DALMAU NAGAR PANCHAYAT SEWER SYSTEM AND APPURTENANT WORKS,

DISTRICT-RAEBARELI
ABSTRACT OF COST INTERCEPTOR SEWER
S.
No. Description of works Qty. Unit Rate Amount
1 3 4 5 6 7
1
Excavation for following depth below ground level
for laying of sewers, manholes, gulley pits, sumps
etc. in ordinary soil including cutting of joints pits,
triming, dressing, leveling, refilling of trenches in 15
cm layer. (8% reduction due to excavation already
taken in manhole)
(A) Ordinary soil
A. 0.00 - 1.50 m. depth 7102.92 Cum 227.01 1612432.78
B. 1.50 - 3.00 m. depth 4775.19 Cum 285.96 1365512.30
C. 3.00 - 4.50 m. depth 2156.77 Cum 359.88 776176.66
D. 4.50 - 6.00 m. depth 741.44 Cum 420.98 312130.23
E. 6.00 - 7.50 m. depth 38.82 Cum 550.60 21376.49
2 Provide and fix open timbering (covering 1/3rd
surface area by planks) in trenches for the depth
from 0.00 to 3.00 m. below ground level consisting
of 4.00 cm. thick approved country wood planks for
polling boards (125 cm x 75 cm) Indian sal wood
waler.
(a) 0.0 - 3.00 m 862.92 Sqm 367.53 317148.99
3 Same as above but for close timbering below ground
level with 50 mm. Thick country wood planks 150
mm. X 75 mm. Indian sal wood walers and 125 mm.
Thick sal ballies.

0.00 - 3.00 m. depth 4818.00 Sqm 544.51 2623449.18


3.00 - 6.00 m. depth 2340.97 Sqm 703.38 1646591.48
6.00 - 7.50 m. depth 42.20 Sqm 840.88 35485.14
4 Same as items N. 4-B but left in Trenchess (used
timbering) @ 2 %
0.00 - 3.00 m. depth 48.18 Sqm 1215.59 58567.13
3.00 - 6.00 m. depth 46.82 Sqm 1520.04 71168.27
6.00 - 7.50 m. depth 0.42 Sqm 1766.72 742.02
5 Well graded crushed rock or gravel maximum size
25mm.
0.00 - 1.50 m. depth 189.33 M3 2670.00 505511.10
1.50 - 3.00 m. depth 227.87 M3 2750.10 626665.29
3.00 - 4.50 m. depth 14.74 M3 2856.90 42110.71
4.50 - 6.00 m. depth 169.10 M3 2990.40 505676.64
6.00 - 7.50 m. depth 32.85 M3 3204.00 105251.40
6 10 mm thick lean concrete work in beding below GL
at special depth with cement, local sand and 40mm
gauge brick ballast in 1:5:10 including supply of all 7091.39
material labour T&P etc. complete. Or PCC 1:4:8
1.50 - 3.00 m. depth 1.60 M3 7304.13 11686.61
3.00 - 4.50 m. depth 73.30 M3 7587.79 556184.81
4.50 - 6.00 m. depth 2.80 M3 7942.36 22238.60
S.
No. Description of works Qty. Unit Rate Amount
1 3 4 5 6 7
7 Cement concrete work in bedding below G.L. at
specified depth with cement, coarse sand and 20
mm guage approved stone ballast (1:2:4) including
supply of all materials, labour, T&P etc. required for
proper completion of work.
8445.73
a. 1.50 - 3.00 m. depth 1.40 Cum 8699.10 12178.74
b. 3.00 - 4.50 m. depth 63.95 Cum 9036.93 577911.74
c. 4.50 - 6.00 m. depth 2.44 Cum 9459.22 23080.49
d. 6.00 - 7.50 m. depth 0.00 Cum 10134.88 0.00
8 Supply of following sizes of R.C.C. non pressure pipes
with rubber gasket including all taxes.
(A) For RCC Sewer Pipes
For NP3 Pipes 1415.70
350 mm dia 2379.00 M 1573.00 3742167.00
(B) For NP4 Pipes
300 mm dia 100.00 M 1197.90 119790.00
350 mm dia 765.00 M 1730.30 1323679.50
9 Carting of following sizes of pipes including
transportation, loading and unloading and R.C.C.
non pressure pipes class NP3 and NP4 socket/spigot
rubber ring jointing and specials from store to the
site of work lowering the same into trenches in the
following depth below ground level, true to
alignment, caulking the joints with necessary open
yarn soaked.

1579.986
For RCC NP3 Pipes
350 mm. Dia
0.00 - 1.50 m depth 732.00 M 1755.54 1285055.28
1.50 - 3.00 m. depth 1100.00 M 1868.77 2055649.56
3.00 - 4.50 m. depth 540.00 M 1984.64 1071704.50
4.50 - 6.00 m. depth 7.00 M 2119.81 14838.70
6.00 - 7.50 m. depth 0.00 M 2309.41 0.00
For RCC NP4 Pipes
300 mm. Dia
0.00 - 1.50 m depth 0.00 M 1737.98 0.00
1.50 - 3.00 m. depth 0.00 M 1850.08 0.00
3.00 - 4.50 m. depth 28.00 M 1964.79 55014.16
4.50 - 6.00 m. depth 72.00 M 2098.62 151100.38
6.00 - 7.50 m. depth 0.00 M 2286.32 0.00
350 mm. Dia
0.00 - 1.50 m depth 0.00 M 1911.78 0.00
1.50 - 3.00 m. depth 16.00 M 2035.09 32561.49
3.00 - 4.50 m. depth 88.00 M 2161.27 190191.83
4.50 - 6.00 m. depth 582.00 M 2308.48 1343534.22
6.00 - 7.50 m. depth 79.00 M 2514.95 198681.10
10 Sand filling including supply of all materials, labout
T&P etc. required for proper completion of work for
road crossing and as and where required as per site
conditiond during execution of work.

145.49 Sqm 829.52 120686.86


S.
No. Description of works Qty. Unit Rate Amount
1 3 4 5 6 7
11 Supply of all materials , labour T & P etc. and
construct of circular manhole of following depth as
pe type design (unit estimate enclosed)
900 mm internal dia upto 1.65 m deep 33.00 No. 17800.00 587400.00
1200 mm internal dia upto 2.3 m deep 20.00 No. 45700.00 914000.00
1500 mm internal dia upto 5.0 m deep 23.00 No. 161500.00 3714500.00
12 Increase/decrease in manhole shaft for every
additional depth in following size of circular
manhole.
900 mm internal dia upto 1.65 m deep 23.86 M 7435.75 177409.55
1200 mm internal dia upto 3.3 m deep 24.14 M 11915.18 287632.34
1500 mm internal dia upto 4.95 m deep 30.57 M 33684.65 1029638.70
13 Dismantling of roads for laying sewers including
sorting out and stacking of serviciable materials, and
diposal of unserviciable materials upto a distance of
60m and its reinstatement after filling and proper
compaction of trenches.

