Professional Documents
Culture Documents
4384 QPD 9 TS H 0001 1 CDF
4384 QPD 9 TS H 0001 1 CDF
4384 QPD 9 TS H 0001 1 CDF
Doc. No.: 4384-QPD-9-TS-H-0001 Rev.: 1 Disposition Dept.: Al-Balagh Trading & Cont. Co. WLL
Review Date: 16/04/2023 Disposition Date: Select date.
Status 10,
S. No. 2, 3, 6, 1 Comments Dispositions (Contractor) Status/Remarks
and 11.
ITEM 8.08
Status 10,
S. No. 2, 3, 6, 1 Comments Dispositions (Contractor) Status/Remarks
and 11.
ITEM 8.08-8.09-8.10
3. 2 Rev.1 OPEN
Noted.
Provide scope of work demarcation of proposed the
Please note the correction from VAV to CAV in all pages
proposed modification of the control philosophy of the
which are existing base-build units only.
existing CAV/FCU’s serving the service lobby.
Status 10,
S. No. 2, 3, 6, 1 Comments Dispositions (Contractor) Status/Remarks
and 11.
Status 10,
S. No. 2, 3, 6, 1 Comments Dispositions (Contractor) Status/Remarks
and 11.
2. 2 1. Item 7.05 Pls clarify why replacing the exiting weather 1. QDC reported observation about existing weather
louvres at Level 29 will prevent clogging and damage to louver and proposed sand trap louver in fan room to
plant ? Refer also to PIQ0052C comments. protect the new motorized dampers from sand and silt
ingress and protect from clogging, thus preventing
ambient air infiltration into staircase and lobby. Weather
louver is assigned with priority 2 (optional) in Section 9 of
the report No. 4092_DPS_T8_R1. A semi-annual
maintenance Plan is proposed for pressurization fan
motorized damper in section 8.01, 8.02 and 8.03 of the
report No. 4092_DPS_T8_R1.
Status 10,
S. No. 2, 3, 6, 1 Comments Dispositions (Contractor) Status/Remarks
and 11.
Refer to section 8.08-8.13 of the report No.
4092_DPS_T8_R1.
6. Noted and updated in Section 7.12, in report No.
4092_DPS_T8_R1.
6. Item 7.12 provide snapshot of the Staircase 1 door opening
at Level 1 opens to Mech area. 7. DFCU to be allowed with new FCU controller for BMS in
service lobies.. All service lobbies set point temperature
7. Item 7.13 BMS controlled DFU's, is this feasible with existing proposed 28C. Refer to Section 8.04 and 8.05 for set point
base build DFU's? What set point temperature is temperature, in report No. 4092_DPS_T8_R1.
recommended? 8. Temperature control in lobby is by space sensor i.e.
input and monitoring is by BMS. Refer to Section 8.15 of
the report No. 4092_DPS_T8_R1.
8. Item 7.14 are you advocating that the temperature control of 9. Noted and updated in Section 8.16b of the report No.
this lobby area should be via BMS as well? 4092_DPS_T8_R1.
Status 10,
S. No. 2, 3, 6, 1 Comments Dispositions (Contractor) Status/Remarks
and 11.
11. QCS 2014, Section 22, under design data 1.1.7 refers to
summer peak condition of 46Cdb and 30Cwb, resulting in
dew point temperature of 25.2C. Comparing QCS with
ASHRAE specific Evaporative condition is worst case in
11. Item 8.05 the implication that condensation 35hrs / yr (0.4 Section 4.03 and Appendix of the report No.
exceedance) would seem that ASHRAE is not a reliable 4092_DPS_T8_R1.
source for estimating the duration of probable
condensation here in the MENA region. 12. Airlock lobby with door access control and provision of
split unit is proposed to staircase 1 door open to terrace at
level 29. Refer to Section 8.07 of the report No.
4092_DPS_T8_R1.
12. Item 8.06, please refer to my comments on Item 7.07 i.e.
pls mention provision of airlock in Section 7.07 13. Door repair/replacement should be in accordance to
NFPA 80 Section 5.5: Maintainence.
13. Item 8.07 apart from door seals, should we not address if
door needs to be replaced as well, as some doors may not be Refer to section 8.08-8.13 of the report No.
re-useable? 4092_DPS_T8_R1.
Status 10,
S. No. 2, 3, 6, 1 Comments Dispositions (Contractor) Status/Remarks
and 11.
will lead to complaints from individuals.
1. The comment states that dust ingress might damage the 1. QDC reported observation about existing weather
Mechanical equipment inside the room due to non-available louver and proposed sand trap louver in fan room to
weather louver. However, rest of the pressurization fan are protect the new motorized dampers from sand and silt
exposed to outdoor without any enclosure or dust protection. ingress and protect from clogging, thus preventing
ambient air infiltration into staircase and lobby. Weather
louver is assigned with priority 2 (optional) in Section 9 of
the report No. 4092_DPS_T8_R1. A semi-annual
maintenance Plan is proposed for pressurization fan
motorized damper in section 8.01, 8.02 and 8.03 of the
3. 2 report No. 4092_DPS_T8_R1.
