KZN HUMAN SETTLEMENTS RENTAL

HOUSING ROLL-OUT LAN


2018-2023

20 JULY 2021

GROWING KWAZULU-NATAL TOGETHER


1
1. PROGRESS ON MUNICIPAL STATE OF
READINESS
MUNICIPALITY PRIORITY FULL STATE OF READINESS MILESTONES COMMENTS
CATEGORY

LAND DISPOSAL POLICY SHI APPOINTMENTS

eThekwini Metropolitan 1 Adopted • Municipality has adopted a SHI database


from which appointments are made.
• Municipality has allocated 10 projects to
SHIs that are currently at various stages of
planning

uMhlathuze Municipality 1 Adopted • Municipality appoints SHIs on a project to


project basis.
• Municipality has allocated 2 projects to SHIs
that are currently at various stages of
planning
1. PROGRESS ON MUNICIPAL STATE OF
READINESS CONT…
Newcastle Municipality 1 Adopted • Municipality appoints SHIs on a project to project basis.
• Municipality has allocated 1 project to a SHI that has just
recently graduated to construction.

uMsunduzi Municipality 2 Adopted • Municipality has adopted a SHI database from wherein 4
accredited SHIs have been registered.

Alfred Duma 2 Adopted • Municipality intends to adopt a SHI database, however in


Municipality the interim SHIs will be appointed on a project to project
basis.
1. PROGRESS ON MUNICIPAL STATE OF
READINESS CONT…
Ray Nkonyeni 3 Adopted • Municipal area has a major challenge of bulk service
infrastructure, the Ugu District Municipality currently
undertaking processes to secure funding for the
required infrastructure upgrades- estimated timeframe
is 5 years.
• Municipality will only initiate processes to appoint SHIs
once the afore-mentioned upgrades have progressed
significantly.
• In the interim Municipality is in the process of
appointing service providers to undertake feasibility
studies in preparation for project packaging.

KwaDukuza 4 Municipality currently undertaking internal • Municipality currently undertaking internal processes to
processes to adopt policy- to be tabled at the adopt a SHI database- will re-advertise for tender
next Council sitting
2. PROCESS TO RE-ALIGN MAPPING OF RESTRUCTURING ZONES AND
PREPARATION OF PERFORMANCE ASSESSMENT REPORT WITH
RECOMMENDATIONS TO THE MINISTER
• The Planning Unit initiated a process to assess performance within the gazetted restructuring zones throughout the Province for
the attention of the Minister, as per policy prescripts.
• During the exercise it was ascertained that there is a misalignment in the datasets of mapping across the three spheres of
government. Cases that were established include:
• Misalignment in the names of the restructuring zones used by the Municipalities, which differs to the names in the gazette;
what was listed in the applications made by municipalities is not what is listed in the gazette in terms of names.
• Subsequently, the associated mapping is also not aligned to the gazette.
• This called for an assessment of all mapping and ensuring that re-alignment is sort. The Planning unit then conducted another
round of municipal consultations to undertake working sessions to re-align the mapping and assess performance in terms of
projects being implemented within the gazetted zones. A series of emerging issues were established including:
• Lack of land availability within the boundaries, which called for boundaries to be expanded to include suitable parcels of land
and properties suitable for social housing.
• Limited capacity and or lack of bulk service infrastructure.
• Municipalities made proposals for additional restructuring zones to be gazetted in identified areas of future development
and growth where social housing can be enhanced.
• All the affected Municipalities have complied and a report has been concluded and its current at the Directors office for vetting.
3. PROGRESS UPDATE ON SOCIAL HOUSING PROJECTS
IN PLANNING PHASE
No ESTIMATED TIMEFRAME TO PROJECTED DATE TO
MUNICIPALITY PROJECT NAME UNITS SHI/ODA UPDATE CONCLUDE PLANNING COMMENCE
CONSTRUCTION
A. PROJECTS REGISTERED ON THE SHRA PIPELINE