(a) Bitumen Road 8153.50 Sqm 163.18 1330488.13


14 Provision for road reinstatement charges.
(a) Bitumen Road 8153.50 Sqm 2462.86 20080929.01
15 Disposal of surplus earth 2564.00 m3 240.27 616060.83
16 Provide,erect and remove casurina pole three tier
barrcading using poles of 100 mm/80mm dia and
1.50 height above ground level (0.30 m BGL) fixed
vertically @ 2.5 m c/c and horizontally @ 0.50 m and
tied with coir rope firmly.

4055.00 M 163.00 660965.00


TOTAL SEWER SYSTEM 52932954.95
SAY (in Lacs) 529.00
DALMAU NAGAR PANCHAYAT SEWER SYSTEM AND APPURTENANT WORKS,
DISTRICT-RAEBARELI

DETAILED MEASUREMENT OF INTERCEPTOR SEWER

S. No. Description of works No L B H Qty

1 2 3 4 5 6 7
SEWER NETWORK
1 Excavation for following depth below ground level
for laying of sewers, manholes, gulley pits, sumps
etc. in ordinary soil including cutting of joints pits,
triming, dressing, leveling, refilling of trenches in 15
cm layer. (8% reduction due to excavation already
taken in manhole)

(A) Ordinary soil


A. 0.00 - 1.50 m. depth 7720.56 - - 7102.92 M3
B. 1.50 - 3.00 m. depth 5190.42 - - 4775.19 M3
C. 3.00 - 4.50 m. depth 2344.31 - - 2156.77 M3
D. 4.50 - 6.00 m. depth 805.91 - - 741.44 M3
E. 6.00 - 7.50 m. depth 42.20 - - 38.82 M3
2 I. Provide and fix open timbering (covering 1/3rd
surface area by planks) in trenches for the depth
from 0.00 to 3.00 m. below ground level consisting
of 4.00 cm. thick approved country wood planks for
polling boards (125 cm x 75 cm) Indian sal wood
waler.

(a) 0.0 - 3.00 m 862.92 862.92 M2


3 I. Same as above but for close timbering below
ground level with 50 mm. Thick country wood
planks 150 mm. X 75 mm. Indian sal wood walers
and 125 mm. Thick sal ballies.

0.00 - 3.00 m. depth 4818.00 4818.00 M2


3.00 - 6.00 m. depth 2340.97 - - 2340.97 M2
6.00 - 7.50 m. depth 42.20 - - 42.20 M2
4 Same as items N. 4-B but left in Trenchess (used
timbering) @ 1 %
0.00 - 3.00 m. depth 48.18 - - 48.18 M2
3.00 - 6.00 m. depth 46.82 - - 46.82 M2
6.00 - 7.50 m. depth 0.42 - - 0.42 M2
5 Well graded crushed rock or gravel maximum size
25mm.
0.00 - 1.50 m. depth 189.33 189.33 M3
1.50 - 3.00 m. depth 227.87 227.87 M3
3.00 - 4.50 m. depth 14.74 14.74 M3
4.50 - 6.00 m. depth 169.10 169.10 M3
6.00 - 7.50 m. depth 32.85 32.85 M3
S. No. Description of works No L B H Qty

1 2 3 4 5 6 7
6 10 mm thick lean concrete work in beding below GL
at special depth with cement, local sand and 40mm
gauge brick ballast in 1:5:10 including supply of all - -
material labour T&P etc. complete. Or PCC 1:4:8

1.50 - 3.00 m. depth 1.60 - 1.60 M3


3.00 - 4.50 m. depth 73.30 - 73.30 M3
4.50 - 6.00 m. depth 2.80 - 2.80 M3
7 Cement concrete work in bedding below G.L. at
specified depth with cement, coarse sand and 20
mm guage approved stone ballast (1:2:4) including
supply of all materials, labour, T&P etc. required for - -
proper completion of work.

a. 1.50 - 3.00 m. depth 1.40 - - 1.40 M3


b. 3.00 - 4.50 m. depth 63.95 - - 63.95 M3
c. 4.50 - 6.00 m. depth 2.44 - - 2.44 M3
d. 6.00 - 7.50 m. depth 0.00 - - 0.00 M3
8 Supply of following sizes of R.C.C. non pressure
pipes with rubber gasket including all taxes.
(A) For RCC Sewer Pipes
i For NP3 Pipes
350 mm dia 2379.00 2379.00 M
ii For NP4 Pipes
300 mm dia 100.00 - - 100.00 M
350 mm dia 765.00 - - 765.00 M
9 Carting of following sizes of pipes including
transportation, loading and unloading and R.C.C.
non pressure pipes class NP3 and NP4 socket/spigot
rubber ring jointing and specials from store to the
site of work lowering the same into trenches in the
following depth below ground level, true to
alignment, caulking the joints with necessary open
yarn soaked.

(A) For RCC NP3 Pipes


(i) 350 mm. Dia
0.00 - 1.50 m depth 732.00 - - 732.00 M
1.50 - 3.00 m. depth 1100.00 - - 1100.00 M
3.00 - 4.50 m. depth 540.00 - - 540.00 M
4.50 - 6.00 m. depth 7.00 - - 7.00 M
6.00 - 7.50 m. depth 0.00 - - 0.00 M
(B) For RCC NP4 Pipes
(i) 300 mm. Dia
0.00 - 1.50 m depth 0.00 - - 0.00 M
1.50 - 3.00 m. depth 0.00 - - 0.00 M
3.00 - 4.50 m. depth 28.00 - - 28.00 M
4.50 - 6.00 m. depth 72.00 - - 72.00 M
6.00 - 7.50 m. depth 0.00 - - 0.00 M
(i) 350 mm. Dia
0.00 - 1.50 m depth 0.00 - - 0.00 M
S. No. Description of works No L B H Qty

1 2 3 4 5 6 7
1.50 - 3.00 m. depth 16.00 - - 16.00 M
3.00 - 4.50 m. depth 88.00 - - 88.00 M
4.50 - 6.00 m. depth 582.00 - - 582.00 M
6.00 - 7.50 m. depth 79.00 - - 79.00 M
10 Sand filling including supply of all materials, labout
T&P etc. required for proper completion of work for
road crossing and as and where required as per site
conditiond during execution of work.

