Download as pdf or txt
Download as pdf or txt
You are on page 1of 20

A/C behalf and owes the client a "fiduciary duty" (Trust).

Example:
Construction Manager for fee but classified as an independent
An abbreviation for air conditioner or air conditioning. contractor for tax purposes. A construction manager for fee does not
have any financial responsibility whereas a construction manager at-
A/C CONDENSER
risk does have financial risk similar to a general contractor.
The outside fan unit of the Air Conditioning system. It removes
AGGREGATE
the heat from the freon gas and "turns" the gas back into a
liquid and pumps the liquid back to the coil in the furnace. A mixture of sand and stone and a major component of concrete.
ACOUSTICS AGREEMENT
The science of sound. In construction, acoustical materials An arrangement between the parties regarding a method of action.
used to keep down noise within a room or to prevent it from
passing through walls. ALLOWANCE(S)

ACTIVITY A sum of money set aside in the construction contract for items which
have not been selected and specified in the construction contract. For
1. A scheduling term example, selection of tile as a flooring may require an allowance for an
underlayment material, or an electrical allowance which sets aside an
2. The smallest work unit within a project; the basic building
amount of money to be spent on electrical fixtures.
block of a project.
ALTERATIONS
ADA
1. A term used to describe partial construction work performed within
The Americans with Disabilities Act which gives civil rights
an existing structure
protection to individuals with disabilities similar to those
provided to individuals on the basis of race, color, sex, national 2. Remodeling without a building addition.
origin, age, and religion. It guarantees equal opportunity for
individuals with disabilities in public accommodations, ALTERNATE BID
employment, transportation, State and local government
services, and telecommunications. Amount stated in the bid to be added or deducted from the base bid
amount proposed for alternate materials and/or methods of
ADDENDUM construction.

(Addenda) Written information adding to, clarifying or modifying APPLICATION FOR PAYMENT
the bidding documents. An addendum is generally issued by the
owner to the contractor during the bidding process and as such, Contractor's written request for payment for completed portions of the
addenda are intended to become part of the contract documents work and, for materials delivered or stored and properly labeled for the
when the construction contract is executed. respective project.

AGENT ARCADE

One authorized by a client (principal) to act in his/her stead or A series of arches supported by a row of columns.
ARCH ATRIUM

A curved structure that will support itself by mutual pressure and An open court within a building.
the weight above its curved opening.
BACK CHARGE
ARCHITECT
Billings for work performed or costs incurred by one party that, in
One who designs and supervises the construction of buildings accordance with the agreement, should have been performed or
or other structures. incurred by the party to whom billed. Owners bill back charges to
general contractors, and general contractors bill back charges to
ARCHITECTS BASIC SERVICES subcontractors. Examples of back charges include charges for
cleanup work or to repair something damaged by another
A recognized series of phases performed by an architect as
subcontractor.
follows: 1st Schematic Design Phase, 2nd Design Development
Phase, 3rd Construction Document Phase, 4th Bidding or BACKFILL
Negotiated Phase, 5th Construction Phase.
The replacement of excavated earth into a trench around or against a
ARCHITECT-ENGINEER basement /crawl space foundationwall.
An individual or firm offering professional services as both BACKING
architect and engineer.
Frame lumber installed between the wall studs to give additional
ARCHITECTURAL DRAWING support for drywall or an interior trim related item, such as handrail
brackets, cabinets, and towel bars. In this way, items are screwed and
A line drawing showing plan and/or elevation views of the
mounted into solid wood rather than weak drywall that may allow the
proposed building for the purpose of showing the overall
item to break loose from the wall.
appearance of the building.
BAFFLE
AREA WELLS
A partial blocking against the flow of wind or sound.
Corrugated metal or concrete barrier walls installed around a
basement window to hold back the earth. BALLAST
AS-BUILT DRAWINGS (also known as Record Drawings) A transformer that steps up the voltage in a florescent lamp.
Contract drawings marked up to reflect changes made during BALLOON FRAMED WALL
the construction process. It is good practice to make As-Built
drawings by marking the changes on reproducible drawings Framed walls (generally over 10' tall) that run the entire vertical length
such a sepias for the duplication purposes later. from the floor sill plate to the roof. This is done to eliminate the need
for a gable end truss.
ASTRAGAL
BALUSTRADE
A molding, attached to one of a pair of swinging double doors,
against which the other door strikes. The rail, posts and vertical balusters along the edge of a stairway or
elevated walkway.
BARGE 3. The horizontal structural member over an opening (for example over
a door or window).
Horizontal beam rafter that supports shorter rafters.
BEDROCK
BARGE BOARD
A subsurface layer of earth that is suitable to support a structure.
A decorative board covering the projecting rafter (fly rafter) of
the gable end. At the cornice, this member is a fascia board. BID

BASE OR BASEBOARD 1. An offer or proposal of a price

A trim board placed against the wall around the room next to 2. The amount offered or proposed.
the floor.
BID BOND
BAT
A written form of security executed by the bidder as principal and by a
A half-brick. surety for the purpose of guaranteeing that the bidder will sign the
contract, if awarded the contract, for the stated bid amount.
BEAM
BID DATE/TIME
A structural member transversely supporting a load. A structural
member carrying building loads (weight) from one support to The due date and time set by the owner, architect or engineer for
another. Sometimes called a "girder". receiving bids.

