MS For Mobilization of Site Offices55
MS For Mobilization of Site Offices55
: Doc No : IP1-02-002-04-
HUDAYRIAT 11-CW-HLCO-MT-000003
ISLAND (WEST) Rev.: 00
ENABLING PAVING lllE WAY fOIIWAIU)
WORK Date: 17-Jan-2021
METHOD STATEMENT
FOR
Table of Contents
1. Introduction
2. Scope
3. Definitions
4. References
5. Product Required
7. Manpower Required
9. Safety Precautions
11. Environmental
13. Attachments
a. Risk Assessment
b. Checklist
1. Purpose:
The purpose of this method statement is to outline the general requirements &
precautionary measures which should be taken into consideration for the mobilization of
site offices.
2. Scope:-
The scope of this method statement is to provide a detailed description of the mobilisation
of temporary site offices. This method statement will ensure that works are executed within
the quality requirements of the contract, minimise risks related to that activity and finally
prevent accidents and damages.
3. Definitions:-
• Employer MODON
• Consultant: SALFO & Associates SA
• Contractor : Hila! Bil Badi & Partners Contracting Company (WLL)
• RA Risk Assessments
4. References:-
• Particular Specification
• Standard Specification
• Drawings
• Approved HSE Plan
• Abu Dhabi Occupational Safety & Health System Framework (OSHAD- SF)
• Approved Project Quality Plan
5. Product Required:-
• Precast concrete blocks
• Prefabricated Cabins
• Electrical Cable
• Data Cable
• UPVC Pipes and accessories
• Cement, Sand and Water
• GRP tanks
• Scaffolding
6. Tools and Equipment Required:-
• JCS
• Hand Roller
• Trailers
• Crane and lifting equipment
• Small Tools
• Pick up, Long body pick up
• Hiab
• Grader
• Ladders/temporary access
• Scaffolding
• CAT Scanner
• Bus
• Water Tanker
7. Workforce:-
• Supervisory:
Project Manager I Construction Manager
Site Engineer
Foreman
Asst. Foreman
HSE Advisor
• Direct:
Ganger Steel Fixers
Operators Mason
Labour Flagmen
Surveyor Electrician
Carpenter Plumber
Key Personnel
Project Manager:
He is the end responsible of the project. He is responsible for organizing induction
and training of people, organizing the site team and ensures that sufficient and
adequate safety equipment is available. He is the chairman of the Safety
Committee.
Foreman/Asst. Foreman:
Directly supervises the work activity on the site and has full control over the use of
the labour, plant and equipment. He ensures that the work is carried out in full
compliance with the specifications, and in a manner that is conform to the Safety,
Quality and Environmental requirements. He reports to the Coordinator/Supervisor
when the work is completed.
.HSE Adviser:
He visits the activities on site and checks if the works are carried out as per laws,
Health, Safety and Environmental Plan and method statements. He advises all
members of the hierarchic line on any shortcomings or additional measures to be
taken and reports to the Project Manager. He has the power to stop the works
immediately if required.
Date: 17-Jan-2021
9. Safety Precautions:-
• Lifting activities shall be done with a trained and certified mobile crane operator and a
rigger. All of the cranes equipment and mechanical items shall be inspected by third
party who shall provide a fit for purpose certificate.
• All the operations will be carried out in a safe working manner and in each and every
case, fully compliant to the HSE plan and risk assessment.
• Specific tool box talks will be given prior to commencing any sort of lifting activity by
the engineer, foreman and HSE inspector. All workforce will enforce one another to
continuously implement HSE regulations and to follow the minimum HSE PPE
requirements.
j. It is important to add that all these activities mentioned above shall be accompanied by
specific tool box talks in relation to that said activity.
k. Drainage and sewer systems shall be connected from the office cabins to the temporary
constructed house connection chambers and then eventually to the underground septic
tank.
I. Furthermore, office cabins shall be powered by a nearby generator. All connections from
office to SMDB and to the generator shall be done by a trained electrician.
m. All these connections shall be done in line with the latest requirements of the governing
bodies.
11. Environmental:-
AII the works will be carried out in accordance with the environmental code of practice
Implemented by contractor. All specific environmental issues are addressed below:
Spill kits will be provide by contractor and operatives will be given full training and tool
box talks on the procedures to be adopted in the event of a spillage.
A( Boom Length) = m
B( Radius ) = Swl (C) m
==
Weight of load (D)=
Calculation :
efficiency of crane = DIC * 100
◄······••tt••···••tt•••♦
NOTE: ITEM 'C' IS TO INCLUDE ALL REQUIRED DEDUCTION E.G., WIRE ROPES, MAIN HOOK, AUX HHOK, FLY JIB ETC