Job Method Statement For Re-Instatement Work

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 7

MCHE-EXE-

Doc Ref
HCSB-MLNG-000-
JOB METHOD No
CVS-JMS-0005
STATEMENT
Page No 1 of 7

JOB METHOD STATEMENT FOR RE-INSTATEMENT WORK

PROJECT : PROVISION OF DISASSEMBLE, TRANSPORT


AND DISPOSAL OF OLD MAIN CRYOGENIC
HEAT EXCHANGER

CLIENT : MLNG

CONTRACT NO : RFP-000000059466

DOCUMENT TITLE : JOB METHOD STATEMENT FOR RE-


INSTATEMENT WORK

A 16/11/23 IFR
Hadoumi Norma Ibrahim
Prepared Reviewed Approved Review Endorsed Approved
Rev Date Description
HCSB MLNG
MCHE-EXE-
Doc Ref
HCSB-MLNG-000-
JOB METHOD No
CVS-JMS-0005
STATEMENT
Page No 2 of 7

JOB METHOD STATEMENT FOR RE-INSTATEMENT WORK

TABLE OF CONTENTS

SECTION DESCRIPTION PAGE


1. INTRODUCTION 3

2. SCOPE OF WORK 3

3. REFERENCE CODE AND STANDARD 3

4. MAN POWER 4

5. PLANT, MACHINERY & EQUIPMENT 4

6. GENERAL SAFETY & REQUIREMENT 5

7. WORK PROCEDURE 5-7

8. PERMIT TO WORK 7
MCHE-EXE-
Doc Ref
HCSB-MLNG-000-
JOB METHOD No
CVS-JMS-0005
STATEMENT
Page No 3 of 7

JOB METHOD STATEMENT FOR RE-INSTATEMENT WORK

1. INTRODUCTION
Based on scope of work, the MCHE Module 5 need to be decontamination, dismantling,
demolish and manage the scrap as per project direction. The MCHE currently located at
MLNG Car Park to be specific at Lot 39 Old MCHE Storage area.

2. SCOPE OF WORK

The following scopes shall be covered and abide to this document.

a) Mobilize and demobilize of equipment, machinery, material and tools.


b) Remove perimeter metal hoarding.
c) Repair damage ground surface.
d) Removal of bund wall, concrete slab and sump pit.
e) Housekeeping and reinstatement work.

3. REFERENCE CODE AND STANDARD

a) MLNG-09_01-L3-910250 MLNG HSE Training Requirements and Management


b) MY MLNG X X S 05 015 I General Safety Regulation
c) MY MLNG X X S 05 106 I Incident Reporting
d) MY MLNG X X S 05 032 I Supply & Handling of Chemicals Health, Safety, Security and
Environment (HSSE) Balance of Consequence
e) MY MLNG X X S 05 074 I Job Hazard Analysis
f) MY MLNG X X S 05 026 I Traffic Regulations
g) MY MLNG X X S 05 132 I Personnel Protective Equipment
h) MY MLNG X X S 05 109 I Permit to Work System
i) MY MLNG X X S 05 050 I Scaffolding
j) MY MLNG X X S 05 025 I Misuse Substances
k) MY MLNG X X S 05 026 I MLNG Traffic and Vehicle Rules and Regulations
l) MY MLNG X X S 05 067 I WAH-Working at Heights Procedure
m) MY MLNG X X S 05 027 I Health Assessment to Fitness to Work
n) MY MLNG X X 5 05 073 I Lifting Safety Operation
o) MY MLNG X X S 05 036 I Scheduled Waste Management
p) MY MLNG X X P 05 009 I Technical Documents and Drawings Handover for final
documentation
MCHE-EXE-
Doc Ref
HCSB-MLNG-000-
JOB METHOD No
CVS-JMS-0005
STATEMENT
Page No 4 of 7

JOB METHOD STATEMENT FOR RE-INSTATEMENT WORK

4. MANPOWER

No Position No of Pax
1 Construction Supt. 1
2 Site Safety Supervisor 1
3 Lifting Supervisor 1
4 Site Supervisor 1
5 Radiation Protection Officer 2
6 Work Leader (Dismantling & Demolition) 1
7 Work Leader (Cleaning) 1
8 Welder 2
9 Fitter 4
10 General Workers (Dismantling & Demolition) 13
11 General Workers (Cleaning) 5
12 Decontamination Technician 4
13 Rigger 4
14 Scaffolding Inspector 1
15 Scaffolders 6
TOTAL 47 PAX

5. PLANT, MACHINERY & EQUIPMENT

No Equipment and Tools List Unit


1 Mobile Crane 80 tonne 1
2 Lorry Crane 1
3 Backhoe 1
4 370 CFM Compressor 1
5 Tool Box 1
6 175 KVA Genset 1
8 Hose and Accessories 1 Lot
9 Diamond Cut Machine 2 Sets
10 Hand tools 1 Lot
11 Portable Eye Wash 1
12 Portable Habitat 1
13 Schedule Waste Drums 150 unit (approximately)
14 Water Pump 1 unit
15 Portable Toilet 1 unit
16 Water Tank 1 unit
MCHE-EXE-
Doc Ref
HCSB-MLNG-000-
JOB METHOD No
CVS-JMS-0005
STATEMENT
Page No 5 of 7

JOB METHOD STATEMENT FOR RE-INSTATEMENT WORK

6. GENERAL SAFETY & REQUIREMENT

a) All workers entering the worksite must be properly briefed on the rules and regulations
on the safety of working in the hazardous area.
b) Toolbox meeting shall be conducted prior to the start of any workday to ensure worker
are aware of the activity being carried out and safety requirement to execute the work.
c) HCSB to ensure that all PPE requirement are being adhered to.
d) The worksite must be clearly marked with suitable signboard to prevent any unauthorized
entry.
e) All personnel must observe strictly to the MLNG Safety regulation and occupational
safety, health and environment plan.
f) Precaution to be taken for lifting over live plant, field weld shall be strictly adhered to
PTW, JHA and relevant PTS.

