ID Task Task Name Duration Start Finish Predecessors Resource Names December 21 August 11 April 1 November 21 July 11

Mode 12/11 4/2 7/23 11/12 3/3 6/23 10/13 2/2 5/25 9/14
1 PROJECT A 156 days Thu 11/2/23 Thu 6/6/24
2 surveying 1 day Thu 11/2/23 Thu 11/2/23 surveyer surveyer
3 column marking 1 day Fri 11/3/23 Fri 11/3/23 2 column marking column marking
4 foundation ,marking 4 days Mon 11/6/23 Thu 11/9/23 3 column marking,sand[1],water[1] column marking,sand[1],water[1]
5 steel design 6 days Fri 11/10/23 Thu 12/14/23 2,4 steel [1] steel [1]
6 curing 1 day Fri 12/15/23 Fri 12/15/23 5 water[1] water[1]
7 brick work 15 days Mon 12/18/23 Fri 1/5/24 6 brick [1],cement[1],sand[1],water[1] brick [1],cement[1],sand[1],water[1]
8 slab 7 days Mon 1/8/24 Tue 1/16/24 7 cement[1],sand[1],slab[1] cement[1],sand[1],slab[1]
9 interior works 17 days Wed 1/17/24 Thu 2/8/24 7,8 cement[1],sand[1],steel [1],wood[1] cement[1],sand[1],steel [1],wood[1]
10 electric work 3 days Fri 2/9/24 Tue 2/13/24 9 electrician electrician
11 plumbing work 4 days Wed 2/14/24 Mon 2/19/24 10 plumber plumber
12 PROJECT B 119 days Fri 11/3/23 Wed 4/17/24
13 surveying 1 day Fri 11/3/23 Fri 11/3/23 surveyer surveyer
14 foundation 1 day Wed 2/14/24 Wed 2/14/24 10,13 surveyer surveyer
excavation
15 column marking 1 day Thu 2/15/24 Thu 2/15/24 14 column marking,surveyer column marking,surveyer
16 steel designing 4 days Fri 2/16/24 Wed 2/21/24 15 steel [1] steel [1]
17 casting/curing 25 days Fri 2/16/24 Thu 3/21/24 14,15 water[1] water[1]
18 brick work 20 days Thu 2/22/24 Wed 3/20/24 16 brick [1],cement[1],water[1] brick [1],cement[1],water[1]
19 parapet wall 4 days Fri 3/22/24 Wed 3/27/24 17,16 brick [1],cement[1],sand[1],water[1] brick [1],cement[1],sand[1],water[1]
20 plumbing work 7 days Thu 3/21/24 Fri 3/29/24 18 plumber plumber
21 flooring 15 days Thu 3/28/24 Wed 4/17/24 19 cement[1],water[1] cement[1],water[1]
22 painting 8 days Mon 4/1/24 Wed 4/10/24 20 painter painter
23 PROJECT C 41 days Thu 4/11/24 Thu 6/6/24
24 site cleaning 2 days Thu 4/18/24 Fri 4/19/24 21 helper helper
25 surveying 1 day Thu 4/11/24 Thu 4/11/24 22 helper,surveyer helper,surveyer
26 foundation marking 1 day Mon 4/22/24 Mon 4/22/24 22,24 helper,surveyer helper,surveyer
27 excavation 1 day Fri 4/12/24 Fri 4/12/24 25 helper helper
28 laying footing 2 days Tue 4/23/24 Wed 4/24/24 26 helper helper
29 concrete design 3 days Thu 4/25/24 Mon 4/29/24 27,26 cement[1],sand[1],water[1],helper cement[1],sand[1],water[1],helper
30 brick work 20 days Tue 4/30/24 Mon 5/27/24 28 brick [1],cement[1],helper,sand[1],water[1] brick [1],cement[1],helper,sand[1],water[1]
31 interior design 12 days Tue 4/30/24 Wed 5/15/24 29 cement[1],water[1],worker cement[1],water[1],worker
32 parapet wall 4 days Tue 5/28/24 Fri 5/31/24 30 brick [1],cement[1],helper,sand[1],water[1] brick [1],cement[1],helper,sand[1],water[1]
33 painting 8 days Tue 5/28/24 Thu 6/6/24 29,30,31 painter painter

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
Project: RAGUNATH.T
097
Milestone Inactive Task Manual Summary Rollup Progress
Date: Thu 11/2/23
Summary Inactive Milestone Manual Summary
Project Summary Inactive Summary Start-only

Page 1 097