Professional Documents
Culture Documents
Cost Estimation Assignment No 3
Cost Estimation Assignment No 3
Cost Estimation Assignment No 3
Asignment No 3
Answer:
First, we have the dimension of brick is given as below:
9 ×4.5 ×3
Now considering mortar the size of brick work is given below:
9 ×4.5 ×3 (6.5 in^3 mortar
Calculating amount of bricks per single cubic feet can be done by following equation.
Volume
Quantity of Bricks=
Volume of Single Brick
1
Quantity of Bricks=
0.0741
Quantity of Bricks=13.5
Question No 2: Determine the number of bricks, corrugated masonry ties, and mortar
needed to face a wall 50 feet long by 10 feet high. The brick is 2 1/2 inches high by 3 1/2
inches wide by 11 1/2 inches long. Allow for a 1/2-inch mortar joint. The spacing between
the ties is to be 18 inches measured vertically and 36 inches measured horizontally.
Historically, 10.2 cubic feet of mortar is required per 100 square feet of brick.
Answer:
Given:
Length of wall = 50 ft
Height of wall = 10 ft
Height (depth) of brick is = 2 ½ inches
Width of brick is = 3 ½ inches
Length of bricks is = 11 ½ inches
Mortar joint is = ½ inches
Spacing of ties (vertically) = 18 inches
Spacing of ties (Horizontally) = 36 inches
10.2 cubic ft of mortar is required for per 100 square ft of bricks = 10.2 ft 3 / 100 ft2
Solution:
First, we calculate the volume of single brick as given below;
Volume of brick =l× w × d
Along the wall, the ties are arranged in rows and columns. Along the wall, a column will appear every three
feet. Seven rows of ties will make up the columns, which are spaced 1 foot, 6 feet, 3 feet, 4 feet, 6 feet, 7
feet, 9 feet, and 9 feet 9 inches above the wall's base. Since the wall's base will rest on a footing,
foundation, or steel lintel, a tie is not required there.
We calculate the number of horizontal ties as follows;
Heigth ofwall
Number Row ties=
Horizontal Spacing
Putting values in above formula, we get:
10
Number Row ties=
1.5
Number Row ties=6.66∨7 rows
Now, we calculate the volume of mortar needed as by using the following formula we get;
3
ft
Volume of mortar =10.2 2
×500
100 f t
3
Volume of mortar =51 f t
Also,
3
1 cy=27 f t
Now,
51
Volume of mortar =
27
Volume of mortar =1.888 cy
Question No 3: Determine the volume of concrete in cubic yards and the lineal feet of
forms needed to complete the footings shown in Figures below. Include 8% waste in the
calculated volume of concrete.
Solution:
We need to calculate the volume of concrete required for this
The base thickness of footing is given as,
Thickness of footing=2.5 ft
(
Volume=( 115 ×1 ×2.5 ) + 115 ×8 ×
8
12 )
Volume=900 cft
Question 04: Determine the volume of concrete in cubic yards, and the rebar needed to
complete 10 of the columns shown in Figure below. Provide 2 inches of cover for the
rebar in the columns. The ties begin 3 inches from the bottom of the column and end 3
inches from the top of the column. Include 5% waste in the calculated volume of
concrete.
Answer:
2
πd 2
Areaof column= =1.4 f t
4
Total number ofcolumns=10
Depth of column=8 '
Diameter =16
Depth of foundation=1 '
Length of foundation=3' 2
#5:
The #5 re-bar cutting length is given as:
10+16+13
=3.25 '
12
Hence total number of bars are
Number of bars=8
2π ( 12 )=3.14 '
Hence total number of bars are
Number of bars=15