3 eThekwini Lakehaven 3 216 FMHC • Project was endorsed by PSC on • TBC Commencement-
22 July 2019 TBC
• Project on hold pending
finalisation of FMHC business Completion- TBC
turnaround strategy with the
SHRA
4 eThekwini Bridge City-Site 547 Ke-Nako • Project has been registered on • Awaiting plan approval Commencement
33 the SHRA pipeline and being • Plan submission subject to date can only be
processed for funding approval. approval by Bridge City provided once
• The QSC needs to be reviewed as Management Association plans are approved
in its current form may require Design Review Panel and SHRA grant
more funding from other sources • Awaiting review of Bridge approval has been
• LAA has been signed and finalized City Precinct Scheme by obtained
• Lease agreement finalised yet to Development Planning
be signed Catalytic Projects
• Awaiting confirmation of
availability of bulk
3. PROGRESS UPDATE ON SOCIAL HOUSING PROJECTS
IN PLANNING PHASE CONT…
No ESTIMATED TIMEFRAME TO PROJECTED DATE TO
MUNICIPALITY PROJECT NAME UNITS SHI/ODA UPDATE CONCLUDE PLANNING COMMENCE
CONSTRUCTION

6 eThekwini 71 Playfair 180 Vascowiz • Project endorsed by PSC on 25 Awaiting plan submission by the Commencement- TBC
September 2019, SHI Demolition of existing
• Awaiting final SHRA approval and structures currently
loan funding approval from FNB. underway. Demolition
• Project also includes GAP contractor on site.
Housing units to cross-subsidize
project.
• All planning activities been
concluded.
7 uMsunduzi Crows Nest 412 Mapamo • Project endorsed by PSC on 21 95% Completed-awaiting final Commencement-
Housing January 2020 funding approval from the TBC
• SHI has reconfigured the project SHRA. Building plans yet to be
and adjusted the yield. submitted to Municipality
• The SHI has re-submitted phase 1
of the project to the SHRA-
project will be assessed for
funding approval in Quarter 3
3. PROGRESS UPDATE ON SOCIAL HOUSING PROJECTS IN PLANNING
PHASE CONT…
No ESTIMATED TIMEFRAME PROJECTED DATE TO
MUNICIPALITY PROJECT NAME UNITS SHI/ODA UPDATE TO CONCLUDE COMMENCE
PLANNING CONSTRUCTION
B. PROJECTS ENDORSED BY THE PROVINCIAL PSC (YET TO BE REGISTERED ON THE SHRA PIPELINE)
8 eThekwini 44 Lancers 288 Ubuntu Housing • Project endorsed by PSC on 23 October 2018 • TBC • TBC
• Project is subject to AMAFA approval for partial
demolition;
• SHRA has approved funding to appoint heritage
architect to undertake required detailed designs.
• Processes to apply for rezoning, currently on hold
subject to approval from AMAFA.
• Awaiting for the appointment of a social facilitator
by the Municipality.
9 eThekwini 2 Epsom 300 Royal Stock • Project endorsed by PSC on 23 October 2018 • SHI in the Commencement
Housing • Project is subject to AMAFA approval for partial process of TBC
demolition; finalising
• Application is currently underway for SHRA funding detailed Completion- TBC
to appoint heritage architect to undertake AMAFA drawings
approval process • Submission of
• SHI has submitted project to the SHRA in order for detailed plans is
funds to be dispersed. contingent on
• LAA being circulated for signature between SHI & Amafa clearance
eThekwini Municipality for submission to the SHRA and approval of
Rezoning and consolidation applications currently rezoning and
stayed pending AMAFA clearance. consolidation
application
3. PROGRESS UPDATE ON SOCIAL HOUSING PROJECTS
IN PLANNING PHASE CONT…
No ESTIMATED TIMEFRAME TO PROJECTED DATE TO
MUNICIPALITY PROJECT NAME UNITS SHI/ODA UPDATE CONCLUDE PLANNING COMMENCE
CONSTRUCTION
10 eThekwini Morans Lane 150 SOHCO • Consolidation and rezoning application • SHI is yet to commence with TBC
has been finalised. project planning.
• The SHI has not signed the Land • eThekwini Municipality has
Availability Agreement presented by the placed SHI on terms
Municipality.
• SHI has yet to submit project be placed
on the SHRA pipeline

