OWS

ACCOMPLISHMENT
Item Description Wgt % Material Labor Material Labor OVERALL
MAIN OWS (Oil/Water Separator)
A Excavation Works
1 Excavation 8.75% 5.69% 3.06% 5.69% 3.06% 8.75%
B Concrete Works
1 Portland Cement 25.26% 16.42% 8.84% 16.42% 8.84% 25.26%
2 Sand 2.95% 1.91% 1.03% 1.91% 1.03% 2.95%
3 Gravel 7.57% 4.92% 2.65% 4.92% 2.65% 7.57%
C Structural Rebars
1 12mm dia. X 6m RSB 15.81% 10.28% 5.53% 10.28% 5.53% 15.81%
2 G.I. Wire #16 0.77% 0.50% 0.27% 0.50% 0.27% 0.77%
D Formworks and Scaffoldings
1 3/8'' x 4' x 8' Plywood 4.57% 2.97% 1.60% 2.97% 1.60% 4.57%
2 2'' x 3'' x 12' Cocolumber 3.36% 2.18% 1.17% 2.18% 1.17% 3.36%
3 Asstd. C.W. nails 0.41% 0.26% 0.14% 0.26% 0.14% 0.41%
E Masonry Works
1 Portland Cement 5.13% 3.33% 1.79% 3.33% 1.79% 5.13%
2 Fine sand 0.73% 0.48% 0.26% 0.48% 0.26% 0.73%
F Pipe/Hardwares
1 4'' dia. X 6m B.I. Pipe 5.13% 3.33% 1.79% 3.33% 1.70% 5.04%
2 4'' dia. B.I. Tee 0.16% 0.10% 0.05% 0.10% 0.05% 0.16%
3 12mm dai. U-Bolt 0.15% 0.10% 0.05% 0.10% 0.05% 0.15%
4 1/4'' x 2-1/2'' x 6m Flat Bar 0.16% 0.11% 0.06% 0.11% 0.06% 0.16%
5 12mm dia. X 3'' Expansion Bolt 0.08% 0.05% 0.03% 0.05% 0.03% 0.08%
6 16mm dia. X 6m Plain Round Bar 0.18% 0.12% 0.06% 0.12% 0.06% 0.18%
G Steel Cover
1 1/4'' x 2'' x 6m Angle Bar 3.84% 2.49% 1.34% 2.49% 0.13% 2.63%
2 1/4'' x 1-1/2'' x 6m Flat Bar 11.96% 7.77% 4.19% 7.77% 0.42% 8.19%
3 Welding Rod 0.61% 0.40% 0.21% 0.40% 0.02% 0.42%
H Painting Works
1 Painting Materials 2.44% 1.59% 0.85% 0.00% 0.00% 0.00%
Sub-Total
TOTAL 100.00% 65.00% 35.00% 92.30%