BEARING PARTITION BID FORM

A partition that supports any vertical load in addition to its own A standard written form furnished to all bidders for the purpose of
weight. obtaining the requested information and required signatures from the
authorized bidding representatives.
BEARING POINT
BID OPENING
A point where a bearing or structural weight is concentrated
and transferred to the foundation The actual process of opening and tabulating bids submitted within
the prescribed bid date/time and conforming with the bid procedures.
BEARING WALL A Bid Opening can be open (where the bidders are permitted to attend)
or closed (where the bidders are not permitted to attend).
A wall that supports any vertical load in addition to its own
weight. BID PRICE
BEARING HEADER The stipulated sum stated in the bidder’s bid.
1. A beam placed perpendicular to joists and to which joists BID TABULATION
are nailed in framing for a chimney, stairway, or other opening.
A summary sheet listing all bid prices for the purpose of analysing the
2. A wood lintel. bid results. Bid tabulations include the required items of the invitation
to bid and usually include bid amount, completion time, underground.
addendas included, contract exclusions, bonding rate, etc.
Often times, the apparent low bidder is not the low bidder. BONDING COMPANY

BID SHOPPER A properly licensed firm or corporation willing to execute a surety bond,
or bonds, payable to the owner, securing the performance on a
A buyer or client who seeks to play one proposed supplier contract either in whole or in part; or securing payment for labor and
or subcontractor against the other for the purpose of materials.
reducing a purchase price.
BREAKER PANEL
BIDDING DOCUMENTS
The electrical box that distributes electric power to each branch circuit
The published advertisement or written invitation to bid , (each plug and switch) and composed of circuit breakers.
instructions to bidders, the bid form and the proposed
contract documents including any acknowledged addenda BREEZEWAY
issued prior to receipt of bids.
A roofed walkway with open sides.
BIDDING PERIOD
BRIDGING
The calendar period allowed from issuance of bidding
Small wood or metal members that are inserted in a diagonal position
requirements and contract documents to the prescribed
between the floor joists or rafters at mid-span for the purpose of
bid date/time.
bracing the joists/rafters & spreading the load.
BIDDING REQUIREMENTS
BUDGET (CONSTRUCTION BUDGET)
The written minimum acceptable requirements set forth by the
1. An itemized summary of estimated or intended expenditures for a
owner to the contractor during bidding process. The owner
given period of time
usually reserves the right to reject a bid if the Bidding
Requirements are not met. 2. The total sum of money allocated for a specific project.
BLUE PRINT(S) BUILDING
A type of copying method often used for architectural 1. To form by combining materials or parts
drawings. Usually used to describe the drawing of a structure
which is prepared by an architect or designer for the purpose 2. A structure enclosed within a roof and within exterior walls housing,
of design and planning, estimating, securing permits and actual shelter, enclosure and support of individuals, animals, or real property
construction. of any kind.

BLUE STAKE BUILDING CODE

Another phrase for Utility Notification. This is when a utility The legal requirements set up by the prevailing various governing
company (telephone, gas, electric, sewer and water, etc) comes agencies covering the minimum acceptable requirements for all types
to the job site and locates and spray paints the ground and/or of construction.
installs little flags to show where their service is located
BUILDING ENVELOPE BTU

(Sometimes referred to as Building Shell) Abbreviation for British Thermal Unit; a standard unit for measuring
heat gain or loss.
1. The waterproof elements of a building which enclose
conditioned spaces through which thermal energy may be CAISSON
transferred to or from the exterior.
A 10" or 12" diameter hole drilled into the earth and embedded into
2. The outer structure of the building. bedrock 3 - 4 feet. The structural support for a type of foundation wall,
porch, patio, monopost, or other structure. Two or more "sticks" of
BUILDING INSPECTOR/OFFICIAL reinforcing bars (rebar) are inserted into and run the full length of the
hole and concrete is poured into the caisson hole.
A qualified government representative authorized to inspect
construction for compliance with applicable building codes, CANTILEVER
regulations and ordinances. Courts have ruled that building
inspections are exempt from errors and omissions liabilities. An overhang. Where one floor extends beyond and over a foundation
wall.
BUILDING PERMIT
CANTILEVERED VOID
A written document issued by the appropriate governmental
authority permitting construction to begin on a specific project Foundation void material used in unusually expansive soils conditions.
in accordance with drawings and specifications approved by This void is "trapezoid" shaped and has vertical sides of 6" and 4"
the governmental authority. respectively.

BUILDING PROCESS CAVITY WALL

A term used to express every step of a construction project Double masonry wall having an air space between the wyths.
from it’s conception to final acceptance and occupancy.
CEILING JOIST
BUILT-UP ROOF
One of a series of parallel framing members used to support ceiling
A roofing composed of three to five layers of asphalt felt loads and supported in turn by larger beams, girders or bearing walls.
laminated with coal tar, pitch, or asphalt. The top is finished Also called roof joists.
with crushed slag or gravel. Generally used on flat or
low-pitched roofs. CFM (cubic feet per minute)

