Download as pdf or txt
Download as pdf or txt
You are on page 1of 167

5/11/2014

ADVANCED OPEN PIT MINE


PLANNING AND DESIGN

Presenter
Prof Emmanuel Chanda
The University of Adelaide, Australia

ADVANCED OPEN PIT MINE


PLANNING AND DESIGN
M1-Strategic mine planning
M2-Open pit optimisation
M3-Mine Production scheduling
M4-Optimum Cut-off Grades
M5-Mine Planning Software
M6-Mine-to-Mill Optimisation
M7-Equipment Selection
M8-Financial Technical Modelling
 M9-Dewatering and Pumping
Open Pit Mine Planning and Design 2

1
5/11/2014

Objectives

 Fundamentals of open pit mine design and


current developments in planning and design
methodology,
 Current industry practices to maximise economic
return.
 Open pit mine planning and design process in
theory and practice,
 Unit Operations – Drill-Blast-Load-Haul
 Apply this knowledge to plan/evaluate new
open pit projects and/or existing mines.

Open Pit Mine Planning and Design 3

What do you expect to learn from this


Course?

Open Pit Mine Planning and Design 4

2
5/11/2014

Module 1
Strategic Mine Planning
1. What is strategic planning?

2. Mine planning process

3. Mining strategy

4. Feasibility Studies

5. Exercises
Open Pit Mine Planning and Design 5

Overview/scope
• Big picture mine planning and design process

• Big picture decision-making process

• Applies to Greenfields as well operating mines

• SP takes place at all levels of the company


 Corporate level: vision, mission, feasibility, etc
 Business unit level: expansion of production
 Mine level: medium/long term production strategy

 Analogy: military strategy


Open Pit Mine Planning and Design 6

3
5/11/2014

What is Strategic Mine


Planning?
Strategic mine planning is concerned with those
decisions that largely determine the value of the
mining business whereas tactical mine planning
deals with the tasks required to actually achieve
that value.
Both types of planning are necessary; they can be
looked at separately, even discussed separately,
but they cannot be separated in practice!

Open Pit Mine Planning and Design 7

Types of planning and mine life cycle

Tactical Mine
Mine Planning

Planning

Strategic Mine
Planning

Prospecting Exploration Development Production Closure

Life cycle of an orebody

Open Pit Mine Planning and Design 8

4
5/11/2014

Strategic mine planning focuses on those technical


variables that affect the life of a mine and the value of
the underneath mineral resource
It starts with the discovery of the mineral resource and
finishes when it is exhausted or abandoned.

Go! List variables (factors) considered in SMP…

Open Pit Mine Planning and Design 9

Business Strategy

Strategic Decision- Economic


Planning Making Evaluation
Behaviour

Mine Planning

Open Pit Mine Planning and Design 10

5
5/11/2014

Decision-Making Behaviour:
 Risk Averse – seeks other business goals
 Risk Neutral – seeks maximise NPV

Open Pit Mine Planning and Design 11

Mine Planning Process Flowchart

Open Pit Mine Planning and Design 12

6
5/11/2014

Mine Planning Process


Four main stages of mine planning process:
• Geology of resource
• Value of resource
• Long-Term planning (Strategic) – feasibility
studies
• Medium-term/Short-term planning - production

Mine Planning Process*:


Geology + Data Analysis  Resource Model  Mining Method Selection 

Optimisation  Mine Design  Optimal Schedulling  Financial Technical Model

* A dynamic and iterative process *


Open Pit Mine Planning and Design 13

Activity 1:
Work in Groups of 2-4
To plan a new open pit mine in Kerman Province. List all the
data required to perform a feasibility study and where
these data would come from.

Open Pit Mine Planning and Design 14

7
5/11/2014

Technical Aspects:
Once the geological features are understood and the
physical characteristics of the ore body are determined,
the main technical decisions that follow are:
 Mining method selection
 Processing route
 Scale of operation (size)
 Mining sequence
 Selective cut-offs (e.g. cut-off grade at the mine)

Open Pit Mine Planning and Design 15

•All these variables are inextricably interrelated in the


sense that they cannot be determined in isolation from
each other
•Moreover, they cannot be determined without taking
into account the market variables and related data from
the geologic, metallurgical, geotechnical, and
environmental models…….
•……….as shown on next slide…

Open Pit Mine Planning and Design 16

8
5/11/2014

MARKET

Geological Metallurgical
Model Model

Mining Processing
Method Route
Geotechnical Environmental
Model Model
Scale of Mining
Operation Sequence

Selective
Cut-offs

MINE PLAN
Open Pit Mine Planning and Design 17

Mining Method Selection

• The choice of the mining method depends on the


shape, emplacement and properties of the
orebody and host rock; again, beyond technical
considerations, this is an economic decision

• In general, there are two main mining methods:


 Surface mining (open pit, quarries)
 Underground mining (block caving, cut & fill)

Open Pit Mine Planning and Design 18

9
5/11/2014

• However, depending on the emplacement of the


orebody and its grade distribution, there are cases
where both methods are feasible – e.g. open-pit
followed by underground mining or the other way
around
• This is the classic case of sub-vertical deposits such as
kimberlitic pipes containing diamonds and some
porphyry copper deposits

Open Pit Mine Planning and Design 19

Economic considerations

• Many decisions concerning the choice of the mining


method are related to the "opportunity cost” concept

• For example:
 In massive, disseminated deposits that are close to
surface, open pit mining is more productive than an
underground

 Underground mining usually requires more


development and preparation works

Open Pit Mine Planning and Design 20

10
5/11/2014

Considerations in Mining Method Selection


Finances:
• Finance influences method selection:

 Length of pre-production development and phases

 Thoroughness of the ore body delineation program

 Scale of operations – bulk mining methods, eg., block


caving

 Technology applications - automation

Open Pit Mine Planning and Design 21

Markets

 The mining method should be flexible enough to


respond to market changes.