2. The proposed DFCU in the staircase is with heater similar to a 2. Refer to Section 8.01, 8.02, 8.03, 8.07, 8.08-8.13 and
modified dehumidifier. There is difficulty for the source of 8.20, in report No. 4092_DPS_T8_R1, to stop ambient air
chilled water as the building was built without provision for infiltration in staircase & lobby.
such DFCU in the staircase. The DFCU will not contribute Proposed FCU (chilled water and VRF option) in staircase is
positive pressure to counter any leakage of outside air since it for recirculation of air in the staircase and to maintain
will work only to recirculate the air while removing moisture. temperature above the dew point. The proposed solution
Please submit another alternative which will not violate QCDD does not violate QCDD requirement. Refer to Section
requirements. 8.16a of the report No. 4092_DPS_T8_R1.
4. 2 Section 3. (Project Overview) of the Submittal: Contractor to Noted.
clarify who will be developing the detail drawings as per the Detailed drawings will be submitted by design consultant.
current Dew point study outcome, as QDC scope as quoted
Section-3 is limited to Dew-point study
Status 10,
S. No. 2, 3, 6, 1 Comments Dispositions (Contractor) Status/Remarks
and 11.
Section 7.14 of the submittal: A space sensor is more suitable
rather than the thermostat in order to provide the setpoint Noted and updated in Section 7.15 and 8.15 of the report
only from the BMS only. No. 4092_DPS_T8_R1.
Section 7.16 of the submittal: QDC to clarify the impact of Refer 7.17 section of the report, Storm water retention
'Roofing drainage related maintenance' on Staircase over a long period can absorb into the fabric, causing
condensation. damage to building material, and increase risk of
condensation. Refer to BS 5250:2021 for impact of
precipitation on building condensation. The driest weather
prevails in Qatar in the month of June, July, August &
September. On this basis the roof treatment is assigned
priority 2 (optional) in Section 9, of the report No.
4092_DPS_T8_R1.
Section 8 of the submittal: Contractor to confirm the inclusion
of BMS monitoring in their current work execution at site for Noted.
new smoke dampers for Staircase and Lobby fans Confirmed for BMS monitoring of newly installed smoke
dampers.
Section 8.01, 8.02 8.03 of the submittal: Contractor to include
the specific site condition for Ducts, flexibles joints condition Noted.
for air tightness and sealant issue. Site condition of Ducts, Ducts and joints are air-tight which will not allow any
flexibles joints and sealant should be clearly highlighted as part exfiltration. Sealant applied is UL approved only.
of this report.
Document Reference: 4384-QPD-9-TS-H-0001 Rev. 1 Page 8 of 12
CLIENT CONSULTANT (QRC) PROJECT DETAILS
Project Name: EPIC FOR MISCELLANEOUS IMPROVEMENT 1 AT QPD
Package No.:
Status 10,
S. No. 2, 3, 6, 1 Comments Dispositions (Contractor) Status/Remarks
and 11.
Status 10,
S. No. 2, 3, 6, 1 Comments Dispositions (Contractor) Status/Remarks
and 11.
in Section 8.10
"Pressure test is proposed in each staircase for assessment of Following the proposed remedial measures outlined in the
infiltration flow." report, it is proposed to conduct pressure test on the
Section 8.10 of the submittal: staircases for infiltration assessment.
Refer to Section 8.20, in report No. 4092_DPS_T8_R1.
5. 2 1. Please provide the basis of selecting the proposed FCU's Refer to Note in Section 8.16a of the report No.
locations in the staircase, A detail design is required for the 4092_DPS_T8_R1. CFD simulation will be done to confirm
proposed FCU’s in the staircase including the location, final No. Of FCU’s, location, capacity, and heater sizing.
capacities, heater sizing, temperature set points. A CFD analysis
will be an appropriate guidance to finalize the location,
capacity, heater sizing, temperature set points etc. of the
proposed FCU, Contractor to submit the same ad part of the
current report.
Noted.
2. Further, Strategy/concept for Chilled water Tap-off form If CHW FCU strategy is adopted, all details including
existing chilled water network to be studied and clarified, schematics /drawings/ drainage/ electrical will be
Similarly, Condensate drainage and electrical termination provided.
strategy to be included. If VRV strategy is adopted, same will follow.
3. Other alternative to be studied for cooling/dehumidification Options considered for dehumidification includes chilled
of the staircase. water FCU beside VRF system. Refer to Section 8.16a of
the report No. 4092_DPS_T8_R1.
Status 10,
S. No. 2, 3, 6, 1 Comments Dispositions (Contractor) Status/Remarks
and 11.
For further comments, please refer to the attached commented
copy of the submittal.
Status 10,
S. No. 2, 3, 6, 1 Comments Dispositions (Contractor) Status/Remarks
and 11.
further, Only one level i.e. Level-13 is identified where the AHU
room is located adjacent to Staircase, however,
there are several instances where the AHU rooms are adjusted
to staircase-1 at tower-1, all such level shall be
clearly identified as part of this report.
Document Status: 10 = Approved 2 = Approved with Comments (Incorporate comments 3 = Not Approved (Incorporate comments and
(Resubmission not and resubmit - work may proceed subject to resubmit - work shall not proceed)
required) incorporation of comments)
6 = For Information 1 = Approved without Comments (Resubmission 11 = Cancellation Accepted
Only required - work may proceed)
Note 1: A unique CDF serial number will be allocated with document initial submission; subsequent revisions will be reflected in CDF revisions (applicable at least by QRC and QP)
Note 2: Originator - QP/ QRC
Note 3: Please encode separate number for each CDF in the footer with revision number