BUTTERFLY ROOF A rating that expresses the amount of air a blower or fan can move.
The volume of air (measured in cubic feet) that can pass through an
A roof with two sides sloping down toward the interior of opening in one minute.
the building.
CHANGE ORDER
BUTTRESS
A written document between the owner and the contractor signed by
Vertical masonry or concrete support, usually larger at the the owner and the contractor authorizing a change in the work or an
base, which projects from a wall. adjustment in the contract sum or the contract time. A change order
may be signed by the architect or engineer, provided they have CLASS "A"
written authority from the owner for such procedure and that a
copy of such written authority is furnished to the contractor upon Optimum fire rating issued by Underwriter's Laboratories on roofing.
request. The contract sum and the contract time may be changed The building codes in some areas require this type of roofing for fire
only by change order. A change order may be in the form of safety.
additional compensation or time; or less compensation or time
CLASS "C"
known as a Deduction (from the contract) the amount deducted
from the contract sum by change order. Minimum fire rating issued by the Underwriters' Laboratories for
roofing materials.
CHANGE ORDER PROPOSAL
CLOSED BID/ESTIMATE
A change order proposal is the written document before it has
been approved and effected by the Contractor and Owner. A A service where only invited bidders or estimators are given access to
change order proposal can be issued by either the contractor or the project specific RFP (Request for Proposal) information. This
the owner. The change order proposal becomes a change order option is for those seeking bids/estimates from a prequalified and
only after it has been approved and effected by the Contractor selected list of professionals or service.
and Owner.
CO
CHANGE ORDER REQUEST
An abbreviation for "Certificate of Occupancy". This certificate is
A written document issued by the owner requesting an adjustment issued by the local municipality and is required before anyone can
to the contract sum or an extension of the contract time; generally occupy a space. It is issued only after the local municipality has made
issued by the architect or owners representative. all inspections and all monies and fees have been paid.
CHECK VALVE CODES
A valve that permits passage through a pipe in only one direction. Prevailing regulations, ordinances or statutory requirements set forth
by governmental agencies associated with building construction
CIRCUIT
practices and owner occupancy, adopted and administered for the
The path of electrical flow from a power source through an protection of public health, life safety and welfare.
outlet and back to ground.
COLD AIR RETURN
CIRCUIT BREAKER
The ductwork (and related grills) that carries room air back to the
A device which looks like a switch and is usually located inside the furnace for re-heating.
electrical breaker panel or circuit breaker box. It is designed to (1) shut
COLLAR BEAM
of the power and (2) to limit the amount of power flowing through a
circuit (measured in amperes). 110 volt household circuits require a Nominal 1- or 2-inch-thick members connecting opposite roof rafters.
fuse or circuit breaker with a rating of 15 or a maximum of 20 amps. They serve to stiffen the roof structure.
220 volt circuits may be designed for higher amperage loads.
COLUMN

A vertical structural compression member which supports loads.


COMBUSTION AIR CONSTRUCTION

The duct work installed to bring fresh, outside air to the furnace The act or process of constructing.
and/or hot water heater. Normally 2 separate supplies of air are
brought in: one high and one low. CONSTRUCTION COST

COMPRESSOR The direct contractor costs for labor, material, equipment, and
services; contractors overhead and profit; and other direct
A mechanical device that pressurizes a gas in order to turn it construction costs. Construction cost does not include the
into a liquid, thereby allowing heat to be removed or added. A compensation paid to the architect and engineer and consultants, the
compressor is the main component of conventional heat pumps cost of the land, rights-of-way or other costs which are defined in the
and air conditioners. In an air conditioning system, the contract documents as being the responsibility of the owner.
compressor normally sits outside and has a large fan
(to remove heat). CONSTRUCTION DOCUMENTS

CONCRETE A term used to represent all drawings, specifications, addenda, other


pertinent construction information associated with the construction of
The mixture of Portland cement, sand, gravel, and water. Used to a specific project.
make garage and basement floors, sidewalks, patios, foundation
walls, etc. It is commonly reinforced with steel rods (rebar) or wire CONSTRUCTION DOCUMENTS PHASE
screening (mesh).
The third phase of the architect's basic services wherein the architect
CONDENSATE LINE prepares working drawings, specifications and bidding information.
Depending on the architects scope of services the architect may
The copper pipe that runs from the outside air conditioning assists the owner in the preparation of bidding forms, the conditions
condenser to the inside furnace ( where the a/c coil is located). of the contract and the form of agreement between the owner and
contractor.
CONDENSING UNIT
CONSTRUCTION DOCUMENT REVIEW
The outdoor component of a cooling system. It includes a
compressor and condensing coil designed to give off heat. The owners review of the borrowers construction documents (plans
and specifications), list of materials, and cost breakdowns for the
CONDUIT, ELECTRICAL purpose of confirming that these documents and estimates are
feasible and are in accordance with the proposed loan or project
A pipe, usually metal, in which wire is installed.
appraisal.
CONSTRUCTION DOCUMENTS
CONSTRUCTION MANAGEMENT
All drawings, specifications and addenda associated with a
Organizing and directing men, materials, and equipment to accomplish
specific construction project.
the purpose of the designer.
CONSTRUCT
CONSTRUCTION MANAGEMENT CONTRACT
To assemble and combine construction materials and
A written agreement wherein responsibilities for coordination and
methods to make a structure.
accomplishment of overall project project design and CONTRACT OVER-RUN (under-run)
construction are given to a construction management firm.
The building team generally consists of the owner, contractor The difference between the original contract price and the final
and designer or architect. completed cost including all adjustments by approved change order.