 When and how to high grade during peak commodity


prices

 Changes to mine development schedule

 Focus on production of by-products (eg. cobalt in copper


ore)

 Mining companies are price takers. What can be done


about this?
Open Pit Mine Planning and Design 22

11
5/11/2014

Technology and Human Resources


 Choice of particular mining method commits operation
to certain type of technology, equipment, human
resources and processes.

 Later change in method will be at a cost

 Must allow for possibility of introducing new


technology

 Necessary skills must be available to operate selected


mining system
 Lack of expertise may eliminate a particular mining
method, though technically suitable.

 Consider specific training and supervision


Open Pit Mine Planning and Design 23

Processing route

• The selection of the processing route depends


essentially on the characteristics of the ore; however,
beyond technical considerations, this is a business
decision

• Essentially, there are basically two main routes:


 Physical methods (concentration)
 Chemical methods (hydrometallurgy)

Open Pit Mine Planning and Design 24

12
5/11/2014

Mineral

Liberation Comminution

Unacceptable

Classification

Acceptable

Separation Concentration

Physical Chemical
Open Pit Mine Planning and Design 25

Factors to consider
 Products recovered
 Recoveries and achievable grades
 Environmental aspects
 Market considerations
 Capital and operating costs
 Cycle times
 Mine plan
 Cash flow and profitability

In short, technical and financial considerations


Open Pit Mine Planning and Design 26

13
5/11/2014

Metallurgical tests

• Lab testing – for initial investigation


 Core samples and samples from outcrops
(chip samples)
• Pilot tests – to confirm lab tests and design
 Core samples and some bulk samples from
underground workings
• Industrial tests – to feasibility
 Bulk samples from underground workings
and additional core samples

Open Pit Mine Planning and Design 27

Scale of the operation


• The scale of the operation refers to production
capacity, which in turn is related to the physical size of
the installations at the mine and plants
• This is directly related to the capital investment
required to produce the final output deemed to put in
the market
• The larger the scale, the higher the investment and
production

Case Study: Olympic Dam Expansion Project


in South Australia

Open Pit Mine Planning and Design 28

14
5/11/2014

• From the point of view of a mining project, the


scale of the operation is the dominant factor
for establishing the mine life and business
value
• There is a compromise between the NPV of a
project and its size – the optimum size exits,
because a very large operation may shorten
the mine life too much, making the marginal
investment unworthy

Open Pit Mine Planning and Design 29

Size-profitability-risk relationship
Scenario 500 kt/d
NPV Scenario 300 kt/d
(MUS$) Scenario 150 kt/d

Scenario 72 kt/d 
3000
Risk
2700

2000

1000

Scale of operation
Open Pit Mine Planning and Design 30

15
5/11/2014

Mining Sequence and Final Limits


• It refers to the path or trajectory employed to exploit
a mine – from an initial situation until reaching the
final limits or exhausting the ore reserves

• Usually, these two variables are treated separately


but because of their co-dependency they should be
handled together

Open Pit Mine Planning and Design 31

• The mining sequence is usually defined in


terms of sequential “cuts” or "sectors“ in
which a final mining envelope is split to guide
the mining extraction

• These sectors can be phases, cut-backs or


push-backs as they are usually called in open-
pit mining; or blocks, panels, rooms or stopes
as these are commonly referred to in
underground mining

Open Pit Mine Planning and Design 32

16
5/11/2014

• It is worth noting that the partition of a final


mining envelope into cuts or sectors is done
because the time value of money

• In effect, the purpose is to postpone


expenditures and bring forward revenue as
much as possible from production sales

Open Pit Mine Planning and Design 33

The scheduling “saw graph”

• To illustrate how the time value of money


affects the economics of mining it is useful to
introduce the “saw graph” tool
• It assumes that mining activities always
require some preparation works
(development) prior to ore extraction:
 Stripping in open pit mining (t, m3)
 Developments in underground (m3,
m2, m, t)

Open Pit Mine Planning and Design 34

17
5/11/2014

The scheduling “Saw Graph”

Minimum Ore
Exposure
yr-1 yr-2 yr-3 yr-4 yr-5 yr-6
Time

Open Pit Mine Planning and Design 35

Integral optimisation of the final pit


Exploitation phases
500 t (ore)

