Seaoil Mabini Phase III 2023.01.

30 30-Jan-2023
1/3
Activity ID Activity Name Original Start Finish February 2023 March 2023 April 2023 May 2023 June 2023 July 2023 August 2023 September 2023 October 2023 November 2023 2023
Duration
3 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27 04
Seaoil Mabini Phase III 2023.01.30 305 01‐Feb‐2023 02‐Dec‐2023
PROJECT MILESTONES
MIL 305 01‐Feb‐2023 02‐Dec‐2023
PM1010 Contracts Award 0 01‐Feb‐2023
PM1020 Permits 0 01‐Feb‐2023
PM1030 Hand‐over of Tank Farm Area 0 01‐Feb‐2023
PM1040 Mechanical Comple on 0 11‐Oct‐2023
PM1050 Commissioning Complete 0 01‐Nov‐2023
PM1060 Project Contract Close‐out 0 02‐Dec‐2023
Mechanical Completion
C of Tanks 50 22‐Aug‐2023 11‐Oct‐2023
PMT.1010 101 MOGAS ‐ 3ML 0 22‐Aug‐2023
PMT.1020 102 MOGAS ‐ 3ML 0 22‐Aug‐2023
PMT.1030 103 DIESEL ‐ 3ML 0 11‐Oct‐2023
PMT.1040 104 ETHANOL ‐ 3ML 0 11‐Oct‐2023
PMT.1050 105 CME ‐ 1ML 0 08‐Oct‐2023
PMT.1060 WT ‐ 2ML 0 22‐Aug‐2023
DESIGN AND ENGINEERING WORKS 104 01‐Feb‐2023 15‐May‐2023
Civil 74 01‐Feb‐2023 15‐Apr‐2023
D&E1010 Calcula ons, Studies, Data Sheets, & Procedures 30 01‐Feb‐2023 02‐Mar‐2023
D&E1030 Design Drawings 60 15‐Feb‐2023 15‐Apr‐2023
Mechanical 94 01‐Feb‐2023 05‐May‐2023
D&E1100 Calcula ons, Studies, Data Sheets, & Procedures 30 01‐Feb‐2023 02‐Mar‐2023
D&E1110 Design Drawings 60 15‐Feb‐2023 15‐Apr‐2023
D&E1120 Fabrica on Drawings 40 27‐Mar‐2023 05‐May‐2023
Electrical and Instrumentation 74 03‐Mar‐2023 15‐May‐2023
D&E1130 Calcula ons, Studies, Data Sheets, & Procedures 30 03‐Mar‐2023 01‐Apr‐2023
D&E1140 Design Drawings 60 17‐Mar‐2023 15‐May‐2023
PROCUREMENT
PROCUREME 60 17‐Mar‐2023 15‐May‐2023
A1090 Delivery to Site/Fab. Shop ‐ Civil 60 17‐Mar‐2023 15‐May‐2023
A1100 Delivery to Site/Fab. Shop ‐ Mechanical 60 17‐Mar‐2023 15‐May‐2023
FABRICATION 115 17‐Mar‐2023 09‐Jul‐2023
Tank Plates 65 17‐Mar‐2023 20‐May‐2023
FAB1010 Plates ‐ Pre‐fabrica on 30 17‐Mar‐2023 15‐Apr‐2023
FAB1020 Plates ‐ Blas ng and Pain ng 40 01‐Apr‐2023 10‐May‐2023
FAB1030 Plates ‐ Delivey to Site 10 11‐May‐2023 20‐May‐2023
Tank Appurtenances
Appurte 100 01‐Apr‐2023 09‐Jul‐2023
FAB1040 TA ‐ Pre‐fabrica on 90 01‐Apr‐2023 29‐Jun‐2023
FAB1050 TA ‐ Blas ng and Pain ng 60 01‐May‐2023 29‐Jun‐2023
FAB1060 TA ‐ Delivey to Site 10 30‐Jun‐2023 09‐Jul‐2023
Piping 60 21‐Apr‐2023 19‐Jun‐2023