CONSTRUCTION PHASE CONTRACT PAYMENT BOND

The fifth and final phase of the architect's basics services, A written form of security from a surety company to the owner, on
which includes the architect's general administration of the behalf of an acceptable prime or main contractor or subcontractor,
construction contract(s). guaranteeing payment to all persons providing labor, materials,
equipment, or services in accordance with the contract.
CONSULTANT
CONTRACT PERFORMANCE BOND
One hired by the owner or client to give professional advise.
A written form of security from a surety company to the owner, on
CONTRACT behalf of an acceptable prime or main contractor or subcontractor,
guaranteeing the completion of the work in accordance with the terms
1. An agreement between two or more parties, especially one of the contract.
that is written and enforceable by law
CONTRACT PERIOD
2. The writing or document containing such an agreement.
The elapsed number of working days or calendar days from the
CONTRACT ADMINISTRATION specified date of commencing work to the specified date of
completion, as specified in the contract.
The contractual duties and responsibilities of the architect and
engineer during the construction phase of a specific project. CONTRACT SUM
CONTRACT BOND The total agreeable amount payable by the owner to the contractor for
the performance of the work under the contract documents.
A written form of security from a surety company, on behalf
of an acceptable prime or main contractor or subcontractor, CONTRACT TIME
guaranteeing complete execution of the contract and all
supplemental agreements pertaining thereto and for the The time period set forth established in the contract documents for
payment of all legal debts pertaining to the construction of completing a specific project; usually stated in working days or
the project. calendar days. The contract time can only be adjusted by valid time
extensions through change order.
CONTRACT DOCUMENTS
CONTRACTUAL LIABILITY
A term used to represent all executed agreements between the owner
and contractor; any general, supplementary or other contract The liability assumed by a party under a contract.
conditions; the drawings and specifications; all addenda issued prior
to execution of the contract; and any other items specifically CONTRACTOR
stipulated as being included in the contract documents.
A properly licensed individual of company that agrees to furnish labor,
materials, equipment and associated services to perform the work as
specified for a specified price. board, a soffit and appropriate trim moldings.

CONTRACTOR'S OPTION COST CODES

A written provision in the contract documents giving the A numbering system given to specific kinds of work for the purpose of
contractor the option of selecting certain specified materials, organizing the cost control process of a specific project.
methods or systems without changing in the contract sum.
COST OF WORK
CONTRACTOR'S QUALIFICATION STATEMENT
All costs incurred by the contractor in the proper performance of the
A written statement of the Contractor's experience and work required by the plans and specifications for a specific project.
qualifications submitted to the Owner during the contractor
selection process. The American Institute of Architects COST PLUS FEE AGREEMENT (Cost-Plus)
publishes a standard Contractor's Qualification Statement
A written agreement with the owner under which the contractor or the
form for this purpose.
architect and engineer is reimbursed for his/her direct and indirect
CONTRACTING OFFICER costs and, in addition, is paid a fee for his services. The fee is usually
stated as a stipulated sum or as a percentage of cost.
An official representative of the owner with specific authority
to act in his behalf in connection with a specific project. COUNTER FLASHING

CONTROL JOINT A metal flashing usually used on chimneys at the roofline to cover
shingle flashing and used to prevent moisture entry.
Tooled, straight grooves made on concrete floors to "control"
where the concrete should crack. COUNTERFORT

COOLING LOAD A foundation wall section that strengthens (and generally


perpendicular to) a long section of foundation wall.
The amount of cooling required to keep a building at a
specified temperature during the summer, usually 78° F, CRAWL SPACE
regardless of outside temperature.
Shallow space below the floor of a building built above ground,
CORBEL generally surrounded with a foundation wall.

The triangular, decorative and supporting member that holds CRICKET


a mantel or horizontal shelf.
A second roof built on top of the primary roof to increase the slope of
CORNER BRACES the roof or valley. A saddle-shaped, peaked construction connecting a
sloping roof with a chimney. Designed to encourage water drainage
Diagonal braces at the corners of the framed structure away from the chimney joint.
designed to stiffen and strengthen the wall.
CRITICAL PATH
CORNICE
The set of activities that must be completed on time for the project
Overhang of a pitched roof , usually consisting of a fascia completion date to be met. Activities on the critical path have no slack
time. CURE

CRITICAL PATH METHOD (C.P.M.) To allow concrete to dry slowly by keeping it moist to allow maximum
strength.
A planning scheduling and control line and symbol diagram
drawn to show the respective tasks and activities involved in CURRENT DATE LINE
constructing a specific project.
A vertical line on the chart indicating the current date.
CROSS BRACING
CURTAIN WALL
Boards nailed diagonally across studs or other boards to
make framework rigid. An exterior wall that provides no structural support.

