Preliminary Technical Deliverable Register
PROJECT NO: DOCUMENT NO. CONTRACTOR DOCUMENT CONTRACTOR DOCUMENT NO Rev: 0 Date
a
Rev A Document Approval with IFC Issue for Weightage
Start Draft Complete Doc. Status/Remarks
Document Document submission Comments Construction Achieved
Sr. No. Item Description Doc No Latest Rev Dates
Class Type
o
Civil 0% 0% 0%
Page 1 of 3
PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION SERVICE FOR MAJNOON APPRAISAL WELL PAD AND ACCESS ROAD PROJECT FOR GROWTH2
Preliminary Technical Deliverable Register
PROJECT NO: DOCUMENT NO. CONTRACTOR DOCUMENT CONTRACTOR DOCUMENT NO Rev: 0 Date
a
Rev A Document Approval with IFC Issue for Weightage
Start Draft Complete Doc. Status/Remarks
Document Document submission Comments Construction Achieved
Sr. No. Item Description Doc No Latest Rev Dates
Class Type
o
Construction 0% 0% 0%
Elictrical 0% 0% 0%
Page 2 of 3
PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION SERVICE FOR MAJNOON APPRAISAL WELL PAD AND ACCESS ROAD PROJECT FOR GROWTH2
Preliminary Technical Deliverable Register
PROJECT NO: DOCUMENT NO. CONTRACTOR DOCUMENT CONTRACTOR DOCUMENT NO Rev: 0 Date
a
Rev A Document Approval with IFC Issue for Weightage
Start Draft Complete Doc. Status/Remarks
Document Document submission Comments Construction Achieved
Sr. No. Item Description Doc No Latest Rev Dates
Class Type
o
HSE 0% 0% 0%
QA/QC 0% 0% 0%
Planned 2-Nov-14 7-Nov-14 12-Nov-14 17-Nov-14 21-Nov-14
96 Communication and Correspondence Procedure PR Actual 4-Nov-14 18-Nov-14 19-Nov-14 30-Dec-14 1-Jan-15 0.00 0.00 0.00
Forecast
Planned 2-Nov-14 7-Nov-14 12-Nov-14 17-Nov-14 21-Nov-14
97 Quality Matrix PL Actual 2-Nov-14 6-Nov-14 11-Nov-14 16-Nov-14 20-Nov-14 0.00 0.00 0.00
Forecast
Planned 5-Nov-14 7-Nov-14 12-Nov-14 17-Nov-14 21-Nov-14
98 Calibration Procedure PR Actual 5-Nov-14 6-Nov-14 26-Nov-14 20-Dec-14 25-Dec-14 0.00 0.00 0.00
Forecast
Planned 3-Nov-14 7-Nov-14 12-Nov-14 17-Nov-14 21-Nov-14
99 Final Documentation Procedure PR Actual 4-Nov-14 18-Nov-14 20-Nov-14 23-Dec-14 3-Jan-15 0.00 0.00 0.00
Forecast
Planned 29-Oct-14 7-Nov-14 12-Nov-14 17-Nov-14 21-Nov-14
100 Document Numbering and Control Procedure PR Actual 4-Nov-14 16-Nov-14 17-Nov-14 30-Dec-14 1-Jan-15 0.00 0.00 0.00
Forecast
Planned 2-Nov-14 7-Nov-14 12-Nov-14 17-Nov-14 21-Nov-14
101 Inspection Test Plan PL Actual 26-Oct-14 9-Nov-14 26-Nov-14 20-Dec-14 25-Dec-14 0.00 0.00 0.00
Forecast
Planned 2-Nov-14 7-Nov-14 12-Nov-14 17-Nov-14 21-Nov-14
102 Corrective & Preventive Action Procedure PR Actual 4-Nov-14 25-Nov-14 26-Nov-14 20-Dec-14 25-Dec-14 0.00 0.00 0.00
Forecast
Planned 2-Nov-14 7-Nov-14 12-Nov-14 17-Nov-14 21-Nov-14
103 Material Handling, Storage & Preservation Procedure PR Actual 1-Nov-14 4-Nov-14 30-Nov-14 23-Dec-14 30-Dec-14 0.00 0.00 0.00
Forecast
Planned 1-Nov-14 7-Nov-14 12-Nov-14 17-Nov-14 21-Nov-14
104 Title Block for Documents and Drawings PR Actual 4-Nov-14 25-Nov-14 26-Nov-14 30-Dec-14 2-Jan-15 0.00 0.00 0.00
Forecast
Planned 2-Nov-14 7-Nov-14 12-Nov-14 17-Nov-14 21-Nov-14
105 Project Quality Plan PL Actual 2-Nov-14 6-Nov-14 26-Nov-14 20-Dec-14 25-Dec-14 0.00 0.00 0.00
Forecast
Planned 2-Nov-14 7-Nov-14 12-Nov-14 17-Nov-14 21-Nov-14
106 Non-Conformance Control Procedure PR Actual 2-Nov-14 6-Nov-14 27-Nov-14 20-Dec-14 25-Dec-14 0.00 0.00 0.00
Forecast
Planned 2-Nov-14 7-Nov-14 12-Nov-14 17-Nov-14 21-Nov-14
107 Internal Audit Procedure PR Actual 25-Oct-14 3-Nov-14 18-Nov-14 20-Dec-14 25-Dec-14 0.00 0.00 0.00
Forecast
PROCURMENT 0% 0% 0%
Page 3 of 3