100 t (waste)  3

6 Revenue  2.2 $/t


Cost  -1.0 $/t
Open Pit Mine Planning and Design 36

18
5/11/2014

Partial and cumulative tonnage

Partial tonnage Cumulative tonnage


Phase
Ore Waste O/W Ratio Ore Waste O/W Ratio
1 500 100 0.2 500 100 0.2
2 500 300 0.6 1,000 400 0.4
3 500 500 1.0 1,500 900 0.6
4 500 700 1.4 2,000 1,600 0.8
5 500 900 1.8 2,500 2,500 1.0
6 500 1,100 2.2 3,000 3,600 1.2
7 500 1,300 2.6 3,500 4,900 1.4

Breakeven point  Phase 6

Open Pit Mine Planning and Design 37

When neither the time value of money nor other


operational factors such as mine and plant
capacities are taken into account, the optimal final
limit is reached at Phase 6

The implicit assumption is that ore is exposed


simultaneously with waste and that ore revenue
occurs at the same time as waste cost

Open Pit Mine Planning and Design 38

19
5/11/2014

When accepting that ore and waste extraction have to


consider certain physical restrictions in their
programming (phase size and available equipment), then
the time value of money becomes a relevant issue
The programming can be done using the “saw graph”
early described

Open Pit Mine Planning and Design 39

Case 1: Open pit plan with 6 phases


• Plant ≤ 500 t/y
• Mine ≤ 1,300 t/y
500 1 2 3 4 5 6

1 yr-1 yr-2 yr-3 yr-4 yr-5 yr-6 Time


2
500 3

4 Waste removal
1,000 5
6
Open Pit Mine Planning and Design 40

20
5/11/2014

Economic evaluation: Phase 6

+1,250
1,000

0
yr-1 yr-2 yr-3 yr-4 yr-5 yr-6
- 300 Time

- 1,000 - 800
-225 -546 +706

Present value(t=0, r=10%) = - 65

Open Pit Mine Planning and Design 41

Economic evaluation: Phase 5

+1,250
1,000

0
yr-1 yr-2 yr-3 yr-4 yr-5 yr-6
Time
- 400
- 500
- 1,000
-331 -376 +776

Present value(t=0, r=10%) = + 70

Open Pit Mine Planning and Design 42

21
5/11/2014

Case 2: Open pit plan with 5 Phases


• Plant ≤ 500 t/y
• Mine ≤ 1,300 t/y
500 1 2 3 4 5

1 yr-1 yr-2 yr-3 yr-4 yr-5 Time


2
500 3
4

1,000 5

Open Pit Mine Planning and Design 43

Economic evaluation: Phase 5

+1,250
1,000

0
yr-1 yr-2 yr-3 yr-4 yr-5 yr-6
- 100
Time

- 1,000 - 800
-83 -601 +776

Present value (t=0, r=10%) = + 92

Open Pit Mine Planning and Design 44

22
5/11/2014

Economic evaluation

Net Present Value @ r = 10 % ($)


Phase Case 1 (6 Phases) Case 2 (5 Phases)
Partial Cum Partial Cum
1 1,036 1,036 1,036 1,036
2 733 1,769 733 1,769
3 485 2,254 485 2,254
4 250 2,504 275 2,529
5 70 2,574 92 2,621
6 -65 2,509 - -

Open Pit Mine Planning and Design 45

Summary of results

6
Discounted final
limit (Phase 5)
Breakeven final
limit (Phase 6)

Open Pit Mine Planning and Design 46

23
5/11/2014

Considering an underground
alternative

Open Pit Mine Planning and Design 47

2 open pit phases, 4 underground lifts

2
NPV(1)
3
$ 800
4
5
6

(1) Net present value at the beginning of year 1


Open Pit Mine Planning and Design 48

24
5/11/2014

3 open pit phases, 3 underground lifts….

3
NPV(1)
4 $ 450
5
$ 200
6
$ 50

(1) Net present value at the beginning of year 1


Open Pit Mine Planning and Design 49

NPV of underground lifts


+800

500 +450

+200
+50
0
3  6 4  6 5  6 6 Lifts

NPV Lift 3 (t=0, r=10%) = + 350


NPV Lift 4 (t=0, r=10%) = + 250
NPV Lift 5 (t=0, r=10%) = + 150
NPV Lift 6 (t=0, r=10%) = + 50

Open Pit Mine Planning and Design 50

25
5/11/2014

Economic evaluation
(Open Pit vs Underground)

Net Presente Value @ r = 10 % ($)


Phase Case 3 (OP/UG) Case 4 (Optimum)
Partial Cum Partial Cum
1 1,036 1,036 1,036 1,036
2 733 1,769 733 1,769
3 485 2,254 485 2,254
4 275 2,529 275 2,529
5 92 2,621 150 2,679
6 50 2,671 50 2,729

Open Pit Mine Planning and Design 51

Optimum configuration

5
6

Open Pit Mine Planning and Design 52

26
5/11/2014

Summary of evaluations

Net Present Value @ r = 10 % ($)


Phase
Case 1 Case 2 Case 3 Case 4

1 1,036 1,036 1,036 1,036


2 1,769 1,769 1,769 1,769
3 2,254 2,254 2,254 2,254
4 2,504 2,529 2,529 2,529
5 2,574 2,621 2,621 2,679
6 2,509 - 2,671 2,729