CROSS BRIDGING DAILY CONSTRUCTION REPORT

Diagonal bracing between adjacent floor joists, placed near A written document and record that has two main purposes:
the center of the joist span to prevent joists from twisting.
1. they furnish information to off-site persons who need and have a
CROSS TEE right to know important details of events as they occur daily and
hourly, and
Short metal "T" beam used in suspended ceiling systems to
bridge the spaces between the main beams. 2. they furnish historical documentation that might later have a legal
bearing in cases of disputes. Daily reports should be as factual and
CSI impersonal as possible, free from the expression of personal opinions
and feelings. Each report should be numbered to correspond with the
Construction Specification Institute working days established on the progress schedule. In the event of no-
work days, a daily report should still be made, stating "no work today"
CSI MASTER FORMAT
( due to rain, strike, or other causes). The report includes a description
The CSI Master Format is a system of numbers and titles for of the weather; a record of the total number of employees,
organizing construction information into a regular, standard subcontractors by name, work started and completed today,
order or sequence. By establishing a master list of titles and equipment on the job site, job progress today, names and titles of
numbers Master Format promotes standardization and thereby visitors, accidents and/or safety meetings, and a remarks column for
facilitates the retrieval of information and improves construction other job related information.
communication. It provides a uniform system for organizing
DATE OF AGREEMENT
information in project manuals, for organizing project cost
data, and for filing product information and other technical data. 1. Usually on the front page of the agreement
CULL 2. If not on front page it may be the date opposite the signatures when
the agreement was actually signed
Building material rejected as below standard grade.
3. or when it was recorded
CUPOLA
4. or the date the agreement was actually awarded to the contractor.
A small structure built on top of a roof to provide ventilation.
DATE OF COMMENCEMENT OF THE WORK entire project as to architectural, structural, mechanical and electrical
systems, materials and other essentials as may be appropriate; and
The date established in a written notice to proceed from the prepares a statement of probable construction cost.
owner to the contractor.
DETAIL
DATE OF SUBSTANTIAL COMPLETION
1. An individual part or item
The date certified by the architect when the work or a
designated portion thereof is sufficiently complete, in 2. A graphical scale representation (drawing at a larger scale) of
accordance with the contract documents, so the owner may construction part(s) or item(s) showing materials, composition and
occupy the work or designated portion thereof for the use for dimensions.
which it is intended.
DIRECT COST (or expense)
DEAD LOAD
All items of expense directly incurred by or attributable to a specific
All the weight in a structure made up of unmovable materials. project, assignment or task. Direct Costs, Hard Costs, and
Construction Costs are synonymous.
DEMISING WALLS
DORMER
The boundaries that separate your space from your neighbors'
and from the public corridor. An opening in a sloping roof, the framing of which projects out to form
a vertical wall suitable for windows or other openings.
DESIGN
DOWNSPOUT
A graphical representation consisting of plan views, interior and
exterior elevations, sections, and other drawings and details to A pipe, usually of metal, for carrying rainwater down from the roof's
depict the goal or purpose for a building or other structure. horizontal gutters.

DESIGN-BUILD CONSTRUCTION DRAW

When a Prime or Main contractor bids or negotiates to provide The amount of progress billings on a contract that is currently
Design and Construction services for the entire construction available to a contractor under a contract with a fixed payment
project. schedule.

DESIGN-CONSTRUCT CONTRACT DRAWINGS

A written agreement between and contractor and owner 1. A term used to represent that portion of the contract documents
wherein the contractor agrees to provide both design and that graphically illustrates the design, location and dimensions of the
construction services. components and elements contained in a specific project

DESIGN-DEVELOPMENT PHASE 2. A line drawing.

The second phase of the architect's basic services wherein Drywall (or Gypsum Wallboard (GWB), Sheet rock or Plasterboard)
the architect prepares drawings and other presentation
documents to fix and describe the size and character of the
Wall board or gypsum ELEVATION

A manufactured panel made out of gypsum plaster and encased The drawings of the front, sides, or rear face of a building.
in a thin cardboard. Usually 1/2" thick and 4' x 8' or 4' x 12' in size.
The panels are nailed or screwed onto the framing and the joints ESTIMATE
are taped and covered with a 'joint compound'. 'Green board' type
1. To calculate approximately the amount, extent or value of
drywall has a greater resistance to moisture than regular (white)
something
plasterboard and is used in bathrooms and other "wet areas".
2. To form an opinion of estimated costs.
DURATION
ESTIMATE OF CONSTRUCTION COST, DETAILED
The length of an activity, excluding holidays and other
non-working days. A calculation of costs prepared on the basis of a detailed analysis of
materials and labor for all items of work, as contrasted with an
EASEMENT
estimate based on current area, volume or similar unit costs. *195
The right to use land owned by another, such as a utility
ESTIMATING
company's right-of-way.
A process of calculating the amount of material, labor and equipment
EAVES
required for a given project necessary to complete the work as
The horizontal exterior roof overhang. specified.

EGRESS EXCAVATION

A means of exiting a space. Normally a 4' X 4' window is the Cavity or pit produced by digging the earth in preparation for
minimum size required. construction.

ELECTRICAL ROUGH EXPANSION JOINT

Work performed by the electrical contractor after the plumber Fibrous material (@1/2" thick) installed in and around a concrete slab
and heating contractor are complete with their phase of work. to permit it to move up and down (seasonally) along the non-moving
Normally all electrical wires, and outlet, switch, and fixture boxes foundation wall.
are installed (before insulation).
FABRICATION
ELECTRICAL TRIM
Work done on parts of a structure at the factory before delivery to the
Work performed by the electrical contractor when the project is building site.
nearing completion. The electrician installs all plugs, switches, light
FACADE
fixtures, smoke detectors, appliance "pig tails", bath ventilation fans,
wires the furnace, and "makes up" the electric panel. The electrician Face or front elevation of a building.
does all work necessary to get ready for and to pass the electrical final
inspection.
FACILITY OR SITE ANALYSIS FINAL INSPECTION

