SITE DAILY REPORT DCBWSP

DAVAO CITY BULK WATER SUPPLY PROJECT


10 August 2023 Davao City, Philippines
WITCO Construction & Development Corp. Working/Shift Hours: 0600H to 1500H
Prepared by: Sherkin Torres Extended Hours: 1500H to 2100H

Work Location – Area / Section: Weather Condition:


TWP- AL 4 Dry – Dayshift 600 to 0000

Site Engineer/Supervisor: Site Condition:


Sherkin Torres & Ariel Aroyo Workable – Dayshift 600 to 0000

Receipt of SOR/NCR: Issued WIR:


NONE

Site Deliveries:

Key Issues and Concerns:

Work Activities, Manpower & Equipment:

Site Supervisor Skilled Tools & Equipment &


Area Work Activity Labor Manpower
(Foreman /Leadman) Manpower Quantity

• AL 4-Sta. 7+233 • Final Cleaning inside pipes S. Torres (Supervisor) 2-Painter 2-Helper 1-Genset 25KVA LKPH7045
of AL4-Sta. 7+233 A. Aroyo(Supervisor) 1-Gas Tester 3/2-Ventilation& Lights
• Grinding inside pipes of R. Edgar (Foreman 1-First Aider
AL4-Sta. 7+233 2-Watchman
• Final coating in AL4-Sta. 3-Watchman
7+233 (Nightshift)
• Final DFT in AL 4-Sta.
7+233

• AL4-Sta. 8+890 • Cleaning inside pipes of AL R. Deloso (Safety Lead) 1-Painter 29-Helper 1-Genset 32KVA LKPH7021
4-Sta. 8+890 A. Gabe (Safety Officer) 4-Grinder Operator 2/18-Ventilation& Lights
R. Engco (Safety Officer) 2-Gas Tester 1-6Wheeler Labor Haul
• Manual Dewatering in AL D. Derano (Safety Officer) 1-First Aider (MAE 4987)
4-Sta. 8+890 1-Watchman 1-6Wheeler Boom Truck
2-Watchman (RME 706)
(Nightshift)

TOTAL 7 3 48

Prepared By: Prepared By: Validated By:

SHERKIN TORRES ARIEL AROYO ROY ESPINOSA


WITCO SUPERVISOR WITCO SUPERVISOR AAII PAINTING INSPECTOR
DATE: 08/10/2023 DATE: 08/10/2023 DATE:

Rev. 9– 22 June 2021 1


SITE DAILY REPORT DCBWSP
DAVAO CITY BULK WATER SUPPLY PROJECT
10 August 2023 Davao City, Philippines
WITCO Construction & Development Corp. Working/Shift Hours: 0600H to 1500H
Prepared by: Sherkin Torres Extended Hours: 1500H to 2100H

Photo

Aug 10, 2023 06:11:07

• Final Cleaning inside pipes of AL4-Sta. 7+233 • Final Cleaning inside pipes of AL4-Sta. 7+233

Photo Photo

• Final Cleaning inside pipes of AL4-Sta. 7+233 • Grinding inside pipes of AL4-Sta. 7+233

Photo Photo

• Final coating in AL4-Sta. 7+233 • Final coating in AL4-Sta. 7+233

Rev. 9– 22 June 2021 2


SITE DAILY REPORT DCBWSP
DAVAO CITY BULK WATER SUPPLY PROJECT
10 August 2023 Davao City, Philippines
WITCO Construction & Development Corp. Working/Shift Hours: 0600H to 1500H
Prepared by: Sherkin Torres Extended Hours: 1500H to 2100H

Photo

• Final DFT in AL 4-Sta. 7+233 • Final DFT in AL 4-Sta. 7+233

Photo Photo

August 10, 2023 06:17

• AL4-Sta. 7+233: Genset 25KVA LKPH7045 • AL4-Sta. 7+233: Genset 25KVA LKPH7045

Photo Photo

• AL4-Sta. 7+233: Genset 25KVA LKPH7045 • Set up work area in AL 4-Sta. 8+890

Rev. 9– 22 June 2021 3


SITE DAILY REPORT DCBWSP
DAVAO CITY BULK WATER SUPPLY PROJECT
10 August 2023 Davao City, Philippines
WITCO Construction & Development Corp. Working/Shift Hours: 0600H to 1500H
Prepared by: Sherkin Torres Extended Hours: 1500H to 2100H

Photo

• Cleaning inside pipes of AL 4-Sta. 8+890 • Cleaning inside pipes of AL 4-Sta. 8+890

Photo Photo

• Cleaning inside pipes of AL 4-Sta. 8+890 • Cleaning inside pipes of AL 4-Sta. 8+890

Photo Photo

• Manual Dewatering in AL 4-Sta. 8+890 • AL 4-Sta. 8+890: Genset 32KVA LKPH7021

Rev. 9– 22 June 2021 4


SITE DAILY REPORT DCBWSP
DAVAO CITY BULK WATER SUPPLY PROJECT
10 August 2023 Davao City, Philippines
WITCO Construction & Development Corp. Working/Shift Hours: 0600H to 1500H
Prepared by: Sherkin Torres Extended Hours: 1500H to 2100H

Photo

• AL 4-Sta. 8+890 : Genset 32KVA LKPH7021 • AL 4-Sta. 8+890 : Genset 32KVA LKPH7021

Photo Photo

August 10, 2023 07:35:16 August 10, 2023 14:25:49

• 6Wheeler Boom Truck: RME 706 • 6Wheeler Boom Truck: RME 706

Photo Photo

August 10, 2023 15:27:12

• 6Wheeler Boom Truck: MAE 4987 • 6Wheeler Boom Truck: MAE 4987

Rev. 9– 22 June 2021 5