Open Pit Mine Planning and Design 53

NPV and Shareholder Value

Firm's Information Case 1 Case 2 Case 3 Case 4

Net present value ($) 2,509 2,621 2,671 2,729


Firm 's net debt ($) 1,000 1,000 1,000 1,000
Firm 's m arket value ($) 1,509 1,621 1,671 1,729
N° Shares 1,500 1,500 1,500 1,500
Share value ($/Sh) 1.01 1.08 1.11 1.15

Open Pit Mine Planning and Design 54

27
5/11/2014

Role Of Feasibility Studies


• Why Feasibility Study

• Scoping Study

• Preliminary Study

• Bankable Feasibility Study

• Risks

Open Pit Mine Planning and Design 55

Origin of the FS
• The Feasibility Study is a development of mine
valuation reports. These had remained almost
invariable from 1900 to 1960’s.
• More complex and larger mining operations in
1960’s and 1970’s required sophisticated studies
and reporting. The FS was developed which:
– Brings together all aspects of an operation into
one study
– Looks at the inter-relationships and tries to solve
any problems
– Aims to determine technical and economic
viability of a project

Open Pit Mine Planning and Design 56

28
5/11/2014

Feasibility Studies
• Demonstrate that the project is economically
viable to the satisfaction of the Board, the
shareholders and all other stakeholders.
• The FS enable the financing of:
– Preliminary earthworks
– Engineering construction
– Infrastructure

Open Pit Mine Planning and Design 57

Feasibility Studies
• Provide a detailed analysis of all the
factors affecting a project’s viability.
• Enable determination of a “go” or “no
go” decision
• Have become an aid in obtaining
financial backing

Open Pit Mine Planning and Design 58

29
5/11/2014

Phases
• Scoping Study
• Pre-Feasibility Study
• Final Feasibility Study

Open Pit Mine Planning and Design 59

Scoping Study
• The Scoping Study is a preliminary investigation into a
project between a back of envelope and a pre-feasibility
study, or an assessment of necessary size, grade of a
target to explore.
• It may also be called a ‘Concept(ual) Study.”

• The study is normally undertaken with limited technical


and other data being available.

• There is high reliance on experience and knowledge of


similar projects and it normally involves a basic level of
literature search.

Open Pit Mine Planning and Design 60

30
5/11/2014

Aim of A Scoping Study


• Provide a document for decision-making.
• Identify key factors that will influence the
overall outcome of the project.
• Identify and briefly assess possible options,
identify risks
• Give an indication of the potential financial
worth of the project

Open Pit Mine Planning and Design 61


MCA – Project Management in Mine Planning and Design

Outcomes of Scoping Study


• The outcomes will depend on the situation of the
particular project and reasons for the study. The
outcomes of a scoping study mayl include:
– Information for decisions regarding the future of
the project.
– Identification of key factors and probably risk
areas, requiring further early investigation.
– Highlighting project activities or aspects which
have the greatest influence (sensitivity) on the
project value or return.
– Highlighting project parameters that require
more accurate measurement or definition.
– A proposed plan to advance, or close, the project
with schedules and estimated costs.
Open Pit Mine Planning and Design 63

31
5/11/2014

Scoping Study- Case Study


A scoping study for the Flying Fox T1 deposit as a stand-alone
underground mine with offsite ore treatment was prepared by
mining consultants Golder Associates Pty Ltd.

Main outcomes of the T1 scoping study were as follows:


• Mineable Resources at 196,000t @ 5.4% Ni*
• Contained nickel in concentrate 10,587 Ni tonnes
• Gross Revenue (after royalties) A$101 million
• Operating costs (mining, site, transport, treatment) A$201/tonne
ore (A$1.70/lb Ni produced)
• Capital costs - Establishment A$6.0 million
- Mine development A$12.8 million
• Undiscounted Net cash flow (before tax and D&A) A$37.2
million

* Note : Mineable Resources do not constitute a JORC compliant


resource or reserve category.
Open Pit Mine Planning and
Design
64

Preliminary Feasibility Study


• Decisions: Abandon project, change or continue?
• Planning: Focus continued investigations on project-
critical areas.
– Justify detailed site investigation and resource
definition.
– Determine the optimum project scope.
– Identify risks opportunities and potential “show
stoppers/fatal flaws”.
• Economic justification: Justify a full feasibility study.
– Help sell the project.
– Obtain private finance.
• Development: Support permitting and stakeholder
liaison

Open Pit Mine Planning and Design 65


MCA – Project Management in Mine Planning and Design

32
5/11/2014

Pre Feasibility – looking at


alternate scenarios
Andean Gold’s Cerro Negro project in Argentina
• Open pit optimization for the Vein Zone was completed using Whittle 4x software
and recovered gold block grades. A US$800/oz gold price was used as the base
case and the remaining inputs are as shown below:

