Professional Documents
Culture Documents
3.1. Gravity Sewer For p-00
3.1. Gravity Sewer For p-00
DISTRICT-RAEBARELI
ABSTRACT OF COST INTERCEPTOR SEWER
S.
No. Description of works Qty. Unit Rate Amount
1 3 4 5 6 7
1
Excavation for following depth below ground level
for laying of sewers, manholes, gulley pits, sumps
etc. in ordinary soil including cutting of joints pits,
triming, dressing, leveling, refilling of trenches in 15
cm layer. (8% reduction due to excavation already
taken in manhole)
(A) Ordinary soil
A. 0.00 - 1.50 m. depth 7102.92 Cum 227.01 1612432.78
B. 1.50 - 3.00 m. depth 4775.19 Cum 285.96 1365512.30
C. 3.00 - 4.50 m. depth 2156.77 Cum 359.88 776176.66
D. 4.50 - 6.00 m. depth 741.44 Cum 420.98 312130.23
E. 6.00 - 7.50 m. depth 38.82 Cum 550.60 21376.49
2 Provide and fix open timbering (covering 1/3rd
surface area by planks) in trenches for the depth
from 0.00 to 3.00 m. below ground level consisting
of 4.00 cm. thick approved country wood planks for
polling boards (125 cm x 75 cm) Indian sal wood
waler.
(a) 0.0 - 3.00 m 862.92 Sqm 367.53 317148.99
3 Same as above but for close timbering below ground
level with 50 mm. Thick country wood planks 150
mm. X 75 mm. Indian sal wood walers and 125 mm.
Thick sal ballies.
1579.986
For RCC NP3 Pipes
350 mm. Dia
0.00 - 1.50 m depth 732.00 M 1755.54 1285055.28
1.50 - 3.00 m. depth 1100.00 M 1868.77 2055649.56
3.00 - 4.50 m. depth 540.00 M 1984.64 1071704.50
4.50 - 6.00 m. depth 7.00 M 2119.81 14838.70
6.00 - 7.50 m. depth 0.00 M 2309.41 0.00
For RCC NP4 Pipes
300 mm. Dia
0.00 - 1.50 m depth 0.00 M 1737.98 0.00
1.50 - 3.00 m. depth 0.00 M 1850.08 0.00
3.00 - 4.50 m. depth 28.00 M 1964.79 55014.16
4.50 - 6.00 m. depth 72.00 M 2098.62 151100.38
6.00 - 7.50 m. depth 0.00 M 2286.32 0.00
350 mm. Dia
0.00 - 1.50 m depth 0.00 M 1911.78 0.00
1.50 - 3.00 m. depth 16.00 M 2035.09 32561.49
3.00 - 4.50 m. depth 88.00 M 2161.27 190191.83
4.50 - 6.00 m. depth 582.00 M 2308.48 1343534.22
6.00 - 7.50 m. depth 79.00 M 2514.95 198681.10
10 Sand filling including supply of all materials, labout
T&P etc. required for proper completion of work for
road crossing and as and where required as per site
conditiond during execution of work.
1 2 3 4 5 6 7
SEWER NETWORK
1 Excavation for following depth below ground level
for laying of sewers, manholes, gulley pits, sumps
etc. in ordinary soil including cutting of joints pits,
triming, dressing, leveling, refilling of trenches in 15
cm layer. (8% reduction due to excavation already
taken in manhole)
1 2 3 4 5 6 7
6 10 mm thick lean concrete work in beding below GL
at special depth with cement, local sand and 40mm
gauge brick ballast in 1:5:10 including supply of all - -
material labour T&P etc. complete. Or PCC 1:4:8
1 2 3 4 5 6 7
1.50 - 3.00 m. depth 16.00 - - 16.00 M
3.00 - 4.50 m. depth 88.00 - - 88.00 M
4.50 - 6.00 m. depth 582.00 - - 582.00 M
6.00 - 7.50 m. depth 79.00 - - 79.00 M
10 Sand filling including supply of all materials, labout
T&P etc. required for proper completion of work for
road crossing and as and where required as per site
conditiond during execution of work.