11 eThekwini 144-45th Avenue 128 Motheo • The project requires a rezoning • Municipality due to re-appoint an TBC.
Sherwood application, -has been finalised and alternative SHI for project since
submitted for approval. Motheo has withdrawn from the
• SHI has rescinded its award of the site as project.
the SHI is no longer interested in pursuing • Municipality currently
social housing. undertaking internal SCM
processes to re-appoint an
alternative SHI.
12 eThekwini Duffs Road 400 FMHC • Project was endorsed by PSC on 26 June • TBC Commencement TBC
2018 Completion TBC
• Project on hold pending finalisation of
FMHC business turnaround strategy with
the SHRA
3. PROGRESS UPDATE ON SOCIAL HOUSING PROJECTS IN PLANNING
PHASE CONT…
No ESTIMATED TIMEFRAME TO PROJECTED DATE
MUNICIPALITY PROJECT NAME UNITS SHI/ODA UPDATE CONCLUDE PLANNING TO COMMENCE
CONSTRUCTION
13 eThekwini 1 Henwood, 100 Motheo • The SHI has rescinded its award of the site as the SHI • Municipality due to re- TBC
Pinetown is no longer interested in pursuing social housing appoint an alternative SHI
for project since Motheo
has withdrawn from the
project.
• Municipality currently
undertaking internal SCM
processes to re-appoint
an alternative SHI.
14 eThekwini FMHC Inner-city 248 FMHC • Projects consists of the following buildings owned by • We are currently awaiting
Buildings First Metro Housing: a decision on whether the
o Martinez-44 units projects will be allocated
o Esselem Court- 18 units to an alternative SHI or
o Strathdon Phase 1- 42 units whether they will be
o Tabora Court- 43 units
recapitalised in the hands
o Russel Mansions- 143 units
of FMHC,
• SHI currently in engagements with the Department,
SHRA and Municipality to withdraw the institutional
grant and dispose of the buildings.
• The Municipality has not consented to the disposal of
the buildings to an open market. The Municipality
supports the retention of the stock as Social Housing
or the transfer to other subsidy housing instruments.
• SHRA to confirm if the projects can benefit from grant
funding under another SHI who would take over the
project(s).
3. PROGRESS UPDATE ON SOCIAL HOUSING PROJECTS IN PLANNING
PHASE CONT…
No ESTIMATED TIMEFRAME PROJECTED DATE TO
MUNICIPALITY PROJECT NAME UNITS SHI/ODA UPDATE TO CONCLUDE COMMENCE
PLANNING CONSTRUCTION
15 eThekwini Site 20 Henley 138 Golden Empire • Project is being implemented by an ODA • TBC Commencement:
Road, Seaview Investments • Project was endorsed by PSC on 24 April 2020 TBC
• ODA currently packaging project to submit to the
SHRA for project enrolment and funding approval Completion; TBC
16 eThekwini 15 Alabama Road, 78 Golden Empire • Project is being implemented by an ODA • TBC Commencement:
Wenthworth Investments • Project was endorsed by PSC on 24 April 2020 TBC
• ODA currently packaging project to submit to the
SHRA for project enrolment and funding approval Completion; TBC
17 eThekwini Morningside, 405 Emron Housing • Projects were endorsed by the PSC on the 15th of • TBC Commencement:
Cowey Square Company September 2020, subject to: TBC
• SHI has acquired a municipal support letter in
respect of Cowey Square and Newcentre. Completion; TBC
18 eThekwini Newcentre 230 Emron Housing • SHI to resolve land legal issues with Phoenix sites
before obtaining support
Company
• Municipality will engage with SHI on this to
expedite.

