Professional Documents
Culture Documents
4384 QPD 9 TS H 0003 1 CDF
4384 QPD 9 TS H 0003 1 CDF
4384 QPD 9 TS H 0003 1 CDF
Doc. No.: 4384-QPD-9-TS-H-0003-0 Rev.: 0 Disposition Dept.: Al-Balagh Trading & Cont. Co. WLL
Review Date: 18/04/2023 Disposition Date: Select date.
Status 10, 2,
S. No. Comments Dispositions (Contractor) Status/Remarks
3, 6, 1 and 11.
Level 20
2. 2 Noted. Open
Clarify the DFCU mentioned is newly proposed or DFCU mentioned is base-built unit.
existing base build unit. DFCU is not having EC motor.
Contractor to check and verify the installed base build Base build details are with QRC/ MCFM only
DFCU is having EC Motor.
If the DFCU mentioned is base build unit. CONTRACTOR
to provide the Equipment tag reference number and
DDC reference number for clarity.
Document Reference: 4384-QPD-9-TS-H-0003 Rev. 1 Page 1 of 9
CLIENT CONSULTANT (QRC) PROJECT DETAILS
Project Name: EPIC FOR MISCELLANEOUS IMPROVEMENT 1 AT QPD
Package No.:
Status 10, 2,
S. No. Comments Dispositions (Contractor) Status/Remarks
3, 6, 1 and 11.
REV.1
1. “DFCU is not having EC motor”. CONTRACTOR to
update the attached schematic drawing accordingly.
Provide comprehensive FCU control philosophy with
the scope of work demarcation for review.
2. Previous comment not complied. CONTRACTOR to
provide the base build FCU/VAV Equipment tag
reference number and DDC reference number for
clarity.
Status 10, 2,
S. No. Comments Dispositions (Contractor) Status/Remarks
3, 6, 1 and 11.
Status 10, 2,
S. No. Comments Dispositions (Contractor) Status/Remarks
3, 6, 1 and 11.
QATAR ENERGY COMMENTS REV. 0:
8. 2 Section-2 of the Submittal: Please include the wind data for Noted and updated in Section 4.01, in report No.
Peak humid month of July, Aug and September 4092_DPS_T3_R1.
1. The comment states that dust ingress might damage the QDC reported observation about existing weather louver
Mechanical equipment inside the room due to non available and proposed sand trap louver in fan room to protect
weather louver. However, rest of the pressurization fan are the new motorized dampers from sand and silt ingress
exposed to outdoor without any enclosure or dust protection. and protect from clogging, thus preventing ambient air
infiltration into staircase and lobby. Weather louver is
assigned with priority 2 (optional) in Section 9 of the
report No. 4092_DPS_T3_R1. A semi-annual
maintenance Plan is proposed for pressurization fan
motorized damper in section 8.01, 8.02 and 8.03 of the
report No. 4092_DPS_T3_R1.
2. The proposed DFCU in the staircase is with heater similar to a Refer to Section 8.01, 8.02, 8.03, 8.07, 8.11-8.16, 8.17
modified dehumidifier. There is difficulty for the source of and 8.23, in report No. 4092_DPS_T3_R1, to stop
chilled water as the building was built without provision for ambient air infiltration in staircase & lobby.
such DFCU in the staircase. The DFCU will not contribute Proposed FCU (chilled water and VRF option) in staircase
positive pressure to counter any leakage of outside air since it is for recirculation of air in the staircase and to maintain
will work only to recirculate the air while removing moisture. temperature above the dew point. The proposed
Please submit another alternative which will not violate QCDD solution does not violate QCDD requirement. Refer to
requirements. Section 8.20a of the report No. 4092_DPS_T3_R1.
Noted.
Section 3. (Project Overview) of the Submittal: Contractor to Detailed drawings will be submitted by design
clarify who will be developing the detail drawings as per the consultant.
current Dew point study outcome, as QDC scope as quoted
Status 10, 2,
S. No. Comments Dispositions (Contractor) Status/Remarks
3, 6, 1 and 11.
Section-3 is limited to Dew-point study
Noted and updated in Section 6.03, in report No.
Section 6 of the submittal: Please also Add Layout of Fans and 4092_DPS_T3_R1.
Show the relative Wind direction in Peak Humid months to
understand the impact of Wind Direction.
Noted and updated in Section 7.19 and 8.19 of the
Section 7.14 of the submittal: A space sensor is more suitable report No. 4092_DPS_T3_R1.
rather than the thermostat in order to provide the setpoint
only from the BMS only. Operation of CAV with space temperature sensor to shut
Currently we are proposing to restore AC to this area via CAV, off dampers is outlined in Section 8.19 of the report No.
QDC to clarify the impact and provide recommendation. 4092_DPS_T3_R1.
Noted.
