Professional Documents
Culture Documents
My Reporting Dashboard
My Reporting Dashboard
My Reporting Dashboard
68.10%
RISKS PRIORITY
1
2
3
Actual
PTC
Engineering Percentage Completion Procurement Percentage Completion Pre-Construction & Fabrication Percentage Marine Spread Percentage Completion Construction Percentage Completion
Completion
100.00% 100.00% 100.00% 100.00% 94.12%
1 2
200 98.13%
98.00%
96.00%
95.43%
150
94.00% 94.14%
94.00%
Percentage
Count
92.00%
100
90.24%
77 90.00%
88.00%
50 46
42
27 27
86.00%
16 15 15 13
6 6 8
0 1 0 0 0 0 0 0 0 0 3 0 0 0
0 84.00%
ENGINEERING Process Mechanical Piping Electrical Instrumentation THSE Materials Structural Process Mechanical Piping Electrical Instrumentation THSE Materials Structural
Discipline
Discipline
Completed In-Progress Not-Started Planned Actual
Project Name: Reporting Date: 28-Mar-23
Project Engineer: Overall Progree Percentage
WP Planed Start Planned Finish Actual Start Actual Finish
1 Overall 05-Nov-21 14-Sep-23 05-Nov-21 21-Sep-23 52.70%
2 Engineering 29-Mar-22 12-May-22 01-Feb-22 10-Aug-22
3 Procurement 17-Aug-22 24-Jan-23 25-Jul-22 28-Mar-23
4 Pre-Construction 14-Dec-22 24-Jan-23 16-Nov-22 11-Apr-23
5 Construction & Installation 07-Mar-23 14-Mar-23 13-Jul-23 20-Jul-23
Planned Activities
1
2
49.22%
3
4
RISKS PRIORITY
1
1
1
Actual
-3.48%
Engineering Percentage Completion Procurement Percentage Completion Pre-construction & Fabrication Percentage Construction Percentage Completion
100.00% 100.00% 79.30% Completion
0.00%
100.00%
95.00% 57.25% 0.00%
0.00% -5.00%
-22.05%
Overall Critical Activities Status Fabrication Critical Activities Status Procurement Critical Activities Status Construction & Installation Crtical Activities
Completed Status
14% Completed
In-progress Completed In-progress
0%
29% In-progress 0%
14%
33%
In-progress
43%
In-progress Not Started Completed In-progress Not Started Completed In-progress Not Started Completed In-progress Not Started Completed