Waste Ore Recovered


Pit Optimization Parameters Pit
Revenue
Factor
Tonnes Tonnes
Recovered
Au (g/t)
Ounces
Strip Ratio
(W:O)
('000) ('000) ('000)
• Bench Angle 85o 1 0.30 9,763.1 2,083.3 5.30 355.0 4.69
5 0.38 11,922.4 2,580.3 4.84 401.3 4.62
• Berm Width 9 metres every 20 metres 10
15
0.48
0.58
14,631.9
15,704.0
3,111.4
3,580.2
4.43
4.06
443.6
467.2
4.70
4.39


20 0.68 16,357.2 3,941.0 3.81 482.6 4.15
Pit Slope 52o overall slope with ramps 25 0.78 16,697.4 4,143.1 3.68 489.8 4.03
28 0.84 16,765.5 4,247.6 3.61 493.0 3.95

• Mining Cost $1.50 per tonne mined 29


30
0.86
0.88
25,403.2
25,370.3
4,547.3
4,581.3
3.56
3.54
520.4
521.2
5.59
5.54


36 1.00 25,725.8 4,750.5 3.45 526.2 5.42
Processing Cost $14.00 per tonne ore 40 1.14 26,977.6 5,016.1 3.31 534.3 5.38
45 1.28 27,120.3 5,110.1 3.26 536.3 5.31

• General & Administrative Cost $3.00 50


55
1.42
1.60
27,163.4
29,865.5
5,199.4
5,363.9
3.22
3.15
537.9
543.6
5.22
5.57
60 1.72 29,983.6 5,422.6 3.12 544.6 5.53
per tonne ore 67 2.00 30,555.8 5,536.6 3.07 546.5 5.52

66
Open Pit Mine Planning and
Design

Pre Feasibility – scheduling


production
Open pit schedule
Oxide
Mix "Ore" Totals Waste
"Ore" Oxide "Ore" Mix "Ore" Totals Strip
Period (000's (000's (000's
(000's (g/t Au) (g/t Au) (g/t Au) Ratio
Tonnes) Tonnes) Tonnes)
Tonnes)
Pre-production 2.4 2.58 2,290.7
Year 1 644.1 3.05 28.2 4.00 672.3 3.09 3,615.3 5.38
Year 2 670.6 3.71 4.7 2.18 675.3 3.7 5,063.0 7.50
Year 3 643.1 4.62 31.7 3.65 674.9 4.58 2,022.2 3.00
Year 4 758.0 4.39 89.3 3.45 847.3 4.29 7,476.7 8.82
Year 5 1,186.7 2.55 163.3 2.76 1,350.0 2.58 7,619.7 5.64
Year 6 279.6 4.39 130.4 2.52 410.0 3.8 2,287.7 5.58
Totals 4182.1 3.59 447.7 2.96 4,629.8 3.53 30,375.3 6.56

Open pit and underground schedule


Vein Zone Eureka Cerro Negro Total
Period
Portable Ore Portable Ore Portable Ore
g/t Au g/t Au g/t Ag g/t Au g/t Ag
000's Tonnes 000's Tonnes 000's Tonnes
Year 1 672.3 3.09 677.7 11.54 242.81 1,350.0 7.33 121.89
Year 2 675.3 3.70 674.7 14.07 258.86 1,350.0 8.88 129.37
Year 3 674.9 4.58 675.1 12.97 203.05 1,350.0 8.77 101.55
Year 4 847.3 4.29 502.7 6.69 120.41 1,350.0 5.18 44.84
Year 5 1,350.0 2.58 1,350.0 2.58 0.00
Year 6 410.0 3.80 410.0 3.80 0.00
Totals 4,629.8 3.53 2,530.2 11.63 212.16 7,160.0 6.39 74.97

67
Open Pit Mine Planning and
Design

33
5/11/2014

Pre Feasibility – things will change


over time
Brisas Gold Mine Venezuela
Key Economic Parameters and Results 2008 2006
Mill Through-Put Range (tonnes per day) 75,000 - 68,000 70,000
Metallugy Recovery
Plant Recovery - Gold 83% 83%
Plant Recovery - Copper 87% 87%
Net Payable Metal - Gold 82% 81%
Net Payable Metal - Copper 83% 83%
Life of Mine Production (payable metals)
Gold (million ounces) 8.35 8.41
Copper (million ounces) 1,156 1,113
Average Annual Production
Gold (ounces) 457,000 456,000
Copper (ounces) 63 60
Mine Life (years) 18.25 18.5

Initial Capital Cost ($million) 2008 2006


$ $
Mine 59.0 76.6
Mill 314.7 241.5
Infrastructure 67.8 65.8
Tailings management facility 38.3 23.8
Owner's Costs 63.4 55.6
Pre-Stripping 16.7 18.3
Indirect Costs (includes EPCM and Camp) 127.6 97.0
Contingency 43.8 59.4
Total Initial Capital $731.3 $638.0
69
Open Pit Mine Planning and
Design