A visual inspection of a building and on-site improvements for A final site review of the project by the contractor, owner or owner’s
functional or physical deterioration; prepare optional authorized representative prior to issuing the final certificate for
Replacement Cost Estimate for making recommendations to payment.
improve functional and physical deficiencies to increase
market value; AND/OR prepare a Reserve Study over five (5) FINAL PAYMENT
years to increase Net Operating Income (NOI) for the facility.
The last payment from the owner to the contractor of the entire unpaid
FAST TRACK CONSTRUCTION (Fast Tracking) balance of the contract sum as adjusted by any approved change
orders.
A method of construction management which involves a
continuous design-construction operation. When a prime or FINISH DATE
main contractor starts the construction work BEFORE the plans
The date that an activity or project is completed.
and specifications are complete.
FIRE-RESISTIVE OR FIRE RATED
FF&E
Applies to materials that are not combustible in the temperatures of
1. An abbreviation for furniture, fixtures and equipment
ordinary fires and will withstand such fires for at least 1 hour.
2. Items classified as personal property rather than real property
FIRE RETARDANT CHEMICAL
3. An abbreviation generally associated with interior design and
A chemical or preparation of chemicals used to reduce the
planning of retail stores or office facilities.
flammability of a material or to retard the spread of flame.
FIELD ORDER
FIRE-STOP
A written order effecting a minor change or clarification in the
Tight closure material or blocking to prevent the spread of flame or
work not involving an adjustment to the contract sum or an
hot gases within framing.
extension of the contract time.
FIXED FEE
FIELD WORK ORDER
A set contract amount for all labor, materials, equipment and services;
A written request to a subcontractor or vendor, usually from the
and contractors overhead and profit for all work being performed for a
general or main contractor, site for services or materials.
specific scope of work.
FINAL ACCEPTANCE
FIXED LIMIT OF CONSTRUCTION COSTS
The action of the owner accepting the work from the contractor
A construction cost ceiling agreed to between the owner and architect
when the owner deems the work completed in accordance with
or engineer for designing a specific project.
the contract requirements. Final acceptance is confirmed by
the owner when making the final payment to the contractor. FLASHING

Sheet metal or other material used in roof and wall construction to


protect a building from water seepage. GANTT CHART

FLOATING The schedule of activities for a project. A Gantt Chart shows start and
finish dates, critical and non-critical activities, slack time, and
The next-to-last stage in concrete work, when you smooth off predecessor relationships.
the job and bring water to the surface by using a hand float
or bull float. GENERAL CONDITIONS

FLOATING WALL A written portion of the contract documents set forth by the owner
stipulating the contractor’s minimum acceptable performance
A non-bearing wall built on a concrete floor. It is constructed so requirements including the rights, responsibilities and relationships of
that the bottom two horizontal plates can compress or pull apart the parties involved in the performance of the contract. General
if the concrete floor moves up or down. Normally built on conditions are usually included in the book of specifications but are
basements and garage slabs. sometimes found in the architectural drawings.
FORM GENERAL CONTRACTOR
Temporary structure erected to contain concrete during placing Properly licensed individual or company having primary (prime)
and initial hardening. responsibility for the work.
FOOTPRINT GENERAL CONTRACTING (the traditional method)
The outline of a building's foundation; used for site planning. When a prime or main contractor bids the entire work AFTER the final
design, plans and specifications are complete and have been
FOUNDATION
approved by the owner.
The supporting portion of a structure below the first floor
GIRDER
construction, or below grade, including the footings.
A large or principal beam of wood or steel used to support
FOUNDATION TIES
concentrated loads at isolated points along its length.
Metal wires that hold the foundation wall panels and rebar in
GRADE
place during the concrete pour.
Ground level, or the elevation at any given point. Also the work of
GABLE
leveling dirt. Also the designated quality of a manufactured piece of
The end, upper, triangular area of a home, beneath the roof. wood.

GAMBREL ROOF GRID

A roof with two slopes on each side, the lower slope steeper The completed assembly of main and cross tees in a suspended
than the upper. ceiling system before the ceiling panels are installed.

HEATING LOAD

The amount of heating required to keep a building at a specified


temperature during the winter, usually 65° F, regardless of 2. The condition of being indemnified.
outside temperature.
INDIRECT COST (or expense)
HEAT ROUGH
A contractor’s or consultant’s overhead expense; expenses indirectly
Work performed by the heating contractor after the stairs and incurred and not chargeable to a specific project or task. The terms
interior walls are built. This includes installing all duct work and Indirect costs and soft costs are synonymous .
flue pipes. Sometimes, the furnace and fireplaces are installed
at this stage of construction. INSPECTION

HEAT TRIM 1. The act of inspecting.

Work done by the heating contractor to get ready for the Final 2. An official examination or review of the work completed or in
Heat Inspection. This includes venting the hot water heater, progress to determine its compliance with contract requirements.
installing all vent grills, registers, air conditioning services,
INSPECTION FOR DISBURSEMENT OF FUNDS
turning on the furnace, installing thermostats, venting ranges
and hoods, and all other heat related work. An independent vehicle for the disbursement and accounting of
construction funds allowing construction obligations to be paid
HIP
(progress payments) when work is completed, inspected and
A roof with four sloping sides. The external angle formed by the approved. Job Costs are reviewed prior to making disbursements to
meeting of two sloping sides of a roof. establish that the actual construction payments are within the
confines of the original estimate confines or schedule of construction
I-BEAM values.