145.49 - - 145.49 M3
11 Supply of all materials , labour T & P etc. and
construct of circular manhole of following depth as
pe type design (unit estimate enclosed)

a. 900 mm internal dia upto 1.65 m deep 33 33.00 No.


b. 1200 mm internal dia upto 3.3 m deep 20 20.00 No.
c. 1500 mm internal dia upto 4.95 m deep 23 23.00 No.
12 Increase / decrease in manhole shaft for every
additional depth in following size of circular
manhole.

a. 900 mm internal dia upto 1.65 m deep 23.86 23.86 M


b. 1200 mm internal dia upto 3.3 m deep 24.14 24.14 M
c. 1500 mm internal dia upto 4.95 m deep 30.57 30.57 M
13 Dismantling of roads for laying sewers including
sorting out and stacking of serviciable materials, and
diposal of unserviciable materials upto a distance of
60m and its reinstatement after filling and proper
compaction of trenches.
638.69
(a) Bitumen Road 8153.50 - - 8153.50 M2

14 Provision for road reinstatement charges.

(a) Bitumen Road 8153.50 - 8153.50 M2


15 Disposal of surplus earth 2564.00 - - 2564.00 M3
16 Provide,erect and remove casurina pole three tier
barrcading using poles of 100 mm/80mm dia and
1.50 height above ground level (0.30 m BGL) fixed
vertically @ 2.5 m c/c and horizontally @ 0.50 m and
tied with coir rope firmly.
4055.00 4055.00 RM

Assistant Engineer
DETAILS OF INTERCEPTOR SEWER AS PER DESIGN
Node Quantity of Earth work in Cum. Open Closed Timbering Well graded crushed rock or grvel Type of
Name of main

Length
Dia of pipe
(mm)
Road
Timbering max. size 25mm (in Cum)
From

To 0.0 to 1.5 1.5 to 3.0 3.0 to 4.5 4.5 to 6.0 6.0 to 7.9 <1.5 1.5-3.0 <1.5 1.5-3.0 3.0-4.5 4.5-6.0 6.0-7.9 0.0-1.5 1.5-3.0 3.0-4.5 4.5-6.0 6.0-7.9

TM 14 15 144 350 598.50 490.50 382.50 239.29 48.98 216 216 216 180.79 48.98 18.11 14.23 BOE

TM 15 16 200 350 750.00 600.00 450.00 90.30 300 300 300 90.3 51.73 BOE

TM 16 STP 45 350 165.00 131.25 97.30 10.80 67.5 67.5 67.3 10.8 1.29 10.35 BOE

BS0020 58 14 109 350 490.50 408.75 327.00 245.25 127.07 163.5 163.5 163.5 163.5 127.0 BT

TOTAL 498 2004 1630.5 1256.8 585.64 176.05 0 0 747 747 746.8 445.39 176.02 0 0 1.29 80.19 14.23

10 cm thick lean 1:2:4 RCC for Craddle in Cum 350mm dia pipe laying jointing Manhole
Concrete in Cum
1.5-3.0 3.0-4.5 6.0-7.9 0.0-1.5 1.5-3.0 3.0-4.5 4.5-6.0 6.0-7.9 0.0-1.5 1.5-3.0 3.0-4.5 4.5-6.0 6.0-7.9 0.0-1.5 1.5-3.0 3.0-4.5 4.5-6.0 6.0-7.9

1.9 1.66 83 61 1 1
200 3
20 25 1
10.9 9.51 109 2
0 0 12.8 0 0 0 0 11.17 0 0 20 308 170 0 0 0 5 3
BARIYARPUR NAGAR PANCHAYAT SEWER SYSTEM AND APPURTENANT WORKS,
DISTRICT-DEORIA

ABSTRACT OF COST GRAVITY SEWER


S. SOR Ref.
No. Description of works Qty. Unit Rate Amount
1 2 3 4 5 6 7
1
Excavation for following depth below ground level
for laying of sewers, manholes, gulley pits, sumps
etc. in ordinary soil including cutting of joints pits,
triming, dressing, leveling, refilling of trenches in 15
cm layer. (8% reduction due to excavation already
taken in manhole and SCC)
(A) Ordinary soil
3001 A. 0.00 - 1.50 m. depth 2004.00 Cum 243.67 488314.68
3002 B. 1.50 - 3.00 m. depth 3192.42 Cum 305.39 974933.14
2 Provide and fix open timbering (covering 1/3rd surface
area by planks) in trenches for the depth from 0.00 to
3.00 m. below ground level consisting of 4.00 cm. thick
approved country wood planks for polling boards (125
cm x 75 cm) Indian sal wood waler.

3041 (a) 0.0 - 3.00 m 0.00 cum 424.22 0.00


3 Same as above but for close timbering below ground
level with 50 mm. Thick country wood planks 150 mm. X
75 mm. Indian sal wood walers and 125 mm. Thick sal
ballies.

3032 0.00 - 3.00 m. depth 7201.17 cum 725.43 5223944.75


4 Same as items N. 4-B but left in Trenchess (used
timbering) @ 2 %
3038 0.00 - 3.00 m. depth 72.01 cum 1679.86 120969.57
5 Supply of following sizes of DWC SN-8/R.C.C. non
pressure pipes with rubber gasket including all taxes.

DWC SN-8 Pipe


QUOT 150 mm dia 0.00 M 189.33 0.00
QUOT 200 mm dia 0.00 M 284.00 0.00
QUOT 250 mm dia 0.00 M 442.00 0.00
For RCC Sewer Pipes
For NP3 Pipes
3024 300 mm dia 0.00 720.00 0.00
3025 350 mm dia 498.00 1160.00 577680.00
6 Carting of following sizes of pipes including
transportation, loading and unloading and DWC/R.C.C.
non pressure pipes class NP3 and NP4 socket/spigot
rubber ring jointing and specials from store to the site of
work lowering the same into trenches in the following
depth below ground level, true to alignment, caulking the
joints with necessary open yarn soaked.
S. SOR Ref.
No. Description of works Qty. Unit Rate Amount
1 2 3 4 5 6 7
DWC Sewer pipes
150 mm. Dia
SOR 0.00 - 1.50 m depth 0.00 56.68 0.00
SOR 1.50 - 3.00 m. depth 0.00 60.00 0.00
SOR 3.00 - 4.50 m. depth 0.00 63.88 0.00
SOR 4.50 - 6.00 m. depth 0.00 68.75 0.00
200 mm. Dia
SOR 0.00 - 1.50 m depth 0.00 65.57 0.00
SOR 1.50 - 3.00 m. depth 0.00 69.41 0.00
SOR 3.00 - 4.50 m. depth 0.00 73.90 0.00
SOR 4.50 - 6.00 m. depth 0.00 79.54 0.00
250 mm. Dia
SOR 0.00 - 1.50 m depth 0.00 72.13 0.00
SOR 1.50 - 3.00 m. depth 0.00 76.35 0.00
SOR 3.00 - 4.50 m. depth 0.00 81.29 0.00
SOR 4.50 - 6.00 m. depth 0.00 87.49 0.00
6.00 - 7.50 m. depth 0.00
For RCC NP3 Pipes
90% 300 mm. Dia
3194 0.00 - 1.50 m depth 0.00 935.59 0.00
3205 1.50 - 3.00 m. depth 0.00 995.93 0.00
3206 3.00 - 4.50 m. depth 0.00 1057.68 0.00
3207 4.50 - 6.00 m. depth 0.00 1129.72 0.00
350 mm. Dia
3194 0.00 - 1.50 m depth 20.00 1039.54 20790.80
3205 1.50 - 3.00 m. depth 478.00 1106.59 528950.18
7 1017 Cement concrete work in bedding below G.L. at specified
depth with cement, coarse sand and 20 mm guage
approved stone ballast (1:2:4) including supply of all
materials, labour, T&P etc. required for proper
completion of work.