Pre Feasibility – things


will change over time
Base Case Economics 2008 2006
$ $
Metal Prices
Gold per ounce $600 $470
Copper per pound $2.25 $1.80
Cash Operating Cost Per Ore Tonne
Mining and Dewatering $2.68 $2.08
Processing 3.00 2.59
General and Administrative 0.43 0.42
Transport and Freight 0.43 0.34
Smelting and Refining 1.08 1.02
Total cash operating cost per tonne $7.62 $6.45
Cash per Ounce of Gold
Cash Operating Costs $120 $126
Exploitation Tax 22 16
Capital Cost (initial, sustaining and sunk) 135 111
Total Costs (including sunk costs) $277 $253
Total Cost (excluding sunk costs) $268 $245
Pre-Tax
Internal Rate of Return 20.5% 15.4%
Net Present Value (NPV)
@ 0% discount (billions) $2.77 $1.91
@ 5% discount (billions) $1.29 $0.78
70
Open Pit Mine Planning and
Design

34
5/11/2014

(Final) Feasibility Study (FFS)


• The Feasibility Study Report is a decision-making
document based on verified facts and minimum
assumptions (criteria). The report may be used for
several purposes:
– Assemble a comprehensive framework of facts.
– Present a detailed project description.
– Forecast profitability.
– Facilitate partners and/or sources of finance.
– Basis for detailed engineering.

Open Pit Mine Planning and Design 71


MCA – Project Management in Mine Planning and Design

Requirements of a FS to be
bankable

• A FS must be;
– Credible
– Definitive
– Relevant
– Independent

Open Pit Mine Planning and Design 72

35
5/11/2014

Final Feasibility – high level issues


• Geology and ore reserves - size, shape and depth of the ore, the grade of the
ore and distribution, how homogeneous, any major faults or intrusions and
hydrological reports.
• Mining method and schedule – surface, open cut, underground, annual
production rate vs life of mine, phasing of development, envisaged ROM
grade, capital equipment and manning levels required. (High production rate,
high capital expenditure, shorter mine life – what is the optimum?)
• Infrastructure requirements - including ancillary buildings, roads, drainage,
tailings disposal, general arrangement drawings of infrastructure layout.
• Metallurgy/concentrator/washery design – recovery factor, concentrate grade,
product quality.
Recommendations for the process plant including:
Flow diagram
Material and water balances
Equipment list (major items) together with budget quotations
General arrangement plan and elections of process plant to scale
1:100
Electrical system (line diagram)

73
Open Pit Mine Planning and
Design

- high level issues continued


• Infrastructure, water, power, accommodation and environmental issues –
source, capital and operating cost, disposal of tailings.
• Permits – right to mine and discharge waste and make good.
• Construction schedule – timing, how long to first production – the quicker the
better.
• Logistics - of supply materials, equipment and manpower to site including an
investigation of transport modes.
• Identification of strategic decisions required - early ordering of long delivery
items, early starts to opening of negotiations for right-of-way dispensation etc.
• Preliminary programme -for carrying-out the Project.
• Construction cost – minimum expenditure to get the project operating, which
varies depending on type and size of mine. All costs to include transport and
commissioning costs, fees and all management costs except for Client's own
costs.
• Markets and marketing – transport to market (FOB or CIF), price for product
quality sold, secondary processing costs, adequate demand for product.
• Financial analysis – put all of the above together to determine if the project is
financially viable.

74
Open Pit Mine Planning and
Design

36
5/11/2014

Things can go wrong –


Mt Todd gold mine
• Combination of many errors in forecasting can
be fatal for any project.
• Project owner is Pegasus Gold Inc and wrote off
US$353.5 million in November 1997 after
closing down the project.
• This write down of shareholders funds was of
balance sheet items amounting to US$122.6
million of acquisition costs, US$49.4 million of
deferred preproduction and development
expenses and US$181.3 million for property and
equipment.

Rudenno, 2008
Open Pit Mine Planning and Design
75

Case Study – Mt Told Gold


Project
• Commodity price overoptimism resulted in a
forecast gold price of US$385 per ounce,
including a hedging premium above
expected spot prices.
• Spot prices while the project was operating
were about US$315 per ounce and the
hedging premium was small.

MCA - Risk Assessment in Mine Planning and Design

Open Pit Mine Planning and Design


76

37
5/11/2014

Case Study – Mt Told Gold


Project
Forecast Actual Change

Reserves grade 1.07g/tAu 0.96g/tAu -10%


Metallurgical recovery of gold 84% 74% -12%
Throughput per year 8 Mt 6.7 Mt - 16%
Crushing costs $1.36/t $2.49/t +83%
Contract mining $1.00/t $1.15/t +15%
Power costs $0.058/kwh $0.075/kwh +29%
Cyanide usage 0.68kg/t 0.86kg/t +26%
Total cash costs $11.86/t $13.58/t +15%
Cash costs per ounce gold US$287/oz US$415/oz +45%
produced
Gold price US$385 US$315 -18%
Exchange rate, A$1.00=US$ 0.7 0.74 +6%

Open
MCA Pit MineinPlanning
- Risk Assessment and
Mine Planning Design
and Design
77

NATURE & PURPOSE OF


FEASIBILITY STUDIES IN MINING
Your Audience
Type Scoping Preliminary Feasibility

Audience Internal Technical Mixed Professional External

Exploration Business Executives Boards


Development
Joint venture Financiers
Executive
Extracts to stake Investors
holders
Consultants
Their Interests Critical factors Optimum project scope Profitability
Potential Profitability Costs
Cost of next stage Schedule
Risks, etc