FAB1070 Piping ‐ Pre‐fabrica on 30 21‐Apr‐2023 20‐May‐2023
FAB1080 Piping ‐ Blas ng and Pain ng 30 11‐May‐2023 09‐Jun‐2023
FAB1090 Piping ‐ Delivey to Site 10 10‐Jun‐2023 19‐Jun‐2023
MOBILIZATION
MOBILIZATIO 128 01‐Feb‐2023 08‐Jun‐2023
MBL1010 Civil ‐ Key Personnel 14 01‐Feb‐2023 14‐Feb‐2023
MBL1020 Mechanical ‐ Key Personnel 14 17‐Mar‐2023 30‐Mar‐2023
MBL1030 Electrical ‐ Key Personnel 14 26‐May‐2023 08‐Jun‐2023
CONSTRUCTI
CONSTRUCTION 260 15‐Feb‐2023 01‐Nov‐2023
CIVIL WORKS 255 15‐Feb‐2023 27‐Oct‐2023
Building 240 02‐Mar‐2023 27‐Oct‐2023
BLDG.1010 Opera on Building Office (Admin) 240 02‐Mar‐2023 27‐Oct‐2023
BLDG.1020 MCC & Genset Room 120 09‐Mar‐2023 06‐Jul‐2023
BLDG.1030 Guard House & Driver's Lounge 150 16‐Mar‐2023 12‐Aug‐2023
BLDG.1040 Opera on House / Maintenance Shed 120 23‐Mar‐2023 20‐Jul‐2023
BLDG.1050 Fire Pump House 120 30‐Mar‐2023 27‐Jul‐2023
BLDG.1060 Product Pump Shed with Roofing & Chain Hoist 210 01‐Apr‐2023 27‐Oct‐2023
Structural W
Works 254 16‐Feb‐2023 27‐Oct‐2023
SW.1010 Bulk Filling Gantry (4 TTLR x 8 Loading Bays) with Trench Canal & Gra ng 150 16‐Feb‐2023 15‐Jul‐2023
SW.1020 Inspec on Pla orm (1 x 2 Bays) with Trench Canal & Gra ng 90 16‐Feb‐2023 16‐May‐2023
SW.1030 Tank Farm Bundwall (1.8m x 42lm & 3m x 390lm ) 180 17‐Apr‐2023 13‐Oct‐2023
SW.1040 Perimeter Fence (2.4m x 223 lm) 150 18‐Mar‐2023 14‐Aug‐2023
SW.1050 Tankfarm Gravel Bedding (3053 sq.m) 30 14‐Sep‐2023 13‐Oct‐2023
SW.1060 Drainage (Manhole, Open Canal, RCP &Water Line) 120 17‐May‐2023 13‐Sep‐2023
SW.1070 Concrete Pavement (10'' thk 5032 sq.m) 45 18‐Jul‐2023 31‐Aug‐2023
SW.1080 Oil Water Separator, Trench canal with gra ng (25.34 x 2.65m) 50 17‐May‐2023 05‐Jul‐2023
SW.1090 Overhead Pipe Bridge (3 sets) 45 17‐Apr‐2023 31‐May‐2023
SW.1100 Walkway (130 lm) 45 01‐Sep‐2023 15‐Oct‐2023
SW.1110 Curbs & Gu er 50 01‐Sep‐2023 20‐Oct‐2023
SW.1120 Green Area at TTLR (406 sq.m) 30 28‐Sep‐2023 27‐Oct‐2023
Tank Found
Foundation 145 15‐Feb‐2023 09‐Jul‐2023
TF.1010 101 MOGAS ‐ 3ML 50 15‐Feb‐2023 05‐Apr‐2023
TF.1020 102 MOGAS ‐ 3ML 50 15‐Feb‐2023 05‐Apr‐2023
TF.1030 103 DIESEL ‐ 3ML 50 06‐Apr‐2023 25‐May‐2023
TF.1040 104 ETHANOL ‐ 3ML 50 06‐Apr‐2023 25‐May‐2023

Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone % Complete Summary
Seaoil Mabini Phase III 2023.01.30 30-Jan-2023
2/3