3190 a. 1.50 - 3.00 m. depth 11.57 8450.13 97768.01


8 1004 Sand filling including supply of all materials, labout T&P
etc. required for proper completion of work for road
crossing and as and where required as per site conditiond
during execution of work.
11.17 1218.35 13608.97
9 Supply of all materials , labour T & P etc. and construct of
Brick circular manhole of following depth as pe type
design (unit estimate enclosed)

AOR 900 mm internal dia upto 1.65 m deep 0.00 18400.00 0.00
AOR 1200 mm internal dia upto 3.3 m deep 8.00 46400.00 371200.00
AOR 1500 mm internal dia upto 4.95 m deep 0.00 138500.00 0.00
10 Increase/decrease in manhole shaft for every additional
depth in following size of circular manhole.

AOR 900 mm internal dia upto 1.65 m deep 0.00 7600.00 0.00
AOR 1200 mm internal dia upto 3.3 m deep 2.17 12100.00 26232.80
AOR 1500 mm internal dia upto 4.95 m deep 0.00 31200.00 0.00
11 Dismantling of roads for laying sewers including sorting
out and stacking of serviciable materials, and diposal of
unserviciable materials upto a distance of 60m and its
reinstatement after filling and proper compaction of
trenches.

(a) AOR Bitumen Road @ 0% 109.62 173.76 19047.57


(b) AOR Earthen Road @ 0% 55.31 0.00 0.00
S. SOR Ref.
No. Description of works Qty. Unit Rate Amount
1 2 3 4 5 6 7
12 Provision for road reinstatement charges.
(a) AOR Bitumen Road @ 0% 109.62 2298.18 251926.49
(b) AOR Earthen Road @ 0% 55.31 0.00 0.00
13 AOR Disposal of surplus earth 564.00 280.46 158179.44
14 Providing and erecting temporary barricading at site as
per drawing/ direction of Engineer-in-Charge which
includes hiring of Eucalyptus Ballies and arrangement for
traffic diversion such as traffic signals during construction
at site as directed by the Engineer-in-Charge. The
barricading provided shall be retained in position at site
continuously i/c shifting of barricading from one location
to another location as many times as required during the
execution of the entire work till its completion. Rate
include its maintenance for damages, painting, all
incidentals, labour materials, equipments and works
required to execute the job. The barricading shall not be
removed without prior approval of Engineer-in-Charge.
(Note :- One time payment shall be made for providing
barricading from start of work till completion of work i/c
shifting. The barricading provided shall remain to be the
property of the contractor on completion of the work).
The rate is for unit length of pipe laying.

AOR 100.00 132.00 13200.00


TOTAL SEWER SYSTEM 8886746.41
TOTAL 8886746.41
SAY (in Lacs) 88.87
BARIYARPUR NAGAR PANCHAYAT SEWER SYSTEM AND APPURTENANT WORKS,
DISTRICT-DEORIA

DETAILED MEASUREMENT OF GRAVITY SEWER

S. No. Description of works No L B H Qty

1 2 3 4 5 6 7
SEWER NETWORK
1 Excavation for following depth below ground level for
laying of sewers, manholes, gulley pits, sumps etc. in
ordinary soil including cutting of joints pits, triming,
dressing, leveling, refilling of trenches in 15 cm layer. (8%
reduction due to excavation already taken in manhole
and SCC)

(A) Ordinary soil


A. 0.00 - 1.50 m. depth 2004.00 - - 2004.00 M3
B. 1.50 - 3.00 m. depth 1630.50 - - 1630.50 M3
2 I. Provide and fix open timbering (covering 1/3rd surface
area by planks) in trenches for the depth from 0.00 to
3.00 m. below ground level consisting of 4.00 cm. thick
approved country wood planks for polling boards (125
cm x 75 cm) Indian sal wood waler.

(a) 0.0 - 3.00 m 0.00 0.00 M2


3 I. Same as above but for close timbering below ground
level with 50 mm. Thick country wood planks 150 mm. X
75 mm. Indian sal wood walers and 125 mm. Thick sal
ballies.

0.00 - 3.00 m. depth 1494.00 1494.00 M2


4 Same as items N. 4-B but left in Trenchess (used
timbering) @ 1 %
0.00 - 3.00 m. depth 14.94 - - 14.94 M2
3.00 - 6.00 m. depth #REF! - - #REF! M2
6.00 - 7.50 m. depth #REF! - - #REF! M2
5 Supply of following sizes of DWC SN-8/R.C.C. non
pressure pipes with rubber gasket including all taxes.

(A) DWC SN-8 Pipe


150 mm dia 0.00 - - 0.00 M
200 mm dia 0.00 - - 0.00 M
250 mm dia 0.00 - - 0.00 M
(B) For RCC Sewer Pipes
For NP3 Pipes
300 mm dia 0.00 - - 0.00 M
350 mm dia 498.00 - - 498.00 M
6 Carting of following sizes of pipes including
transportation, loading and unloading and DWC/R.C.C.
non pressure pipes class NP3 and NP4 socket/spigot
rubber ring jointing and specials from store to the site of
work lowering the same into trenches in the following
depth below ground level, true to alignment, caulking
the joints with necessary open yarn soaked.

(A) DWC Sewer pipes


(i) 150 mm. Dia
0.00 - 1.50 m depth 0.00 - - 0.00 M
S. No. Description of works No L B H Qty