Open Pit Mine Planning and Design 78 of 10

38
5/11/2014

Cost Accuracy
Scoping Preliminary Feasibility Project Control
Study Feasibility Study Estimate

Class 1 Class 2 Class 3 Class IV


(+/- 30% - 50%) (+/- 25%) (+/- 10% - 15%) (+/- 5% - 10%)

Order of
magnitude Equipment factor Definitive;
Forced detail estimate
Capacity factor estimate Fall out detail estimate
estimate

Open Pit Mine Planning and Design 79 of 10

Mining is a Business, but risky

Open Pit Mine Planning and Design 80

39
5/11/2014

MINING PROJECT RISKS


ECONOMIC / FINANCIAL
RISKS

TECHNICAL RISKS
OH&S RISKS

POLITICAL
RISKS

Participants discuss these elements of


Risk in Mining Projects.
81
Open Pit Mine Planning and Design

Conclusion
Strategic planning (SP) involves developing a range
of options, carrying out some form of evaluation,
assessing criteria and decision-making.

Open Pit Mine Planning and Design 82

40
5/11/2014

Activity 2:
Individual learning
Refer to worksheet 1 –
Development of a mining strategy: open pit and/or
underground?

Complete the task and discuss the calculations with the


person(s) sitting next to you!

Open Pit Mine Planning and Design 83

Module 2
OPEN PIT OPTIMIZATION
What you will learn:

• Block Values and Cost calculation

• Pit Optimisation techniques

• Pit Optimisation Software

Open Pit Mine Planning and Design 84

41
5/11/2014

Block Grade to Block Value

Dollar Value = Revenue - Costs

0.3%Cu -$1.13/t

Some factors to consider:


• Location of the block relative to the surface – effect on
cost
• Processing costs my depend on rock type

Dollar Value = Revenues - Costs

• Revenues can be calculated from:


– Ore tonnages
– Grades
– Recoveries
– Product price
• Costs can be calculated from:
– Mining cost
– Milling cost
– Overheads

Open Pit Mine Planning and Design 86

42
5/11/2014

A Formula for a Block Value used in Whittle


VALUE
= (METAL*RECOVERY*PRICE - ORE*COSTP) - ROCK*COSTM

Calculate the value of ore block X:

• 200 grams of metal X


• 100 tonnes of rock/ore
• Metallurgical recovery = 97%
• Selling price of metal $10.00 per gram
• Cost of processing $12.00
• Cost of mining $5.00
BV = [200x0.97x10 – 100x12 – 100x5] = $240

Calculating Costs

• Must calculate values for:

– Mining Cost per Tonne Mined


– Processing Cost per Tonne Processed
– Rehabilitation Cost per Tonne of Waste
– Selling Cost per Unit of Product

• Some Time Costs must be included

Open Pit Mine Planning and Design 88

43
5/11/2014

Include
• Any cost which is directly proportional to the tonnes
or units of product:
• Fuel oil
• Wages
• Spare parts
• Explosives
• etc

• Include with the appropriate activity

Open Pit Mine Planning and Design 89

Include
• Time costs which would stop if mining
stopped:
• Site administration
• Site infrastructure maintenance
• Interest on working capital loan
• Fall in resale value of equipment
• Capital replacement
• Truck purchase (long project)

Open Pit Mine Planning and Design 90

44
5/11/2014

What to do with Time Costs


• When mill limited
– Divide annual time cost by annual mill throughput
and add the result to the processing cost
• When mining limited
– Divide annual time cost by annual mining capacity
and add the result to the mining cost
N.B. Even add the mill time costs!
• When selling limited ...

Open Pit Mine Planning and Design 91

Don’t Include
• Time costs which continue whether
you continue mining or not

• Up-front/sunk costs

Open Pit Mine Planning and Design 92

45
5/11/2014

Activity 3:
Individual learning
Refer to worksheet 2 –
Block Values and Cost Calculation

Complete the task and discuss the calculations with the


person(s) sitting next to you!

Open Pit Mine Planning and Design 93

Open Pit Optimisation


Resource Model

Resource
Mine survey
Classification

Resource estimate Dilution &


Measured ore losses
Indicated
Inferred

Diluted Resource Process


Parameters

Beneficiation Economic Operating


factors Parameters Costs

 position in mine
Ore Reserve Model

planning flow Open pit optimisation


and design
Revenue, cost and
slope parameters

sheet Potential Ore Mining production Overburden


Reserve schedule & sub-grade

Reserve Ore Reserve estimate Beneficiation


Classification Proved and Probable product

Open Pit Mine Planning and Design 94

46
5/11/2014

Activity 4 :
Individual learning
Refer to worksheet 3
Pit Optimisation – Task 1

Complete the task and discuss the calculations with the


person(s) sitting next to you!

Open Pit Mine Planning and Design 95

Definition of the Optimal Outline


• Any feasible outline has a Dollar Value. In this context
“feasible” means that it obeys safe slope requirements

•The optimal outline is defined as the one with the highest


dollar value (Profit = Revenue – Costs)

• Nothing can be added to an optimal outline which will


increase the value without breaking the slope constraints.

