37.)
a.
Maximum Cycle Time = (activity times)
Maximum Cycle Time = 60 minutes
b.
For Maximum Cycle Time:
Daily Output (Max) = Total Daily Time / Maximum Cycle Time
Daily Output (Max) = 480/ 60 minutes
Daily Output (Max) = 8 units/ day
38.)
a. Production rate= Total Daily Time/ Cycle time
Production rate= 480 minutes / 4.5 minutes
Production rate= 106.67 units/day
b. Assembly line Efficiency = (Actual Production Rate/ Maximum production rate) x 100
Assembly line Efficiency = (106.67 units per day / 200 units per day) x 100
Assembly line Efficiency = 53.33 %