Activity ID Activity Name Original Start Finish February 2023 March 2023 April 2023 May 2023 June 2023 July 2023 August 2023 September 2023 October 2023 November 2023 2023
Duration
3 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27 04
TF.1050 105 CME ‐ 1ML 50 21‐May‐2023 09‐Jul‐2023
TF.1060 WATER TANK ‐ 2ML 50 17‐Mar‐2023 05‐May‐2023
MECHANICA WORKS
MECHANICAL 210 06‐Apr‐2023 01‐Nov‐2023
Vertical Storage
Stor Tank Construction 210 06‐Apr‐2023 01‐Nov‐2023
101 MOGAS - 3ML 160 06‐Apr‐2023 12‐Sep‐2023
VST101.1010 101 ‐ Laying of Bo om Plates 10 06‐Apr‐2023 15‐Apr‐2023
VST101.1020 101 ‐ Full Welding of Bo om Plates 14 22‐Jul‐2023 04‐Aug‐2023
VST101.1030 101 ‐ Erec on of Courses 80 16‐Apr‐2023 04‐Jul‐2023
VST101.1040 101 ‐ Full Welding of Courses 90 23‐Apr‐2023 21‐Jul‐2023
VST101.1050 101 ‐ Laying of Roof Plates 10 05‐Jul‐2023 14‐Jul‐2023
VST101.1060 101 ‐ Full Welding of Roof Plates 14 15‐Jul‐2023 28‐Jul‐2023
VST101.1070 101 ‐ Installa on of Column 14 07‐May‐2023 20‐May‐2023
VST101.1080 101 ‐ Installa on of Ra ers 14 05‐Jul‐2023 18‐Jul‐2023
VST101.1090 101 ‐ Installa on of Nozzles 21 14‐May‐2023 03‐Jun‐2023
VST101.1100 101 ‐ Non‐Destruc ve Test (NDT) 21 19‐Jul‐2023 08‐Aug‐2023
VST101.1110 101 ‐ Hydrosta c Test 14 09‐Aug‐2023 22‐Aug‐2023
VST101.1120 101 ‐ Pain ng 28 16‐Aug‐2023 12‐Sep‐2023
102 MOGAS - 3ML 160 06‐Apr‐2023 12‐Sep‐2023
VST102.1010 102 ‐ Laying of Bo om Plates 10 06‐Apr‐2023 15‐Apr‐2023
VST102.1020 102 ‐ Full Welding of Bo om Plates 14 22‐Jul‐2023 04‐Aug‐2023
VST102.1030 102 ‐ Erec on of Courses 80 16‐Apr‐2023 04‐Jul‐2023
VST102.1040 102 ‐ Full Welding of Courses 90 23‐Apr‐2023 21‐Jul‐2023
VST102.1050 102 ‐ Laying of Roof Plates 10 05‐Jul‐2023 14‐Jul‐2023
VST102.1060 102 ‐ Full Welding of Roof Plates 14 15‐Jul‐2023 28‐Jul‐2023
VST102.1070 102 ‐ Installa on of Column 14 07‐May‐2023 20‐May‐2023
VST102.1080 102 ‐ Installa on of Ra ers 14 05‐Jul‐2023 18‐Jul‐2023
VST102.1090 102 ‐ Installa on of Nozzles 21 14‐May‐2023 03‐Jun‐2023
VST102.1100 102 ‐ Non‐Destruc ve Test (NDT) 21 19‐Jul‐2023 08‐Aug‐2023
VST102.1110 102 ‐ Hydrosta c Test 14 09‐Aug‐2023 22‐Aug‐2023
VST102.1120 102 ‐ Pain ng 28 16‐Aug‐2023 12‐Sep‐2023
103 DIESEL - 3ML 160 26‐May‐2023 01‐Nov‐2023
VST103.1010 103 ‐ Laying of Bo om Plates 10 26‐May‐2023 04‐Jun‐2023
VST103.1020 103 ‐ Full Welding of Bo om Plates 14 10‐Sep‐2023 23‐Sep‐2023
VST103.1030 103 ‐ Erec on of Courses 80 05‐Jun‐2023 23‐Aug‐2023
