SPECIAL REPORT

Date: -25/10/2023

Subject: - Issuing BT Rake Fit Memo without proper examination of unloaded BOBYN by
Sh. Dharm Veer, JE/P.way/BJU/ML.

BT Unloading Block: - 13:05 – 14:35


Section: - BJU-TGA (UP Line)
Officials present at site: 1. ADEN/West/BJU, Sh. Pramod Kumar
2. SSE/P.Way/E/SPJ/inc, Vincent Vijay Beck
3. SSE/P.Way/BJU/yard, Sh. Navin Pathak
4. JE/P.way/BJU/ML, Sh. Dharm Veer

BT Unloading block was granted from BJU and block was to be cancelled at TGA. Unloading of
ballast was planned in BJU-TGA UP Main Line.

28 BOBYN Unloaded between OM 180/7 – 15 and OM 183/5 –


184/29 in UP line. All doors in both side of all BOBYN were kept
open during unloading at site. After unloading, I remained at
site and rake moved at 14:25 for block cancellation. Block was
cancelled at 14:35 and sectional PWI/BJU/ML, issued rake fit
memo by considering that all doors were open during the block,
hence there was no possibility of uneven unloading.

But after checking of unloaded BOBYN, it was found that


approximately 25 % ballast is remaining in one side of 8’th
BOBYN from Engine.

This remaining ballast was unloaded in TGA Yard UP Loop Line and Rake fit memo given at
16:00 Hours for movement in next block section.

PRAMOD Digitally signed by PRAMOD


KUMAR

KUMAR Date: 2023.10.25 20:20:26


+05'30'

ADEN/W/BJU