Volume of planned

No. Bridge Position Operation


works total
1 M1 BRIDGE km 45+208 Piles 88
2 M1 BRIDGE km 45+208 Foundations 12
3 M1 BRIDGE km 45+208 Middle piers 12
4 M1 BRIDGE km 45+208 Abutments 8
5 M1 BRIDGE km 45+208 Bearing beams 12
Installation of the precast
6 M1 BRIDGE km 45+208 144
girders
7 M3 BRIDGE km 48+951 Pedestrian walkways 4
8 M6 OVERPASS km 54+014 Bearing beams 4
Installation of the precast
9 M6 OVERPASS km 54+014 18
girders
10 M6 OVERPASS km 54+014 transverse girders 4
11 M6 OVERPASS km 54+014 Bridge deck 1
12 M7 OVERPASS km 56+354 End slope 100%
13 M9 OVERPASS km 58+170 Pedestrian walkways 2
14 M13 BRIDGE km 62+350 End slope 100%
15 M14 OVERPASS km 62+938 Pedestrian walkways 2
16 M15 BRIDGE km 63+700 End slope 100%
Volume of planned works in Volume of executed production from
June 29th of May to 2nd of July
20 11
3 3
3 3
3 1
4 3

56

4 3
1 1

18

2
0.5
50% 50%
1 1
100%
2 1
100% 100%
Volume of executed production from 12th of Description of executed production from 12th of June to
june to 18th of June 18th of June
4 Concreted 4 piles.

2 Concreted 2 middle piers.

2 Concreted 2 bearing beams.

3 Concreted 3 pedestrian walkways.

1 Concreted 1 pedestrian walkway.


50% End slope finishead 50%