Section 8 of the submittal: Contractor to confirm the inclusion Confirmed for BMS monitoring of newly installed smoke
of BMS monitoring in their current work execution at site for dampers.
new smoke dampers for Staircase and Lobby fans
Document Reference: 4384-QPD-9-TS-H-0003 Rev. 1 Page 5 of 9
CLIENT CONSULTANT (QRC) PROJECT DETAILS
Project Name: EPIC FOR MISCELLANEOUS IMPROVEMENT 1 AT QPD
Package No.:
Status 10, 2,
S. No. Comments Dispositions (Contractor) Status/Remarks
3, 6, 1 and 11.
Noted.
Section 8.01, 8.02 8.03 of the submittal: Contractor to include Ducts and joints are air-tight which will not allow any
the specific site condition for Ducts, flexibles joints condition exfiltration. Sealant applied is UL approved only.
for air tightness and sealant issue. Site condition of Ducts,
flexibles joints and sealant should be clearly highlighted as part
of this report
QDC reported observation about existing weather louver
Section 8.4 of the submittal: Sand trap louver is proposed in the and proposed sand trap louver in fan room to protect
pressurization fan room, is this really required as Smoke rated the new motorized dampers from sand and silt ingress
dampers are already proposed in the downstream duct of the and protect from clogging, thus preventing ambient air
fans infiltration into staircase and lobby. Weather louver is
assigned with priority 2 (optional) in Section 9 of the
report No. 4092_DPS_T3_R1. A semi-annual
maintenance Plan is proposed for pressurization fan
motorized damper in section 8.01, 8.02 and 8.03 of the
report No. 4092_DPS_T3_R1.
Status 10, 2,
S. No. Comments Dispositions (Contractor) Status/Remarks
3, 6, 1 and 11.
Section 8.09 of the submittal: A space sensor is more suitable 4092_DPS_T3_R1.
rather than the thermostat in order to provide the setpoint
only from the BMS.
Following the proposed remedial measures outlined in
Section 8.10 of the submittal: QDC to elaborate this statement the report, it is proposed to conduct pressure test on the
in Section 8.10, "Pressure test is proposed in each staircase for staircases for infiltration assessment.
assessment of infiltration flow." Refer to Section 8.23, in report No. 4092_DPS_T3_R1.
Section 8.10 of the submittal:
Refer to Note in Section 8.20a of the report No.
1. Please provide the basis of selecting the proposed FCU's 4092_DPS_T3_R1, stating CFD simulation to confirm final
locations in the staircase, A detail design is required for the No. Of FCU’s, location, capacity, and heater sizing.
proposed FCU’s in the staircase including the location,
capacities, heater sizing, temperature set points . A CFD
analysis will be an appropriate guidance to finalize the location,
capacity, heater sizing, temperature set points etc. of the
proposed FCU, Contractor to submit the same ad part of the
current report. Noted.
If CHW FCU strategy is adopted, all details including
2. Further, Strategy/concept for Chilled water Tap-off form schematics /drawings/ drainage/ electrical will be
existing chilled water network to be studied and clarified, provided.
Similarly, Condensate drainage and electrical termination If VRV strategy is adopted, same will follow.
strategy to be included, Options considered for dehumidification includes chilled
3. Other alternative to be studied for cooling/dehumidification water FCU beside VRF system. Refer to Section 8.20a of
of the staircase. the report No. 4092_DPS_T3_R1.
Status 10, 2,
S. No. Comments Dispositions (Contractor) Status/Remarks
3, 6, 1 and 11.
rise and low rise)
1. CFD analysis is not part of the current report, FCU locations respectively. Under these conditions across the shared
and capacities are still not defined and provided as wall there is no risk of condensation.
part of the report. This report shall finalize the proposed FCU
capacity and location.
The detail drawings for the DFCU shall be developed and chilled
water source shall be finalized and defined.
Reviewer Name: Jovienel Q. Tercero, Lead Mechanicl Engineer, QRC Signature: Date: 05/06/2023
Document Reference: 4384-QPD-9-TS-H-0003 Rev. 1 Page 8 of 9
CLIENT CONSULTANT (QRC) PROJECT DETAILS
Project Name: EPIC FOR MISCELLANEOUS IMPROVEMENT 1 AT QPD
Package No.:
Document Status: 10 = Approved 2 = Approved with Comments (Incorporate comments 3 = Not Approved (Incorporate comments and
(Resubmission not and resubmit - work may proceed subject to resubmit - work shall not proceed)
required) incorporation of comments)
6 = For Information 1 = Approved without Comments (Resubmission 11 = Cancellation Accepted
Only required - work may proceed)
Note 1: A unique CDF serial number will be allocated with document initial submission; subsequent revisions will be reflected in CDF revisions (applicable at least by QRC and QP)
Note 2: Originator - QP/ QRC
Note 3: Please encode separate number for each CDF in the footer with revision number