7. WORK PROCEDURE

7.1. Mobilization and demobilization of Materials, Equipment and Tools


7.1.1.Equipment Mobilization Upon Entering MLNG.
a) HCSB shall ensure that mobilization activities are carried out based on
MLNG HSE and security requirement upon entering MLNG area.
b) Supervisor to ensure HCSB checklist to be fulfilled before mobilizing all
equipment to site.
c) All personnel must have valid MLNG body pass upon entering MLNG facility.
d) Prepare entry exit form at the security post and approved by MLNG.
e) Ensure the transportation is equip with spark arrestor and diesel driven
vehicles.
f) Supervisor shall inform MLNG person in-charge the plan for mobilization at
least one week before the work execution.
g) To ensure assign signalman / flagman during mobilization activities.

7.1.2. Electrical Equipment Inspections


a) All electrical equipment to be check by internal chargeman prior to
equipment inspection by MLNG representative to issue for approval for
usage at site.
b) Charge man shall engage by HCSB.
c) Refer to item no item 1.6 for the list of equipment and tools

7.1.3 Material Mobilization


a) HCSB shall ensure material to be properly stored and secured before lay
at designated laydown area.
b) Supervisor shall monitor and arrange to barricade the laydown area and
MCHE-EXE-
Doc Ref
HCSB-MLNG-000-
JOB METHOD No
CVS-JMS-0005
STATEMENT
Page No 6 of 7

JOB METHOD STATEMENT FOR RE-INSTATEMENT WORK

install signage accordingly.


c) The laydown area must be approved by operation and notify area
owner.

7.1.4 Tool and Equipment Demobilization


a) Supervisor to ensure all the tools and cable shall be stored inside toolbox
and ensure to be locked before lifted to lorry crane.
b) All personnel responsible to check any remaining tools, equipment,
consumables, and material left at site shall be clear.
c) Supervisor shall fill up entry exit form prior to demobilization.
d) To ensure assign signalman / flagman during mobilization and
demobilization activities.

7.2. Removal of temporary perimeter metal hoarding and gate


a) Hoarding shall be removed from existing chain link fencing and gate after completion
of demolition work.
b) Any damage to the fencing shall be marked and repair as per original condition.
c) The joint inspection with MLNG shall be conducted to identify any damage to the
fencing.

7.3. Removal of Slab, Sump Pit and Bund Wall.


a) Slab, Sump Pit and Bund Wall shall be removed using back hoe from the site after
completion of demolition work.
b) Any damage to the ground surface shall be re-instate as per original condition and
compacted.
c) The joint inspection with MLNG shall be conducted to identify any damage to the
fencing.

7.4. Re-Instatement Work


a) Once construction is completed, the site shall be cleared of all redundant
infrastructure, waste and construction material.
b) All areas disturbed during the Works shall be reinstated to a condition in keeping
with the requirements of the re-vegetation guidelines and to the satisfaction of the
Client.
c) Remove from the site all construction equipment, surplus material, waste and
temporary structures and Works of every kind before the final hand-over.
d) After completion of construction, the site should be properly cleaned of any
construction waste, litter etc. and adequately rehabilitated/re-vegetated.
e) Rehabilitate any environmental damage caused by construction activities before the
final hand-over.
f) Removal of all excavated material (rocks, excess soil, etc.) and construction rubble
after construction is completed.
MCHE-EXE-
Doc Ref
HCSB-MLNG-000-
JOB METHOD No
CVS-JMS-0005
STATEMENT
Page No 7 of 7

JOB METHOD STATEMENT FOR RE-INSTATEMENT WORK

7.5. Housekeeping
a) Clean up the job site.
b) Prevent development of safety hazards.
c) All equipment and tools used must be removed after use.
d) Store tools, equipment, and unused materials properly at the end of working day.

8. PERMIT TO WORK
a) MLNG e-PTW system will be diligently adhered to appropriate e-PTW forms will be
submitted to MLNG for approval prior to commencement of work ad copy shall be made
accessible and visible at work site.
b) JMS/JHA will be review and approved by MLNG prior to start work.
c) Approved PTW and related document will be displayed at site where it can be easily seen
and checked.
d) E-PTW shall be returned to receiving authority (RA)/ Area Authority Representative (AAR)
at the end of the day on daily basis for revalidation.
e) After completing the job and finishing 7 days duration, e-PTW form will be signed off by
Receiving Authority/ Area Authority Representative and submitted to MLNG filed for
further reference.
f) Work Leader shall be fully responsible to handle copy of e-PTW and for monitoring
activities to comply with JHA requirements.