145.49 - - 145.49 M3
11 Supply of all materials , labour T & P etc. and
construct of circular manhole of following depth as
pe type design (unit estimate enclosed)
Assistant Engineer
DETAILS OF INTERCEPTOR SEWER AS PER DESIGN
Node Quantity of Earth work in Cum. Open Closed Timbering Well graded crushed rock or grvel Type of
Name of main
Length
Dia of pipe
(mm)
Road
Timbering max. size 25mm (in Cum)
From
To 0.0 to 1.5 1.5 to 3.0 3.0 to 4.5 4.5 to 6.0 6.0 to 7.9 <1.5 1.5-3.0 <1.5 1.5-3.0 3.0-4.5 4.5-6.0 6.0-7.9 0.0-1.5 1.5-3.0 3.0-4.5 4.5-6.0 6.0-7.9
TM 14 15 144 350 598.50 490.50 382.50 239.29 48.98 216 216 216 180.79 48.98 18.11 14.23 BOE
TM 15 16 200 350 750.00 600.00 450.00 90.30 300 300 300 90.3 51.73 BOE
TM 16 STP 45 350 165.00 131.25 97.30 10.80 67.5 67.5 67.3 10.8 1.29 10.35 BOE
BS0020 58 14 109 350 490.50 408.75 327.00 245.25 127.07 163.5 163.5 163.5 163.5 127.0 BT
TOTAL 498 2004 1630.5 1256.8 585.64 176.05 0 0 747 747 746.8 445.39 176.02 0 0 1.29 80.19 14.23
10 cm thick lean 1:2:4 RCC for Craddle in Cum 350mm dia pipe laying jointing Manhole
Concrete in Cum
1.5-3.0 3.0-4.5 6.0-7.9 0.0-1.5 1.5-3.0 3.0-4.5 4.5-6.0 6.0-7.9 0.0-1.5 1.5-3.0 3.0-4.5 4.5-6.0 6.0-7.9 0.0-1.5 1.5-3.0 3.0-4.5 4.5-6.0 6.0-7.9
1.9 1.66 83 61 1 1
200 3
20 25 1
10.9 9.51 109 2
0 0 12.8 0 0 0 0 11.17 0 0 20 308 170 0 0 0 5 3
BARIYARPUR NAGAR PANCHAYAT SEWER SYSTEM AND APPURTENANT WORKS,
DISTRICT-DEORIA
AOR 900 mm internal dia upto 1.65 m deep 0.00 18400.00 0.00
AOR 1200 mm internal dia upto 3.3 m deep 8.00 46400.00 371200.00
AOR 1500 mm internal dia upto 4.95 m deep 0.00 138500.00 0.00
10 Increase/decrease in manhole shaft for every additional
depth in following size of circular manhole.
AOR 900 mm internal dia upto 1.65 m deep 0.00 7600.00 0.00
AOR 1200 mm internal dia upto 3.3 m deep 2.17 12100.00 26232.80
AOR 1500 mm internal dia upto 4.95 m deep 0.00 31200.00 0.00
11 Dismantling of roads for laying sewers including sorting
out and stacking of serviciable materials, and diposal of
unserviciable materials upto a distance of 60m and its
reinstatement after filling and proper compaction of
trenches.