19 eThekwini Phoenix, Shastri 230 Emron Housing


Park Company

20 eThekwini Phoenix, Stanmore 100 Emron Housing


Company
3. PROGRESS UPDATE ON SOCIAL HOUSING PROJECTS IN PLANNING
PHASE CONT…
No ESTIMATED PROJECTED DATE TO
TIMEFRAME TO COMMENCE
MUNICIPALITY PROJECT NAME UNITS SHI/ODA UPDATE
CONCLUDE CONSTRUCTION
PLANNING

C. PROJECTS ASSESSED FOR PRE-FEASIBILITY


uMhlathuze Dumisani Makhaye 1020 Milsetone SHC • Pre-feasibility assessment have been concluded TBC TBC
Village • Installation of bulk and internal services is 100%
complete.
• The project has been endorsed by PSC..
• The SHI is busy with packing applications to submit to
SHRA.
uMhlathuze Auqadene 1000 Dezzo • Installation of bulk and internal service currently TBC TBC
underway; 90% complete.
• LAA is currently outstanding- draft to be revised with
comments from SHI thereafter finalized and signed.
• Project has been endorsed by PSC.
• The SHI is busy with packing applications to submit to
SHRA

uMhlathuze Empangeni 1200 None • Installation of bulk and internal services is 100% TBC TBC
complete.
• A property valuation of the site has been concluded. the
Municipality is in the process of advertising to appoint a
SHI to implement the project.

eThekwini Umgeni 1500 None • mixed use development with 1500 social housing units)- TBC TBC
championed by the Human Settlements Unit
• Drive Inn Site – championed by the LED Unit. Due to
initiate feasibility assessments
3. PROGRESS UPDATE ON SOCIAL HOUSING PROJECTS IN PLANNING
PHASE CONT…
No ESTIMATED PROJECTED DATE TO
TIMEFRAME TO COMMENCE
MUNICIPALITY PROJECT NAME UNITS SHI/ODA UPDATE
CONCLUDE CONSTRUCTION
PLANNING
eThekwini Various Plots 431 None • Pre-feasibility studies have been TBC TBC
Durban, Warwick provided to Municipality
Area • Municipality to appoint SHI to implement
the project

uMsunduzi Oribi Village IRDP 500 Noble Housing • Pre-feasibility studies have been • TBC TBC
provided to Municipality
• Pre-feasibility studies have been
provided by the Municipality
• Project is being implemented by an SHI
• SHI currently packaging project to
submit to the SHRA for project
enrolment and funding approval
uMsunduzi Ethembeni IRDP 350 Khanyisampela • Pre-feasibility studies have been • TBC TBC
provided to Municipality
• Project is being implemented by an SHI

SHI currently packaging project to submit


to the SHRA for project enrolment and
funding approval
uMsunduzi Signal Hill 300 Litadox NPC • Pre-feasibility studies have been • TBC TBC
provided by the Municipality
• Project is being implemented by an SHI
• SHI currently packaging project to
submit to the SHRA for project
enrolment and funding approval
3. PROGRESS UPDATE ON SOCIAL HOUSING PROJECTS IN PLANNING
PHASE CONT…
No ESTIMATED PROJECTED DATE TO
TIMEFRAME TO COMMENCE
MUNICIPALITY PROJECT NAME UNITS SHI/ODA UPDATE
CONCLUDE CONSTRUCTION
PLANNING
Ray Nkonyeni Marburg Erf 4939 300 None • Pre-feasibility studies have been provided to Municipality TBC TBC
• Municipality to appoint SHI to implement the project.

Ray Nkonyeni Marburg Erf 4941 300 None • Pre-feasibility studies have been provided to Municipality TBC TBC
• Municipality to appoint SHI to implement the project.

