The document lists 15 bridge and overpass projects with planned works and progress updates. It provides the bridge number, location, planned operations, planned volume of works, volume executed as of December 30th, volume executed from January 9th to 15th, and descriptions of work done from January 9th to 15th. The operations include finishing works, bearing beams, abutments, precast girders, deck slabs, and piles. The document summarizes progress on planned construction volumes.
The document lists 15 bridge and overpass projects with planned works and progress updates. It provides the bridge number, location, planned operations, planned volume of works, volume executed as of December 30th, volume executed from January 9th to 15th, and descriptions of work done from January 9th to 15th. The operations include finishing works, bearing beams, abutments, precast girders, deck slabs, and piles. The document summarizes progress on planned construction volumes.
The document lists 15 bridge and overpass projects with planned works and progress updates. It provides the bridge number, location, planned operations, planned volume of works, volume executed as of December 30th, volume executed from January 9th to 15th, and descriptions of work done from January 9th to 15th. The operations include finishing works, bearing beams, abutments, precast girders, deck slabs, and piles. The document summarizes progress on planned construction volumes.
works total 1 M1 BRIDGE km 45+208 Finishing works 4 2 M3 BRIDGE km 48+951 Bearing beams 4 3 M3 BRIDGE km 48+951 Abutments 4 4 M3 BRIDGE km 48+951 Precast girders 60 5 M3 BRIDGE km 48+951 Montage of girders 60 6 M3 BRIDGE km 48+951 Deck slab 2 5 M4 BRIDGE km 50+816 Abutment piers 4 6 M4 BRIDGE km 50+816 Deck slab 2 7 M5 OVERPASS km 51+438 Bearing beams 4 8 M5 OVERPASS km 51+438 Precast girders 21 9 M6 OVERPASS km 54+014 piles 14 10 M7 OVERPASS km 56+354 Bearing beams 4 11 M7 OVERPASS km 56+354 Precast girders 18 12 M8 BRIDGE km 56+773 Abutment piers 4 13 M8 BRIDGE km 56+773 Deck slab 2 14 M9 OVERPASS km 58+170 Deck slab 1 15 M11 OVERPASS km 59+967 Deck slab 1 15 M14 OVERPASS km 62+938 Deck slab 1 Volume of planned works in Volume of executed production up to January 30th of December 1 4 2 9 20 0 2 1 2 0 1 0 10 2 1 0 0.5 0 Volume of executed production from 09th of Description of executed production from 09th of January to 15th of January January to 15h of January 0 0 0 0 0 0 0 0 0 0 1 concreted 1 pile. 4 concreted 4 bearing beams. 3 concreted 3 girders. 0 0 0 0 0
A Comparative Study On The Foreign Policy of Japan and South Korea Towards China in Relation To The Issue of Territorial Integrity Under The Presidency of President Xi Jinping (2013)