1 2 3 4 5 6 7
SEWER NETWORK
1 Excavation for following depth below ground level for
laying of sewers, manholes, gulley pits, sumps etc. in
ordinary soil including cutting of joints pits, triming,
dressing, leveling, refilling of trenches in 15 cm layer. (8%
reduction due to excavation already taken in manhole
and SCC)
1 2 3 4 5 6 7
1.50 - 3.00 m. depth 0.00 - - 0.00 M
3.00 - 4.50 m. depth 0.00 - - 0.00 M
4.50 - 6.00 m. depth 0.00 - - 0.00 M
(ii) 200 mm. Dia
0.00 - 1.50 m depth 0.00 - - 0.00 M
1.50 - 3.00 m. depth 0.00 - - 0.00 M
3.00 - 4.50 m. depth 0.00 - - 0.00 M
4.50 - 6.00 m. depth 0.00 - - 0.00 M
(iii) 250 mm. Dia
0.00 - 1.50 m depth 0.00 - - 0.00 M
1.50 - 3.00 m. depth 0.00 0.00 M
3.00 - 4.50 m. depth 0.00 - - 0.00 M
4.50 - 6.00 m. depth 0.00 - - 0.00 M
6.00 - 7.50 m. depth 0.00 - - 0.00 M
(B) For RCC NP3 Pipes
(i) 300 mm. Dia
0.00 - 1.50 m depth 0.00 - - 0.00 M
1.50 - 3.00 m. depth 0.00 - - 0.00 M
3.00 - 4.50 m. depth 0.00 - - 0.00 M
4.50 - 6.00 m. depth 0.00 - - 0.00 M
(ii) 350 mm. Dia
0.00 - 1.50 m depth 0.00 - - 0.00 M
1.50 - 3.00 m. depth 0.00 - - 0.00 M
3.00 - 4.50 m. depth 20.00 - - 20.00 M
4.50 - 6.00 m. depth 308.00 - - 308.00 M
6.00 - 7.50 m. depth 170.00 - - 170.00 M
7 Cement concrete work in bedding below G.L. at specified
depth with cement, coarse sand and 20 mm guage
approved stone ballast (1:2:4) including supply of all
materials, labour, T&P etc. required for proper - -
completion of work.
1 2 3 4 5 6 7
9 Supply of all materials , labour T & P etc. and construct of
Brick circular manhole of following depth as pe type
design (unit estimate enclosed)
100.00 100.00 RM
Assistant Engineer
UNIT ESTIMATE OF 900mm DIA, CIRCULAR MANHOLE 1.65 M DEEP
0.00 - 1.50 M BGL 0.785 0.2772 0.15 0.03264 cum 8445.73 275.67
1.50 - 3.00 M BGL 0.785 0.8100 0.22 0.13989 cum 8699.1 1216.89
0.785 2.7560 0.15 0.32452 cum 8699.1 2823.02
3 1st class brick work in 1:4 (1 cement : 4 local
sand)
0.00 - 1.50 M BGL 3.0144 0.23 0.70 0.48532 cum 6605.17 3205.61
3.5482 0.23 0.65 0.53046 cum 6605.17 3503.75
1.50 - 3.00 M BGL 3.5482 0.23 0.15 0.12241 cum 6803.33 832.81
External
4 12mm thick plaster with cement & local sand
1:4 over BW not to less than 10mm including
supply of all materials, labour tools and plants
etc. required for proper completion of work.
Assistant Engineer
UNIT ESTIMATE OF 1200mm DIA, CIRCULAR MANHOLE 3.30 M DEEP
0.00 - 1.50 M BGL 3.14 1.199 1.5 5.65 cum 227.01 1281.99
1.50 - 3.00 M BGL 3.14 1.199 1.5 5.65 cum 285.96 1614.90
3.00 - 4.50 M BGL 3.14 1.199 0.53 2.00 cum 359.88 718.10
2 Dry Brick ballast 40mm gauge in foundation 3.14 1.199 0.08 0.30 cum 1350.00 406.60
3 Cement concrete with 20mm gauge approved
stone ballast, coarse sand and cement in
proportion of 4:2:1 including supply of all
materials, labour T&P etc. required for proper
completion of the work.
