Professional Documents
Culture Documents
Method Statement - V Drain
Method Statement - V Drain
0 Work Procedure
1.1 Setting Out
1.1.1 Surveyor to set of points and establish of Temporary Bench Mark
(TBM) level.
1.1.2. Setting out and Pegging work for drainage line shall be
established.
1.3 Excavation
1.3.1 Use excavators to dig the trench according to the specified
dimensions and slope, allowing space for the precast V-drain.
1.3.2 Once the formation level is achieved, the bed of excavation shall be
compacted immediately.
1.3.3 All excavations shall be provided with stable side slopes to
minimize slope collapse and to ensure safety at all times.
1.3.4 Excavated soil that is not needed for backfilling will be reuse for the
slope construction.
1.4 Levelling Concrete
1.4.1 Make sure the leveling for V-drain is establish.
1.4.2 Pour the lean concrete in to the excavation area. Make sure the
thickness is 50mm.