1 2 3 4 5 6 7
1.50 - 3.00 m. depth 0.00 - - 0.00 M
3.00 - 4.50 m. depth 0.00 - - 0.00 M
4.50 - 6.00 m. depth 0.00 - - 0.00 M
(ii) 200 mm. Dia
0.00 - 1.50 m depth 0.00 - - 0.00 M
1.50 - 3.00 m. depth 0.00 - - 0.00 M
3.00 - 4.50 m. depth 0.00 - - 0.00 M
4.50 - 6.00 m. depth 0.00 - - 0.00 M
(iii) 250 mm. Dia
0.00 - 1.50 m depth 0.00 - - 0.00 M
1.50 - 3.00 m. depth 0.00 0.00 M
3.00 - 4.50 m. depth 0.00 - - 0.00 M
4.50 - 6.00 m. depth 0.00 - - 0.00 M
6.00 - 7.50 m. depth 0.00 - - 0.00 M
(B) For RCC NP3 Pipes
(i) 300 mm. Dia
0.00 - 1.50 m depth 0.00 - - 0.00 M
1.50 - 3.00 m. depth 0.00 - - 0.00 M
3.00 - 4.50 m. depth 0.00 - - 0.00 M
4.50 - 6.00 m. depth 0.00 - - 0.00 M
(ii) 350 mm. Dia
0.00 - 1.50 m depth 0.00 - - 0.00 M
1.50 - 3.00 m. depth 0.00 - - 0.00 M
3.00 - 4.50 m. depth 20.00 - - 20.00 M
4.50 - 6.00 m. depth 308.00 - - 308.00 M
6.00 - 7.50 m. depth 170.00 - - 170.00 M
7 Cement concrete work in bedding below G.L. at specified
depth with cement, coarse sand and 20 mm guage
approved stone ballast (1:2:4) including supply of all
materials, labour, T&P etc. required for proper - -
completion of work.

a. 1.50 - 3.00 m. depth 0.00 - - 0.00 M3


b. 3.00 - 4.50 m. depth 0.00 - - 0.00 M3
c. 4.50 - 6.00 m. depth 0.00 - - 0.00 M3
d. 6.00 - 7.50 m. depth 11.17 - - 11.17 M3
8 Sand filling including supply of all materials, labout T&P
etc. required for proper completion of work for road
crossing and as and where required as per site
conditiond during execution of work.
11.17 - - 11.17 M3
S. No. Description of works No L B H Qty

1 2 3 4 5 6 7
9 Supply of all materials , labour T & P etc. and construct of
Brick circular manhole of following depth as pe type
design (unit estimate enclosed)

a. 900 mm internal dia upto 1.65 m deep 0 0.00 No.


b. 1200 mm internal dia upto 3.3 m deep 0 0.00 No.
c. 1500 mm internal dia upto 4.95 m deep 8 8.00 No.
10 Increase / decrease in manhole shaft for every additional
depth in following size of circular manhole.

a. 900 mm internal dia upto 1.65 m deep 0.00 0.00 M


b. 1200 mm internal dia upto 3.3 m deep 2.17 2.17 M
c. 1500 mm internal dia upto 4.95 m deep 0.00 0.00 M
11 Dismantling of roads for laying sewers including sorting
out and stacking of serviciable materials, and diposal of
unserviciable materials upto a distance of 60m and its
reinstatement after filling and proper compaction of
trenches.
473.10
(a) Bitumen Road 94.62 15.00 - - 109.62 M2
(b) Earthen road 47.31 8.00 - - 55.31 M2

12 Provision for road reinstatement charges.

(a) Bitumen Road 94.62 - - 94.62 M2


(b) Earthen road 47.31 - - 47.31 M2
13 Disposal of surplus earth 564.00 - - 564.00 M3
14 Providing and erecting temporary barricading at site as
per drawing/ direction of Engineer-in-Charge which
includes hiring of Eucalyptus Ballies and arrangement for
traffic diversion such as traffic signals during construction
at site as directed by the Engineer-in-Charge. The
barricading provided shall be retained in position at site
continuously i/c shifting of barricading from one location
to another location as many times as required during the
execution of the entire work till its completion. Rate
include its maintenance for damages, painting, all
incidentals, labour materials, equipments and works
required to execute the job. The barricading shall not be
removed without prior approval of Engineer-in-Charge.
(Note :- One time payment shall be made for providing
barricading from start of work till completion of work i/c
shifting. The barricading provided shall remain to be the
property of the contractor on completion of the work).
The rate is for unit length of pipe laying.

100.00 100.00 RM

Assistant Engineer
UNIT ESTIMATE OF 900mm DIA, CIRCULAR MANHOLE 1.65 M DEEP

S. No. Description Length Width Depth Qty. Unit Rate Amount


(Rs.) (Rs.)
1 2 3 4 5 6 7 8 9
1 Excavation in foundation in ordinary soil
(loam, clay or sand) for the following depths
below ground level for laying sewer,
manholes, gully pits, chamber, sump etc.
including cutting of joint, pits trimming,
dressing, levelling, refilling of trenches in
20cm layers, watering and ramming the same
including removal of surplus earth and other
dismantled materials upto a distance of 50m
from the centre of the trenches.

0.00 - 1.50 M BGL 0.785x((0.9+(0.23x2)+(0.15x2)^2)x1.5 3.245 cum 227.01 736.58


1.50 - 3.00 M BGL 0.785x((0.9+(0.23x2)+(0.15x2)^2)x0.3 0.649 cum 285.96 185.57
2 Cement concrete with 20mm gauge approved
stone ballast, coarse sand and cement in
proportion of 4:2:1 including supply of all
materials, labour T&P etc. required for proper
completion of the work.

0.00 - 1.50 M BGL 0.785 0.2772 0.15 0.03264 cum 8445.73 275.67
1.50 - 3.00 M BGL 0.785 0.8100 0.22 0.13989 cum 8699.1 1216.89
0.785 2.7560 0.15 0.32452 cum 8699.1 2823.02
3 1st class brick work in 1:4 (1 cement : 4 local
sand)
0.00 - 1.50 M BGL 3.0144 0.23 0.70 0.48532 cum 6605.17 3205.61
3.5482 0.23 0.65 0.53046 cum 6605.17 3503.75
1.50 - 3.00 M BGL 3.5482 0.23 0.15 0.12241 cum 6803.33 832.81
External
4 12mm thick plaster with cement & local sand
1:4 over BW not to less than 10mm including
supply of all materials, labour tools and plants
etc. required for proper completion of work.

0.00 - 1.50 M BGL 3.7366 0.70 2.61562 Sqm. 174.75 457.08


4.2704 0.65 2.77576 Sqm. 174.75 485.06
1.50 - 3.00 M BGL 4.2704 0.15 0.64056 Sqm. 179.99 115.30
Internal
5 12mm thick plaster with cement & coarse
sand 1:4 over BW not to less than 10mm
including supply of all materials, labour tools
and plants etc. required for proper completion
of work.

0.00 - 1.50 M BGL 2.2922 0.70 1.60454 Sqm. 199.78 320.56


2.826 0.45 1.2717 Sqm. 199.78 254.06
6 Provide and fix PVC foot steps at a distance of
300mm c/c in the walls as per direction of
Engineer-in-charge including the cost of
cutting and making good the walls.
4 4 No. 200.00 800.00
7 Provide all materials, T&P and fix RCC
Manhole cover 600mm dia, heavy pattern
type with locking arrangement.
1 1 No. 2541.00 2541.00
8 Site clearance and unforeseen items. Job Job L.S. 47.03
S. No. Description Length Width Depth Qty. Unit Rate Amount
(Rs.) (Rs.)
1 2 3 4 5 6 7 8 9
TOTAL 17800.00

Assistant Engineer
UNIT ESTIMATE OF 1200mm DIA, CIRCULAR MANHOLE 3.30 M DEEP

S. No. Description Length Width Depth Qty. Unit Rate Amount


(Rs.) (Rs.)
1 2 3 4 5 6 7 8 9
1 Excavation in foundation in ordinary soil
(loam, clay or sand) for the following depths
below ground level for laying sewer,
manholes, gully pits, chamber, sump etc.
including cutting of joint, pits trimming,
dressing, levelling, refilling of trenches in
20cm layers, watering and ramming the same
including removal of surplus earth and other
dismantled materials upto a distance of 50m
from the centre of the trenches.