0.00 - 1.50 M BGL 0.79 0.2772 0.15 0.03 cum 8445.73 275.67
3.00 - 4.50 M BGL 0.79 1.4400 0.22 0.25 cum 8699.10 2163.36
0.79 4.7960 0.15 0.56 cum 8699.10 4912.64
4 1st class brick work in 1:4 (1 cement : 4 local
sand)
0.00 - 1.50 M BGL 3.49 0.23 1.20 0.96 cum 6605.17 6353.25
4.49 0.23 0.15 0.15 cum 6605.17 1023.17
1.50 - 3.00 M BGL 4.49 0.23 0.65 0.67 cum 6803.33 4566.77
4.85 0.345 0.85 1.42 cum 6803.33 9678.11
3.00 - 4.50 M BGL 4.85 0.345 0.30 0.50 cum 7067.53 3548.46
External
4 12mm thick plaster with cement & local sand
1:4 over BW not to less than 10mm including
supply of all materials, labour tools and plants
etc. required for proper completion of work.
Assistant Engineer
UNIT ESTIMATE OF 1500mm DIA, CIRCULAR MANHOLE 4.95 M DEEP
0.00 - 1.50 M BGL 0.785 7.398 1.500 8.711 cum 227.01 1977.52
1.50 - 3.00 M BGL 0.785 7.398 1.500 8.711 cum 285.96 2491.04
3.00 - 4.50 M BGL 0.785 7.398 1.500 8.711 cum 359.88 3134.97
4.50 - 6.00 M BGL 0.785 7.398 0.680 3.949 cum 420.98 1662.47
2 Dry Brick ballast 40mm gauge in foundation
4.50 - 6.00 M BGL 0.785 7.398 0.080 0.465 cum 1512.00 702.47
3 Cement concrete with 20mm gauge approved
stone ballast, coarse sand and cement in
proportion of 4:2:1 including supply of all
materials, labour T&P etc. required for proper
completion of the work.
0.00 - 1.50 M BGL 0.785 0.277 0.150 0.033 cum 8445.73 275.67
4.50 - 6.00 M BGL 0.785 2.250 0.220 0.389 cum 10134.88 3938.16
0.785 7.398 0.150 0.871 cum 10134.88 8828.64
4 1st class brick work in 1:4 (1 cement : 4 local
sand)
0.00 - 1.50 M BGL 3.956 0.230 1.300 1.183 cum 6605.17 7812.89
5.432 0.230 0.050 0.062 cum 6605.17 412.61
1.50 - 3.00 M BGL 5.432 0.230 0.800 0.999 cum 6803.33 6799.84
5.793 0.345 0.700 1.399 cum 6803.33 9517.92
3.00 - 4.50 M BGL 6.154 0.460 1.500 4.246 cum 7067.53 30010.58
4.50 - 6.00 M BGL 6.154 0.460 0.450 1.274 cum 7397.79 9423.88
External
4 15mm thick plaster with cement & local sand 1:4
over BW not to less than 10mm including supply
of all materials, labour tools and plants etc.
required for proper completion of work.
Assistant Engineer
UNIT ESTIMATE OF 1500mm DIA, CIRCULAR MANHOLE 9.00 M DEEP
Assistant Engineer
UNIT ESTIMATE OF 900mm DIA, CIRCULAR MANHOLE (1.65 M depth) TO REGULATE
THE DEPTH OF MANHOLE
Assistant Engineer
UNIT ESTIMATE OF 1200mm DIA, CIRCULAR MANHOLE (3.30 M depth) TO
REGULATE THE DEPTH OF MANHOLE
Assistant Engineer
UNIT ESTIMATE OF 1500mm DIA, CIRCULAR MANHOLE (4.95 M depth) TO
REGULATE THE DEPTH OF MANHOLE
Assistant Engineer
UNIT ESTIMATE FOR HIRING OF BARRICADING FOR 7 DAYS (10 M)
ASSISTANT ENGINEER
UNIT ESTIMATE FOR DISPOSAL OF SURPLUS EARTH
ASSISTANT ENGINEER