CONNECTIVITY BRIDGE BETWEEN EAST & WEST WHARF (CBEWW)

CCECC USMANI JOINT VENTURE INTERIM PAYMENT CERTIFICATE NO. 004 WORK DONE: 18-10-2023
Amount (Rs.)
Bill No. DESCRIPTION Remarks
Previous Present Total
1 Geotechnical Investigation 16,013,299.20 - 16,013,299.20

2 Demolishing & Dismantling Works 2,176,802.72 - 2,176,802.72

3 Bridge 63,806,874.25 67,251,613.66 131,058,487.91

4 Road Work - - -

5 Storm Water Drainage System - - -

6 Sub Total - I 81,996,976.17 67,251,613.66 149,248,589.83