VST103.1040 103 ‐ Full Welding of Courses 90 12‐Jun‐2023 09‐Sep‐2023
VST103.1050 103 ‐ Laying of Roof Plates 10 24‐Aug‐2023 02‐Sep‐2023
VST103.1060 103 ‐ Full Welding of Roof Plates 14 03‐Sep‐2023 16‐Sep‐2023
VST103.1070 103 ‐ Installa on of Column 14 26‐Jun‐2023 09‐Jul‐2023
VST103.1080 103 ‐ Installa on of Ra ers 14 24‐Aug‐2023 06‐Sep‐2023
VST103.1090 103 ‐ Installa on of Nozzles 21 03‐Jul‐2023 23‐Jul‐2023
VST103.1100 103 ‐ Non‐Destruc ve Test (NDT) 21 07‐Sep‐2023 27‐Sep‐2023
VST103.1110 103 ‐ Hydrosta c Test 14 28‐Sep‐2023 11‐Oct‐2023
VST103.1120 103 ‐ Pain ng 28 05‐Oct‐2023 01‐Nov‐2023
104 ETHANOL
ETHAN - 3ML 160 26‐May‐2023 01‐Nov‐2023
VST104.1010 104 ‐ Laying of Bo om Plates 10 26‐May‐2023 04‐Jun‐2023
VST104.1020 104 ‐ Full Welding of Bo om Plates 14 10‐Sep‐2023 23‐Sep‐2023
VST104.1030 104 ‐ Erec on of Courses 80 05‐Jun‐2023 23‐Aug‐2023
VST104.1040 104 ‐ Full Welding of Courses 90 12‐Jun‐2023 09‐Sep‐2023
VST104.1050 104 ‐ Laying of Roof Plates 10 24‐Aug‐2023 02‐Sep‐2023
VST104.1060 104 ‐ Full Welding of Roof Plates 14 03‐Sep‐2023 16‐Sep‐2023
VST104.1070 104 ‐ Installa on of Column 14 26‐Jun‐2023 09‐Jul‐2023
VST104.1080 104 ‐ Installa on of Ra ers 14 24‐Aug‐2023 06‐Sep‐2023
VST104.1090 104 ‐ Installa on of Nozzles 21 03‐Jul‐2023 23‐Jul‐2023
VST104.1100 104 ‐ Non‐Destruc ve Test (NDT) 21 07‐Sep‐2023 27‐Sep‐2023
VST104.1110 104 ‐ Hydrosta c Test 14 28‐Sep‐2023 11‐Oct‐2023
VST104.1120 104 ‐ Pain ng 28 05‐Oct‐2023 01‐Nov‐2023
105 CME - 1ML
1 105 10‐Jul‐2023 22‐Oct‐2023
VST105.1010 105 ‐ Laying of Bo om Plates 7 10‐Jul‐2023 16‐Jul‐2023
VST105.1020 105 ‐ Full Welding of Bo om Plates 10 12‐Sep‐2023 21‐Sep‐2023
VST105.1030 105 ‐ Erec on of Courses 40 17‐Jul‐2023 25‐Aug‐2023
VST105.1040 105 ‐ Full Welding of Courses 50 24‐Jul‐2023 11‐Sep‐2023
VST105.1050 105 ‐ Laying of Roof Plates 7 26‐Aug‐2023 01‐Sep‐2023
VST105.1060 105 ‐ Full Welding of Roof Plates 10 02‐Sep‐2023 11‐Sep‐2023
VST105.1070 105 ‐ Installa on of Column 14 07‐Aug‐2023 20‐Aug‐2023
VST105.1080 105 ‐ Installa on of Ra ers 15 26‐Aug‐2023 09‐Sep‐2023
VST105.1090 105 ‐ Installa on of Nozzles 21 14‐Aug‐2023 03‐Sep‐2023
VST105.1100 105 ‐ Non‐Destruc ve Test (NDT) 15 10‐Sep‐2023 24‐Sep‐2023
VST105.1110 105 ‐ Hydrosta c Test 14 25‐Sep‐2023 08‐Oct‐2023
VST105.1120 105 ‐ Pain ng 21 02‐Oct‐2023 22‐Oct‐2023
WATER TANK