A steel beam with a cross section resembling the letter I. It is INSPECTION LIST (PUNCH LIST)
used for long spans as basement beams or over wide wall
openings when wall and roof loads bear down on the opening. A list prepared by the owner or his/her authorized representative of
items of work requiring immediate corrective or completion action by
INDEPENDENT CONTRACTOR the contractor.

One free from the influence, guidance, or control of another or INSPECTION REPORT
others and does not owe a "fiduciary duty". Example: architect,
engineer, prime or main contractor, construction manager at-risk. Sometimes used to describe an Inspection List.

IMPROVEMENTS INSPECTOR

1. A term sometimes used to describe TI'S or Tenant Improvements. One who is appointed or employed to inspect something.

2. Improvements can be in the form of new construction or INTERIOR FINISH


remodel work.
A term used to represent the visible elements, materials and
INDEMNIFICATION applications applied to a building’s interior excluding furniture, fixtures
and equipment.
1.The act of indemnifying.
INVOICE Conditional Lien Waiver, Unconditional Lien Waiver, and Final Lien
Waiver.
A list sent to a purchaser containing the items and charges of
merchandise. LINTEL

JOIST A horizontal structural member that supports the load over an opening
such as a door or window.
Structural member which directly supports floors or ceilings
adn is supported by bearing walls, beam, or girders. LIVE LOAD

LABOR AND MATERIAL PAYMENT BOND The total of all moving and variable loads that may be placed upon a
building.
A written form of security from a surety (bonding) company to
the owner, on behalf of an acceptable prime or main contractor or LOAD BEARING WALL
subcontractor, guaranteeing payment to the owner in the event
the contractor fails to pay for all labor, materials, equipment, or Includes all exterior walls and any interior wall that is aligned above a
services in accordance with the contract. support beam or girder.

LEASEHOLD IMPROVEMENTS LOGGIA

A term used to mean Tenant Improvements. Generally, this term A roofed open gallery, often on an upper level.
is used when building in retail stores as contrasted with the term
LUMENS
Tenant Improvements which are generally associated with office
buildings. The terms are often used interchangeably. Unit of measure for total light output. The amount of light falling on a
surface of one square foot.
LIEN, MECHANIC'S OR MATERIAL
LUMP SUM BID
The right to take and hold or sell an owner’s property to satisfy
unpaid debts to a qualified contractor for labor, materials, A single entry amount to cover all labor, equipment, materials, services,
equipment or services to improve the property. and overhead and profit for completing the construction of a variety of
unspecified items of work without the benefit of a cost breakdown.
LIEN RELEASE
LUMP SUM CONTRACT
A written document from the contractor to the owner that releases
the Lien, Mechanic’s or Material following it’s satisfaction. A written contract between the owner and contractor wherein the
owner agrees the pay the contractor a specified sum of money for
LIEN WAIVER
completing a scope of work consisting of a variety of unspecified
1. An written document from a contractor, subcontractor, material items or work.
supplier or other construction professional(s), having lien rights
MANSARD ROOF
against an owner’s property, relinquishes all or part of those rights.
A roof with two slopes on each side, with the lower slope being nearly
2. Lien waivers are generally used for processing progress
vertical and the upper slope nearly horizontal.
payments to prime or main or subcontractors as follows:
MASONRY MONOPOST

Stone, brick, concrete, hollow-tile, concrete block, or other similar Adjustable metal column used to support a beam or bearing point.
building units or materials. Normally bonded together with mortar
to form a wall. MYLAR

MEETING ATTENDANCE FORM Plastic, transparent copies of a blueprint.

A form consisting of three columns (individuals name, individuals NEC (National Electrical Code)
title, and company the individual represents). This form is given to
A set of rules governing safe wiring methods. Local codes—which are
all persons attending any meeting. Each person attending the
backed by law—may differ from the NEC in some ways.
meeting will complete their respective information. The date of
the meeting should be included for reference. NONBEARING WALL
MEETING NOTES A wall supporting no load other than its own weight.
A written report consisting of a project number, project name, OC- On Center
meeting date and time, meeting place, meeting subject, a list of
persons attending, and a list of actions taken and/or discussed The measurement of spacing for studs, rafters, and joists in a building
during the meeting. Generally, this report is distributed to all from the center of one member to the center of the next.
persons attending the meeting and any other person having an
interest in the meeting. OPEN BID/ESTIMATE

MILESTONE A service where any bidder or estimator is given access to project


specific RFP (Request for Proposal) information. This option is for
An activity with a duration of zero (0) and by which progress those seeking bids/estimates from any interested professionals or
of the project is measured. A milestone is an informational service with out prequalifying them.
marker only; it does not affect scheduling.
ORIENTATION
MILLWORK
The positioning of a building on a lot in relation to the sun, wind, view,
Generally all building materials made of finished wood and and noise.
manufactured in millwork plants. Includes all doors, window and
door frames, blinds, mantels, panelwork, stairway components OUTRIGGER
(ballusters, rail, etc.), moldings, and interior trim. Does not
include flooring, ceiling, or siding. An extension of a rafter beyond the wall line. Usually a smaller
member nailed to a larger rafter to form a cornice or roof overhang.
MONOLITHIC
OWNER
Term used for concrete work poured and cast in one piece
without joints. An individual or corporation that owns a real property.
OWNER-ARCHITECT AGREEMENT standards and actions, as may be necessary to complete a project.
Including the minimum acceptable quality standards and aesthetic
A written form of contract between architect and client for values expected upon completion of the project.
professional architectural services.
PERGOLA
OWNER-BUILDER
Open, structural framework over an outdoor area, usually covered with
A term used to describe an Owner who takes on the climbing vines to form an arbor.
responsibilities of the general contractor to build a specific
project. PERT

OWNER-CONSTRUCTION AGREEMENT An abbreviation for Program Evaluating and Review Technique.

