SITE DAILY REPORT DCBWSP

DAVAO CITY BULK WATER SUPPLY PROJECT


07 August 2023 Davao City, Philippines
WITCO Construction & Development Corp. Working/Shift Hours: 0600H to 1500H
Prepared by: Sherkin Torres Extended Hours: 1500H to 1800H

Work Location – Area / Section: Weather Condition:


TWP- AL 4B Dry – Dayshift 600 to 1800

Site Engineer/Supervisor: Site Condition:


Sherkin Torres & Ariel Aroyo Workable – Dayshift 600 to 1800

Receipt of SOR/NCR: Issued WIR:


NONE

Site Deliveries:

Key Issues and Concerns:

Work Activities, Manpower & Equipment:

Site Supervisor Skilled Tools & Equipment &


Area Work Activity Labor Manpower
(Foreman /Leadman) Manpower Quantity

• AL 4-Sta. 7+233 • Manual Dewatering in S. Torres (Supervisor) 3-Painter 20-Helper 1-Genset 25KVA LKPH7045
AL4-Sta. 7+233 A. Aroyo(Supervisor) 2-Gas Tester 4/15-Ventilation& Lights
• Manual Hauling and R. Edgar (Foreman 1-First Aider 1-6Wheeler Labor Haul
sandbagging of mud in 2-Watchman (MAE 4987)
AL4-Sta. 7+233 2-Watchman
• Cleaning inside pipes of AL (Nightshift)
4-Sta. 7+233

TOTAL 3 3 27

Prepared By: Prepared By: Validated By:

SHERKIN TORRES ARIEL AROYO ROY ESPINOSA


WITCO SUPERVISOR WITCO SUPERVISOR AAII PAINTING INSPECTOR
DATE: 08/07/2023 DATE: 08/07/2023 DATE:

Rev. 9– 22 June 2021 1


SITE DAILY REPORT DCBWSP
DAVAO CITY BULK WATER SUPPLY PROJECT
07 August 2023 Davao City, Philippines
WITCO Construction & Development Corp. Working/Shift Hours: 0600H to 1500H
Prepared by: Sherkin Torres Extended Hours: 1500H to 1800H

Photo

• Manual Hauling and sandbagging of mud in AL4-


• Manual Dewatering in AL4-Sta. 7+233
Sta. 7+233

Photo Photo

• Manual Hauling and sandbagging of mud in AL4- • Manual Hauling and sandbagging of mud in AL4-
Sta. 7+233 Sta. 7+233

Photo Photo

• Manual Hauling and sandbagging of mud in AL4- • Cleaning inside pipes of AL 4-Sta. 7+233
Sta. 7+233
Rev. 9– 22 June 2021 2
SITE DAILY REPORT DCBWSP
DAVAO CITY BULK WATER SUPPLY PROJECT
07 August 2023 Davao City, Philippines
WITCO Construction & Development Corp. Working/Shift Hours: 0600H to 1500H
Prepared by: Sherkin Torres Extended Hours: 1500H to 1800H

Photo

• AL 4-Sta. 7+233: Genset 25KVA LKPH7045 • AL 4-Sta. 7+233: Genset 25KVA LKPH7045

Photo Photo

August 7, 2023 5:43:51 AM

• AL 4-Sta. 7+233: Genset 25KVA LKPH7045 • 6Wheeler Labor Haul: MAE 4987

Photo Photo

August 7, 2023 20:03

• 6Wheeler Labor Haul: MAE 4987