0.00 - 1.50 M BGL 3.14 1.199 1.5 5.65 cum 227.01 1281.99
1.50 - 3.00 M BGL 3.14 1.199 1.5 5.65 cum 285.96 1614.90
3.00 - 4.50 M BGL 3.14 1.199 0.53 2.00 cum 359.88 718.10
2 Dry Brick ballast 40mm gauge in foundation 3.14 1.199 0.08 0.30 cum 1350.00 406.60
3 Cement concrete with 20mm gauge approved
stone ballast, coarse sand and cement in
proportion of 4:2:1 including supply of all
materials, labour T&P etc. required for proper
completion of the work.

0.00 - 1.50 M BGL 0.79 0.2772 0.15 0.03 cum 8445.73 275.67
3.00 - 4.50 M BGL 0.79 1.4400 0.22 0.25 cum 8699.10 2163.36
0.79 4.7960 0.15 0.56 cum 8699.10 4912.64
4 1st class brick work in 1:4 (1 cement : 4 local
sand)
0.00 - 1.50 M BGL 3.49 0.23 1.20 0.96 cum 6605.17 6353.25
4.49 0.23 0.15 0.15 cum 6605.17 1023.17
1.50 - 3.00 M BGL 4.49 0.23 0.65 0.67 cum 6803.33 4566.77
4.85 0.345 0.85 1.42 cum 6803.33 9678.11
3.00 - 4.50 M BGL 4.85 0.345 0.30 0.50 cum 7067.53 3548.46
External
4 12mm thick plaster with cement & local sand
1:4 over BW not to less than 10mm including
supply of all materials, labour tools and plants
etc. required for proper completion of work.

0.00 - 1.50 M BGL 4.21 1.20 5.05 Sqm. 174.75 882.42


5.21 0.15 0.78 Sqm. 174.75 136.62
1.50 - 3.00 M BGL 5.21 0.65 3.39 Sqm. 179.99 609.78
5.57 0.115 0.64 Sqm. 179.99 115.38
1.50 - 3.00 M BGL 5.94 0.85 5.04 Sqm. 179.99 908.02
3.00 - 4.50 M BGL 5.94 0.3 1.78 Sqm. 186.98 332.92
Internal
5 12mm thick plaster with cement & coarse
sand 1:4 over BW not to less than 10mm
including supply of all materials, labour tools
and plants etc. required for proper completion
of work.

0.00 - 1.50 M BGL 2.763 1.20 3.32 Sqm. 199.78 662.39


3.768 0.15 0.57 Sqm. 199.78 112.92
1.50 - 3.00 M BGL 3.768 1.33 5.01 Sqm. 205.77 1031.22
S. No. Description Length Width Depth Qty. Unit Rate Amount
(Rs.) (Rs.)
1 2 3 4 5 6 7 8 9
6 Provide and fix PVC foot steps at a distance of
300mm c/c in the walls as per direction of
Engineer-in-charge including the cost of
cutting and making good the walls.
9 9 No. 200.00 1800.00
7 Provide all materials, T&P and fix RCC
Manhole cover 600mm dia, heavy pattern
type with locking arrangement.
1 1 No. 2541.00 2541.00
8 Site clearance and unforeseen items. Job Job L.S. 24.33
TOTAL 45700.00

Assistant Engineer
UNIT ESTIMATE OF 1500mm DIA, CIRCULAR MANHOLE 4.95 M DEEP

S. No. Description Length Width Depth Qty. Unit Rate Amount


(Rs.) (Rs.)
1 2 3 4 5 6 7 8 9
1 Excavation in foundation in ordinary soil (loam,
clay or sand) for the following depths below
ground level for laying sewer, manholes, gully
pits, chamber, sump etc. including cutting of
joint, pits trimming, dressing, levelling, refilling
of trenches in 20cm layers, watering and
ramming the same including removal of surplus
earth and other dismantled materials upto a
distance of 50m from the centre of the trenches.

0.00 - 1.50 M BGL 0.785 7.398 1.500 8.711 cum 227.01 1977.52
1.50 - 3.00 M BGL 0.785 7.398 1.500 8.711 cum 285.96 2491.04
3.00 - 4.50 M BGL 0.785 7.398 1.500 8.711 cum 359.88 3134.97
4.50 - 6.00 M BGL 0.785 7.398 0.680 3.949 cum 420.98 1662.47
2 Dry Brick ballast 40mm gauge in foundation
4.50 - 6.00 M BGL 0.785 7.398 0.080 0.465 cum 1512.00 702.47
3 Cement concrete with 20mm gauge approved
stone ballast, coarse sand and cement in
proportion of 4:2:1 including supply of all
materials, labour T&P etc. required for proper
completion of the work.

0.00 - 1.50 M BGL 0.785 0.277 0.150 0.033 cum 8445.73 275.67
4.50 - 6.00 M BGL 0.785 2.250 0.220 0.389 cum 10134.88 3938.16
0.785 7.398 0.150 0.871 cum 10134.88 8828.64
4 1st class brick work in 1:4 (1 cement : 4 local
sand)
0.00 - 1.50 M BGL 3.956 0.230 1.300 1.183 cum 6605.17 7812.89
5.432 0.230 0.050 0.062 cum 6605.17 412.61
1.50 - 3.00 M BGL 5.432 0.230 0.800 0.999 cum 6803.33 6799.84
5.793 0.345 0.700 1.399 cum 6803.33 9517.92
3.00 - 4.50 M BGL 6.154 0.460 1.500 4.246 cum 7067.53 30010.58
4.50 - 6.00 M BGL 6.154 0.460 0.450 1.274 cum 7397.79 9423.88
External
4 15mm thick plaster with cement & local sand 1:4
over BW not to less than 10mm including supply
of all materials, labour tools and plants etc.
required for proper completion of work.