Contract between owner and contractor for a construction project. PERT SCHEDULE

OWNER-CONSTRUCTION MANAGEMENT AGREEMENT A diagram that illustrates, charts and reports a projects estimated
start and completion times; and work in progress.
Contract between construction manager and client for
professional services. PIER

PARAPET A column of masonry, usually rectangular in horizontal cross section,


used to support other structural members.
A wall placed at the edge of a roof to prevent people from
falling off. PITCH

PARTITION The incline slope of a roof or the ratio of the total rise to the total
width, i.e., a 6-foot rise and 24-foot width is a one-fourth pitch roof.
A wall that subdivides spaces within any story of a building Roof slope is expressed in the inches of rise, per foot of horizontal run.
or room.
PLAN
PERFORMANCE BOND
1. A line drawing (by floor) representing the horizontal geometrical
1. A written form of security from a surety (bonding) company section of the walls of a building. The section (a horizontal plane) is
to the owner, on behalf of an acceptable prime or main contractor taken at an elevation to include the relative positions of the walls,
or subcontractor, guaranteeing payment to the owner in the event partitions, windows, doors, chimneys, columns, pilasters, etc.
the contractor fails to perform all labor, materials, equipment, or
services in accordance with the contract. 2. A plan can be thought of as cutting a horizontal section through a
building at an eye level elevation.
2. The surety companies generally reserve the right to have the
original prime or main or subcontractor remedy any claims before PLAN CHECKER
paying on the bond or hiring other contractors.
A term sometimes used to describe a building department official who
PERFORMANCE SPECIFICATIONS examines the building permit documents.

The written material containing the minimum acceptable


PLAN VIEW PREDECESSOR

Drawing of a structure with the view from overhead, looking down. An activity that must be completed before another activity can begin.

PLANNER PRELIMINARY DRAWINGS

A person who forms a scheme or method for doing something; 1. The drawings that precede the final approved drawings.
an arrangement of means or steps for the attainment of some
object; a scheme, method, design; a mode of action. 2. Usually these drawings are stamped or titled "PRELIMINARY"; and
the "PRELIMINARY" is removed from the drawings upon being
PLANS reviewed and approved by the owner.

A term used to represent all drawings including sections and PRELIMINARY LIEN NOTICE
details; and any supplemental drawings for complete execution
of a specific project. A written notice given to the property owner of a specific project by
the subcontractors and any person or company furnishing services,
PLUMBING ROUGH equipment or materials to that project. The notice states if bills are not
paid in full for the labor, services, equipment, or materials furnished or
Work performed by the plumbing contractor after the Rough Heat to be furnished, a mechanic's lien leading to the loss, through court
is installed. This work includes installing all plastic ABS drain and foreclosure proceedings, of all or part of the property being so
waste lines, copper water lines, bath tubs, shower pans, and gas improved may be placed against the property even through the owner
piping to furnaces and fireplaces. has paid the prime contractor in full. The notice explains how the
owner can protect himself against this consequence by 1. requiring
PLUMBING TRIM
the prime contractor to furnish a signed release by the person or firm
Work performed by the plumbing contractor to get ready for a thus giving the owner notice before making payment to the prime
final plumbing inspection. Includes installing all toilets (water contractor or 2. any other method or device which is appropriate under
closets), hot water heaters, sinks, connecting all gas pipe to the circumstances. The state of California mandates that a
appliances, disposal, dishwasher, and all plumbing items. Preliminary Lien Notice must be given to the property owner not more
than 20 days after starting the work on the specific project.
POST-AND-BEAM
Pre-qualification of prospective bidders
A basic building method that uses just a few hefty posts and
beams to support an entire structure. Contrasts with stud framing. A screening process wherein the owner or his/her appointed
representative gathers background information from a contractor or
PRECAST construction professional for selection purposes. Qualifying
considerations include competence, integrity, dependability,
Concrete shapes made separately before being used in a structure. responsiveness, bonding rate, bonding capacity, work on hand, similar
project experience, and other specific owner requirements.
Pre-Construction Planning and Team Building

A process used for the purpose of establishing below market dollar


budget(s), overall project scheduling and design criteria; also Reference:
identification and selection of the most feasible project design and
construction team. https://operations.fs.cornell.edu/info/ir_glossary.cfm#R
Republic of the Philippines

SORSOGON STATE UNIVERSITY

College of Engineering and Architecture

BACHELOR OF SCIENCE IN ARCHITECTURE

Sorsogon City

CONSTRUCTION
TERMINOLOGIES

Rhea Lyn M. Leoncito

BS Architecture 3B

You might also like