Method Statement - U Drain
Method Statement - U Drain
0 Work Procedure
1.1 Setting Out
1.1.1 Surveyor to set of points and establish of Temporary Bench Mark
(TBM) level.
1.1.2. Setting out and Pegging work for drainage line shall be
established.
1.3 Excavation
1.3.1 Use excavators to dig the trench according to the specified
dimensions and slope, allowing space for the precast U-shape
drain elements.
1.3.2 Once the formation level is achieved, the bed of excavation shall be
compacted immediately.
1.3.3 All excavations shall be provided with stable side slopes to
minimize slope collapse and to ensure safety at all times.
1.3.4 Excavated soil that is not required for backfilling will be stockpiled
on-site for future use in landscaping or other construction activities.