0.00 - 1.50 M BGL 4.679 1.300 6.083 Sqm. 174.75 1062.95


6.154 0.050 0.308 Sqm. 174.75 53.77
1.50 - 3.00 M BGL 6.154 0.800 4.923 Sqm. 179.99 886.14
6.516 0.115 0.749 Sqm. 179.99 134.88
6.877 0.700 4.814 Sqm. 185.39 892.46
7.238 0.115 0.832 Sqm. 185.39 154.31
3.00 - 4.50 M BGL 7.599 1.500 11.399 Sqm. 186.98 2131.32
4.50 - 6.00 M BGL 7.599 0.450 3.420 Sqm. 195.72 669.27
Internal
5 12mm thick plaster with cement & coarse sand
1:4 over BW not to less than 10mm including
supply of all materials, labour tools and plants
etc. required for proper completion of work.

0.00 - 1.50 M BGL 3.234 1.300 4.204 Sqm. 199.78 839.92


4.710 0.050 0.236 Sqm. 199.78 47.05
1.50 - 3.00 M BGL 4.710 1.500 7.065 Sqm. 205.77 1453.79
3.00 - 4.50 M BGL 4.710 1.360 6.406 Sqm. 213.76 1369.29
S. No. Description Length Width Depth Qty. Unit Rate Amount
(Rs.) (Rs.)
1 2 3 4 5 6 7 8 9
6 Provide and fix PVC foot steps at a distance of
300mm c/c in the walls as per direction of
Engineer-in-charge including the cost of cutting
and making good the walls.
14.000 14.000 No. 200.00 2800.00
7 Provide all materials, T&P and fix RCC Manhole
cover 600mm dia, heavy pattern type with
locking arrangement.
1.000 1.000 No. 2541.00 2541.00
8 Close timbering including supply of all labour and
materials complete as per direction of Engineer
incharge in the following depths
0.0 - 3.0 m BGL 8.540 3.000 25.620 Sqm. 1215.59 31143.42
3.0 - 6.0 m BGL 8.540 2.180 18.617 Sqm. 1520.04 28298.89
9 Site clearance and unforeseen items. 1 Job L.S. 32.89
TOTAL 161500.00

Assistant Engineer
UNIT ESTIMATE OF 1500mm DIA, CIRCULAR MANHOLE 9.00 M DEEP

S. No. Description Qty. Unit Rate Amount


(Rs.) (Rs.)
1 2 6 7 8 9
1 Excavation in foundation in ordinary soil
(loam, clay or sand) for the following depths
below ground level for laying sewer,
manholes, gully pits, chamber, sump etc.
including cutting of joint, pits trimming,
dressing, levelling, refilling of trenches in
20cm layers, watering and ramming the same
including removal of surplus earth and other
dismantled materials upto a distance of 50m
from the centre of the trenches.

0.00 - 1.50 M BGL 38.530 cum 227.01 8746.70


1.50 - 3.00 M BGL 32.080 cum 285.96 9173.60
3.00 - 4.50 M BGL 26.230 cum 359.88 9439.65
4.50 - 6.00 M BGL 20.970 cum 420.98 8827.95
6.00 - 7.50 M BGL 16.290 cum 550.60 8969.27
7.50 - 9.00 M BGL 12.210 cum 723.57 8834.79
9.00 - 10.50 M BGL 1.340 cum 1027.47 1376.81
2 Dry Brick soiling in foundation
9.00 - 10.50 M BGL 0.870 cum 1917.00 1667.79
3 Cement concrete with 20mm gauge approved
stone ballast, coarse sand and cement in
proportion of 4:2:1 including supply of all
materials, labour T&P etc. required for
proper completion of the work.

0.00 - 1.50 M BGL 0.160 cum 8445.73 1351.32


7.50 - 9.00 M BGL 0.810 cum 10979.45 8893.35
4 1st class brick work in 1:4 (1 cement : 4 local
sand)

0.00 - 1.50 M BGL 2.740 cum 6605.17 18098.17


1.50 - 3.00 M BGL 4.250 cum 6803.33 28914.13
3.00 - 4.50 M BGL 5.680 cum 7067.53 40143.58
4.50 - 6.00 M BGL 5.680 cum 7397.79 42019.45
5 RCC 1:1.5:3
6.00 - 7.50 M BGL 2.810 cum 13345.46 37500.75
7.50 - 9.00 M BGL 2.810 cum 14457.59 40625.82
9.00 - 10.50 M BGL 2.020 cum 15792.13 31900.11
6 MS work in RCC including cutting, bending,
straightening and placing etc. complete
6.00 - 7.50 M BGL 1.970 Qtl 18160.90 35776.97
S. No. Description Qty. Unit Rate Amount
(Rs.) (Rs.)
1 2 6 7 8 9
7.50 - 9.00 M BGL 1.970 Qtl 19674.30 38758.38
9.00 - 10.50 M BGL 1.410 Qtl 21490.39 30301.45
7 12mm thick plaster with cement & coarse
sand 1:4 over BW not to less than 10mm
including supply of all materials, labour tools
and plants etc. required for proper
completion of work.

0.00 - 1.50 M BGL 12.710 Sqm. 199.78 2539.20


1.50 - 3.00 M BGL 7.070 Sqm. 205.77 1454.82
3.00 - 4.50 M BGL 7.070 Sqm. 213.76 1511.32
4.50 - 6.00 M BGL 7.070 Sqm. 223.75 1581.94
8 Provide and fix PVC foot steps at a distance of
300mm c/c in the walls as per direction of
Engineer-in-charge including the cost of
cutting and making good the walls.

29.000 Nos 200.00 5800.00


9 Provide all materials, T&P and fix RCC
Manhole cover 600mm dia, heavy pattern
type with locking arrangement.
1.000 Nos 2541.00 2541.00
10 Close timbering including supply of all labour
and materials complete as per direction of
Engineer incharge in the following depths

0.0 - 3.0 m BGL 32.58 Sqm. 1215.59 39603.92


3.0 - 6.0 m BGL 26.58 Sqm. 1520.04 40402.66
6.0 - 9.0 m BGL 22.08 Sqm. 1766.72 39009.18
11 Site clearance and unforeseen items. Job L.S. 235.93
TOTAL 546000.00

Assistant Engineer
UNIT ESTIMATE OF 900mm DIA, CIRCULAR MANHOLE (1.65 M depth) TO REGULATE
THE DEPTH OF MANHOLE

S. No. Description Qty. Unit Rate Amount


(Rs.) (Rs.)
1 2 6 7 8 9
1 Excavation in foundation in ordinary soil
(loam, clay or sand) for the following depths
below ground level for laying sewer,
manholes, gully pits, chamber, sump etc.
including cutting of joint, pits trimming,
dressing, levelling, refilling of trenches in
20cm layers, watering and ramming the same
including removal of surplus earth and other
dismantled materials upto a distance of 50m
from the centre of the trenches.

0.00 - 1.50 M BGL 3.842 cum 227.01 872.17


2 1st class brick work in 1:4 (1 cement : 4 local
sand)
0.00 - 1.50 M BGL 0.816 cum 6605.17 5389.82
3 12mm thick plaster with cement & coarse
sand 1:4 over BW not to less than 10mm
including supply of all materials, labour tools
and plants etc. required for proper
completion of work.

