mm
sides. Fertiliser shall be applied in successive applications of approximately 220 kg
per hectare.
If any unsound material occurs in the bottom of any excavation it shall be removed
and disposed of and the resulting space, shall be filled with 10 Mpa Concrete or as
directed by the Engineer.
Payment for this work will be made at the rates stated in the Bill of Quantities,
provided that the unsoundness of the formation is not due to the Contractor's failure
to keep the excavation free from clean or foul water and also provided that such
work has been ordered by the Engineer (in writing) thereto.
3.15 TERMITES
Where termite nests are encountered on the site the Contractor may be directed to
excavate and remove these and refill and consolidate the resulting hole with a
suitable material. This work shall be paid for at the rates stated in the Bill of
Quantities but no claim for such payment will be considered for holes excavated
unless directed. The Contractor shall state in the Tender Documents his price for
the supply of termite poison and its application by means of watering cans or other
suitable means. The termite poison shall consist of a 5% solution of
ECOPF0514P 42
pentachlorophenol in used engine oil or other approved solvent evenly spread at the
rate of 4,2 litres per square metre and shall be applied only if directed.
Where the removal or demolition of existing structures is called for on the drawings
or in the Bill of Quantities, such structures whether above or below ground shall be
demolished completely and unless otherwise directed, all material resulting from
demolition work shall be collected, stored and handed over to the Employer when
directed. Structures to be demolished shall include buildings of whatever
construction, foundations, floor slabs, fencing, water pipelines, sewers and drains,
manholes, inspection chambers, gulleys, walls, piers, poles anchored in the ground,
wires, cables, culverts, stormwater drains, ditches, sumps, earth and retaining walls,
buried ducts, septic tanks, soakaways and any other structures or portions of
structures which for the purpose of this clause shall be declared to be subject to
demolition work. All structures below ground level shall be grubbed up and
removed and the resulting holes filled with approved material.
The prices tendered and paid for clearing site shall include for all labour,
plant, materials, and cartage in the operations outlined above, as well as for
overheads and Contractor's profits.
Soil stripping shall be measured in square metres and allow for the removal
of 100 mm of topsoil.
Unless otherwise stated in the billed item excavation for pipe trenches will
be paid for per lineal metre run for the particular diameter of pipe at the
depths to invert billed and the rates quoted shall include for excavation in
soft material (Ref Clause 3.6) any extra working room over the trench
widths or depths specified, return fill and ram, spread and level surplus,
timbering, dewatering, working in half road widths and all other contingent
items described or implied herein.
The depths indicated on the drawings are from natural ground level to the
invert level of the pipe and this depth will be used for measurement
purposes. The Contractor must allow in his rates for the extra excavation to
ECOPF0514P 43
the underside of the pipe and the underside of the bedding material where
shown on the drawings.
He must also allow for special shaped trench bottoms where specified and
shown on the drawings and for trimming to grade. Where the natural
ground level has been lowered before trench excavation has commenced,
the depth of the trench will be measured from the reduced ground level.
Rates for excavation are to include for all necessary timbering, dewatering,
stormwater protection, protection of other services, also backfilling and
consolidating where applicable and for additional working space not
elsewhere specifically allowed for.
The rates quoted must allow for all associated operations precautions,
dewatering etc., for backfilling over footings and behind walls, and for
spreading or carting the surplus material to waste.
Payment will be made once only for material moved either from cut or
borrow to fill and cut to spoil. The rate tendered for material hauled must
include allowance for free haul as well as for loading time, waiting and
unloading time etc., which are common to trips of all lengths.
The unit of measurement for fills arising from cut or borrow, shall be the
cubic metre of material measured as Common Excavation in fill after
compaction, and shall be computed by the method of average end areas
from levelled cross sections taken before and after construction of the fill at
20 metre intervals on centre line. All measurement shall be net. The
Contractor's rates shall include for haulage up to one kilometre, unloading,
spreading, application of water and mixing if necessary, compaction to 90%
MOD AASHTO DENSITY and for trimming to final level.
Extra Over payment for Rock and Hard Excavation will be made in
accordance with Clause 3.6
Extra over payments for Rock and Hard Excavation will be made in
accordance with Clause 3.6.
c. Overhaul
Overhaul payments for haul distances greater than one kilometre will be
paid on an m3 km measured basis. The volume of material will be
measured as in (a) and (b) above and the distance will be the overhaul
distance as assessed by the Engineer to the nearest 100-m. The unit of
payment is the product of this volume and distance.
The unit of measurement for stabilised backfill shall be on the cubic metre
compacted volume and the tendered rate shall be paid extra-over trench
excavation and back fill based on the trench widths specified and detailed.
ECOPF0514P 45
finished foundations or within a distance of 600 mm measured from the
shuttered surface.
No excavation for working space shall be paid for except where external
shuttering is directed by the Engineer in substitution for casting concrete
directly against the fact of excavation.
The unit of measurement for top soiling and grassing shall be the square
metre of surface grassed, measured in the plane of the bank.
The price tendered and paid for each square metre of top-soiling and grass
planting shall include full compensation for loading, carting, unloading,
spreading, levelling and seal rolling of topsoil and for procuring and
supplying on site approved fresh grass for planting in drills or clumps, as the
case may be, together with all necessary operations connected therewith, for
such replanting as may be necessary in terms of the Specification
irrespective of the number of items areas may be replanted, as well as for
the provision of all supervision, labour, transport, plant, equipment, tools,
water, irrespective of haul, materials and incidentals necessary to complete,
protect and maintain the work prescribed in this Specification. If any
application of super phosphate at the time of planting (1 kg/m2) is called for
in the Bill of Quantities then this should be allowed for in the tendered rate.
The price tendered and paid for each 50 kg of fertiliser shall include full
compensation for procuring and making available on site approved
fertiliser, for setting out and punching dibble holes and filling such holes
with approved amounts of fertiliser, as well as for the provision of all
supervision, labour, transport, storage, plant, equipment, tools, materials and
incidentals necessary to complete the work in accordance with the
Specification.
Weeding and cutting of grass shall be paid for at dayworks rates, where
instructed by the Engineer. Extra watering of grass not covered by this
Specification, which may be ordered by the Engineer, shall be paid for at
dayworks rates.
3.17.9 Anthills
Nothing shall entitle the Contractor to payment for anthill excavation unless
the Engineer measures the quantities before excavation is commenced.
Anthill excavation shall be paid for at a rate per cubic metre, which shall
include for removal of excavated material to any part of the site within 1
kilometre free haul distance and spreading and levelling as directed.
ECOPF0514P 46