KwaDukuza Thornhill and 870 None • Pre-feasibility studies have been provided to Municipality TBC TBC
Parkwood • Municipality to appoint SHI to implement the project.

KwaDukuza Hyde Park 800 None • Pre-feasibility studies have been provided to Municipality TBC TBC
• Municipality to appoint SHI to implement the project.
4. COMMUNITY RESIDENTIAL UNITS (CRUs)
COMMUNITY RESIDENTIAL UNITS (CRUs)

PROJECTS AT FEASIBLITY PHASE-STAGE 1


• Consists of 180 units
• TEC 1 approval has been granted
1. Mkhuze CRU • Bilateral agreement between DHS and Jozini Municipality has been concluded and signed
• Municipality currently finalizing the signing of the bilateral agreement with the appointed IA
• Detailed planning underway-SPLUMA application has been lodged awaiting public comments.

• Consists of 300 units


• TEC 1 approval has been granted
• Bilateral agreement between DHS and Mzimkhulu Municipality has been concluded and signed
1. Mzimkhulu CRU
• Municipality has appointed an IA to undertake the project
• A project inception meeting was held on the 17 June 2022 and planning has commenced.

PROJECTS AT PRE-FEASIBILITY PHASE


• Consists of 500 units
• Project is at pre-feasibility stage.
1. Phongola CRU
• Project requires a demand study for which preparation funding has been approved.
• Bilateral agreement between DHS and the Municipality has been signed and concluded
• The appointed IA is currently undertaking a demand study.
4. COMMUNITY RESIDENTIAL UNITS (CRUs)
CONT…

• Project requires a demand study for which preparation funding has been approved.
• Bilateral agreement between DHS and the Municipality has been signed and concluded
1. Maphumulo CRU • Isibuko SeAFrica Development Planner have been appointed to undertake the feasibility study.
• The draft report has been completed and submitted to the Department for vetting and we anticipate for the project to be closed out
no later than 31 July 2022.

• Consists of 150 units


• The project required preparation funding as part of pre-feasibility undertakings, funding approval has been granted
1. Shayamoya CRU • Bilateral agreement between DHS and the Municipality has been drafted and will be signed by Friday 07 May 2021.
• Municipality has not appointed an IA to undertake the project and is currently facing litigation.
• Department has provided aiding documents for Municipality to undertaking process to appoint.
5. HOSTELS
1. HOSTELS

GENERAL: Planning unit is currently in the process of finalizing the conditional assessments cost guidelines/model to appoint professionals to undertake conditional assessments on
existing hostels. This will allow for a standardized costs and ensure value for money is achieved. Once this process has been concluded and guidelines have been adopted, processes to
roll-out the 20 year strategy will be initiated.
• All prefeasibility assessments have been concluded and a submission requesting for the approval of funding for stage 1 activities to
undertake detailed planning and design has been drafted and is currently circulating for vetting and signatures.
• The submission was drafted and approved for the appointment of service providers from our built environment data base to undertake
1. Khwezi Hostel
detailed planning and design.
• The Department has resolved for the HDA to proceed with the appointment of a team to undertake detailed planning a progress
meeting is scheduled for 22 July 2022,

• An application for funding to renovate the existing hostels was received by the Department.
• A submission for the approval of funding for the appointment of a professional team to undertake a conditional assessments was
crafted and approval was granted by HOD.
• Approval was forwarded to SCM to undertake internal process to appoint professionals.
• There have been severe delays with SCM due to the BEAC committee being dissolved and re-established.
• The project was finally tabled and approved on the 30th of April 2021
1. Indumeni Hostel
• SCM has given service providers 10 days to craft and submit development programmes
• The services providers have requested sites in order to prepare development programmes.
• Planning unit will facilitate the site visit.
• A tender briefing meeting was held on 30 June 2022 SCM has given an undertaking that all outstanding processes shall be concluded no
later than 31 July 2022.
• Service providers have been appointed to undertake the conditional assessments and letters issued.
THANK YOU