0.00 - 1.50 M BGL 2.826 Sqm. 199.78 564.58


4 Provide and fix PVC foot steps at a distance of
300mm c/c in the walls as per direction of
Engineer-in-charge including the cost of
cutting and making good the walls.

3.000 Nos 200.00 600.00


5 Site clearance Job L.S. 9.18
TOTAL 7435.75

Assistant Engineer
UNIT ESTIMATE OF 1200mm DIA, CIRCULAR MANHOLE (3.30 M depth) TO
REGULATE THE DEPTH OF MANHOLE

S. No. Description Qty. Unit Rate Amount


(Rs.) (Rs.)
1 2 6 7 8 9
1 Excavation in foundation in ordinary soil
(loam, clay or sand) for the following depths
below ground level for laying sewer,
manholes, gully pits, chamber, sump etc.
including cutting of joint, pits trimming,
dressing, levelling, refilling of trenches in
20cm layers, watering and ramming the same
including removal of surplus earth and other
dismantled materials upto a distance of 50m
from the centre of the trenches.

1.50 - 3.00 M BGL 5.647 cum 285.96 1614.82


2 1st class brick work in 1:4 (1 cement : 4 local
sand)
1.50 - 3.00 M BGL 1.272 cum 6803.33 8653.83
3 12mm thick plaster with cement & coarse
sand 1:4 over BW not to less than 10mm
including supply of all materials, labour tools
and plants etc. required for proper
completion of work.

1.50 - 3.00 M BGL 5.049 Sqm. 205.77 1038.95


4 Provide and fix PVC foot steps at a distance of
300mm c/c in the walls as per direction of
Engineer-in-charge including the cost of
cutting and making good the walls.

3.0 Nos 200.00 600.00


5 Site clearance Job L.S. 7.58
TOTAL 11915.18

Assistant Engineer
UNIT ESTIMATE OF 1500mm DIA, CIRCULAR MANHOLE (4.95 M depth) TO
REGULATE THE DEPTH OF MANHOLE

S. No. Description Qty. Unit Rate Amount


(Rs.) (Rs.)
1 2 6 7 8 9
1 Excavation in foundation in ordinary soil
(loam, clay or sand) for the following depths
below ground level for laying sewer,
manholes, gully pits, chamber, sump etc.
including cutting of joint, pits trimming,
dressing, levelling, refilling of trenches in
20cm layers, watering and ramming the same
including removal of surplus earth and other
dismantled materials upto a distance of 50m
from the centre of the trenches.

4.50 - 6.00 M BGL 9.120 cum 420.98 3839.34


2 1st class brick work in 1:4 (1 cement : 4 local
sand)
4.50 - 6.00 M BGL 2.831 cum 7397.79 20943.14
3 12mm thick plaster with cement & coarse
sand 1:4 over BW not to less than 10mm
including supply of all materials, labour tools
and plants etc. required for proper
completion of work.

4.50 - 6.00 M BGL 4.710 Sqm. 223.75 1053.88


4 Provide and fix PVC foot steps at a distance of
300mm c/c in the walls as per direction of
Engineer-in-charge including the cost of
cutting and making good the walls.

3.0 Nos 200.00 600.00


5 Close timbering including supply of all labour
and materials complete as per direction of
Engineer incharge in the following depths

3.0 - 6.0 m BGL 4.7 Cum 1520.04 7159.39


6 Site clearance Job L.S. 88.90
TOTAL 33684.65
Assistant Engineer

UNIT ESTIMATE OF 1500mm DIA, CIRCULAR MANHOLE (9.0 M depth) TO REGULATE


THE DEPTH OF MANHOLE

S. No. Description Qty. Unit Rate Amount


(Rs.) (Rs.)
1 2 6 7 8 9
1 Excavation in foundation in ordinary soil
(loam, clay or sand) for the following depths
below ground level for laying sewer,
manholes, gully pits, chamber, sump etc.
including cutting of joint, pits trimming,
dressing, levelling, refilling of trenches in
20cm layers, watering and ramming the same
including removal of surplus earth and other
dismantled materials upto a distance of 50m
from the centre of the trenches.

9.00 - 10.50 M BGL 10.110 cum 1027.47 10387.72


2 RCC 1:1.5:3
9.00 - 10.50 M BGL 1.700 cum 15792.13 26846.63

3 MS work in RCC including cutting, bending,


straightening and placing etc. complete
9.00 - 10.50 M BGL 1.360 Qtl 21490.39 29226.94
4 Provide and fix PVC foot steps at a distance of
300mm c/c in the walls as per direction of
Engineer-in-charge including the cost of
cutting and making good the walls.

3.0 Nos 200.00 600.00


5 Close timbering including supply of all labour
and materials complete as per direction of
Engineer incharge in the following depths

6.0 - 9.0 m BGL 6.4 Cum 1766.72 11236.34


6 Site clearance Job L.S. 2.38
TOTAL 78300.00

Assistant Engineer
UNIT ESTIMATE FOR HIRING OF BARRICADING FOR 7 DAYS (10 M)

Sl. No. Ref. Description Unit Qty. Rate Amount


1 2 3 4 5 6 7
A MATERIALS
1 Hiring of Eucalyptus Ballies 100mm Dia
Avg. length 1.5 M @ 7/- per day No. 7 12.00 84.00
2 Hiring of Eucalyptus Ballies 80mm Dia
Avg. length 3.0 M @ 6/- per day No. 7 8.00 56.00

3 Nariyal Rope Kg. 5 100.00 500.00


B LABOUR
Beldar No. 1.5 360 540.00
Black Smith No. 0.2 480 96.00
Sundries Job L.S. 200.00
Cost for 10 M 1476.00
Contractor profit @ 10% 147.60
Total Cost for 10 M 1623.60
Cost for 1 M 162.36
SAY 163.00

ASSISTANT ENGINEER
UNIT ESTIMATE FOR DISPOSAL OF SURPLUS EARTH

Sl. No. Ref. Description


1 2 3
At 4.0 Kms Lead (L)
1 Average Speed in Km/Hr (s) 20 Kms/Hr.
2 No. of Trips 8.0/ (2 L/s + 1.5) 5
3 Kms Done 2 NL + 6.50 46.50 Kms.
Cost of Diesel (Assuming 12 Km/Ltr.) (46.5/12)x95 368.13
Cost of M.Oil (Assuming 1 Ltr./125 Km) (46.5/500)x450 41.85
Hiring Charges of tractor trolly with driver per day 2100.00 2100.00
Loading and unloading (Beldar 02 Nos./day) 2 x 360 720.00
Cost of work 3276.48
Add CP @ 10% 327.65
Total Cost of work 3604.12
Cost per trip (for 3.0 m3) 3604.12/5 720.82
Cost per m3 720.82/3 240.27

ASSISTANT ENGINEER