TAN - 2ML 130 06‐May‐2023 12‐Sep‐2023
VSTWT.1010 WT ‐ Laying of Bo om Plates 10 06‐May‐2023 15‐May‐2023
VSTWT.1020 WT ‐ Full Welding of Bo om Plates 14 22‐Jul‐2023 04‐Aug‐2023
VSTWT.1030 WT ‐ Erec on of Courses 50 16‐May‐2023 04‐Jul‐2023
VSTWT.1040 WT ‐ Full Welding of Courses 60 23‐May‐2023 21‐Jul‐2023
VSTWT.1050 WT ‐ Laying of Roof Plates 10 05‐Jul‐2023 14‐Jul‐2023

Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone % Complete Summary
Seaoil Mabini Phase III 2023.01.30 30-Jan-2023
3/3
Activity ID Activity Name Original Start Finish February 2023 March 2023 April 2023 May 2023 June 2023 July 2023 August 2023 September 2023 October 2023 November 2023 2023
Duration
3 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27 04
VSTWT.1060 WT ‐ Full Welding of Roof Plates 14 15‐Jul‐2023 28‐Jul‐2023
VSTWT.1070 WT ‐ Installa on of Column 14 06‐Jun‐2023 19‐Jun‐2023
VSTWT.1080 WT ‐ Installa on of Ra ers 14 05‐Jul‐2023 18‐Jul‐2023
VSTWT.1090 WT ‐ Installa on of Nozzles 21 13‐Jun‐2023 03‐Jul‐2023
VSTWT.1100 WT ‐ Non‐Destruc ve Test (NDT) 21 19‐Jul‐2023 08‐Aug‐2023
VSTWT.1110 WT ‐ Hydrosta c Test 14 09‐Aug‐2023 22‐Aug‐2023
VSTWT.1120 WT ‐ Pain ng 28 16‐Aug‐2023 12‐Sep‐2023
Piping 100 30‐Jun‐2023 07‐Oct‐2023
PI.1010 Product Line 90 30‐Jun‐2023 27‐Sep‐2023
PI.1020 Fire Protec on Line 60 09‐Aug‐2023 07‐Oct‐2023
ELECTRICAL AND INSTRUMENTATION WORKS 120 09‐Jun‐2023 06‐Oct‐2023
E&I.1010 POWER DISTRBUTION 15 09‐Jun‐2023 23‐Jun‐2023
E&I.1020 TRANSFORMER 15 09‐Jun‐2023 23‐Jun‐2023
E&I.1030 MOTOR CONTROL CENTER ( MCC ) 60 24‐Jun‐2023 22‐Aug‐2023
E&I.1040 CABLES 30 24‐Jul‐2023 22‐Aug‐2023
E&I.1050 PERIMETER LIGHTS 21 23‐Aug‐2023 12‐Sep‐2023
E&I.1060 EX‐PROOF LIGHTING FIXTURES 21 13‐Sep‐2023 03‐Oct‐2023
E&I.1070 GROUNDING SYSTEM 30 17‐Jul‐2023 15‐Aug‐2023
E&I.1080 FIRE ALARM SYSTEM 15 20‐Jul‐2023 03‐Aug‐2023
E&I.1090 PUSH BUTTON 15 19‐Aug‐2023 02‐Sep‐2023
E&I.1100 EX‐PROOF BOXES 10 03‐Sep‐2023 12‐Sep‐2023
E&I.1110 CABLE GLANDS 30 07‐Sep‐2023 06‐Oct‐2023
COMMISSIONING
COMMISSION 21 12‐Oct‐2023 01‐Nov‐2023
COMM1010 Overall Tes ng and Commissioning 21 12‐Oct‐2023 01‐Nov‐2023
DEMOBILIZATION
DEMOBILIZAT 31 02‐Nov‐2023 02‐Dec‐2023
DMBL1010 Housekeeping and Punchlis ng 21 02‐Nov‐2023 22‐Nov‐2023
DMBL1020 Demobiliza on 21 12‐Nov‐2023 02‐Dec‐2023

Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone % Complete Summary