• Nothing can be removed from an optimal outline which


will increase the value without breaking the slope
constraints.

96 Open Pit Mine Planning and Design

47
5/11/2014

Pit Optimisation Techniques


• Moving/Floating/Dynamic Cone Algorithm

• Lerchs-Grossmann 2-D Dynamic Programming


Algorithm

• LG 3-D Graph Theory Algorithm.

• Network Analysis Algorithm

• Linear Programming (integer programming)

• etc

Open Pit Mine Planning and Design 97

Floating Cone Method


• Position an inverted cone, with the required slopes,
on each block with a positive value

• If the total value of all blocks in the cone is positive,


“mine” those blocks

• Repeat these steps until no cone has a positive


value

• There are two problems

Open Pit Mine Planning and Design 98

48
5/11/2014

Floating Cone Method

Courtesy: Kores Corpration


Open Pit Mine Planning and Design 99

Floating Cone- Mining too little

-30
-80 -80

+100 +100

Open Pit Mine Planning and Design 100

49
5/11/2014

Floating Cone- Mining too much

Open Pit Mine Planning and Design 101

Lerchs-Grossman Algorithm
• Works with block values

• Works with block mining precedence

• Guarantees to find the three-dimensional


outline with the highest possible value

Open Pit Mine Planning and Design 102

50
5/11/2014

Lerchs-Grossman Algorithm
• Works with block values

• Works with block mining precedence

• Guarantees to find the three-dimensional


outline with the highest possible value

Open Pit Mine Planning and Design 103

Lerchs-Grossman Algorithm

Open Pit Mine Planning and Design 104

51
5/11/2014

LG 3d block and graph representation


• Orthogonal set of blocks – 2 basic geometries to represent open
pit
• Arrows point to the blocks that first need to be removed to
access the underlying block (at the base)

Open Pit Mine Planning and Design 105

Final Pit Design – composite plan

Open Pit Mine Planning and Design 106

52
5/11/2014

Activity 5 :
Individual learning
Refer to worksheet 3
Pit Optimisation – Task 2

Follow the example calculation of the LG pit optimisation


algorithm

Open Pit Mine Planning and Design 107

Precautions with the OP algorithms


1) Ascribing costs to blocks
• The algorithms to determine the final pit
limit assume that an economic value can be
assigned to each block

• However, many of the costs are time costs;


it means that assigning them to blocks
requires an assumption about what is the
unitary operation that restricts production
(to express these costs in terms of that
activity)
Open Pit Mine Planning and Design 108

53
5/11/2014

2) Assumption of a breakeven grade


• To calculate the net value of a block one has
to assume a breakeven cut-off grade

• A common assumption is to classify as ore


those blocks with a positive value and waste
those blocks with a negative value. If the
mine is the limiting operation, this misses the
opportunity to create value.

Open Pit Mine Planning and Design 109

3) Time value of money


• There are costs that can not be estimated
without a mining plan. This is the case of waste
material, which has to be placed in a dump and
the cost will depend on the time that this
happens – because of the haul distance

• This can be solved by iterations!

Open Pit Mine Planning and Design 110

54
5/11/2014

4) Blending requirements
• There are cases where blocks should be
blended with others to be classified as
ore. But that again requires a mining plan in
advance.

• This can also be solved by iterations!

Open Pit Mine Planning and Design 111

Major General Mine Design Systems


Fully functional packages (with build-in CAD systems):
• VULCAN
• DATAMINE/CAE
• SURPAC/GEMCOM
• MineSight
• Minex/Gemcom - WHITTLE
• Micromine

CAD overlaying packages:


• AutoCAD
• SurvCADD/Carlson
• LKAB System

Open Pit Mine Planning and Design 112

55
5/11/2014

Data Import

Import
+
3D Borehole
Processing

Open Pit Mine Planning and Design 113

Geological Interpretation

Open Pit Mine Planning and Design 114

56
5/11/2014

Block Model + Grade Assessment

Block Model with Grade

Open Pit Mine Planning and Design 115

Economical Model - Grade


>>> $Value
Au >>> Value
[g/t] $$$

Open Pit Mine Planning and Design 116

57
5/11/2014

Optimisation/Design
Major optimisation programs based on Lerchs-
Grossman algorithm:

• Whittle FX Optimiser (stand alone)

• MineMax Planner (stand alone)

• Pit Optimizer (Vulcan 3D)

• NPV Scheduler (Datamine)

• Pit Optimiser (Surpac)


Open Pit Mine Planning and Design 117

Whittle FX
Strategic Mine Planning Software

Import Block Model Pit by Pit Graph

Constrains:
• Economical
• Geometrical • No access constrains
• Operational • No haul road/ramp
Open Pit Mine Planning and Design 118

58
5/11/2014

Optimal Pit

Open Pit Mine Planning and Design 119

Mine Design

Open Pit Mine Planning and Design 120

59
5/11/2014

Mine Design

 Geomechanics/Geotechnical
 Access constraints
 Equipment selection
 Ventilation network (underground)
 Rehabilitation
 Environmental constraints

Open Pit Mine Planning and Design 121

Final Optimal Pit

Open Pit Mine Planning and Design 122

60
5/11/2014

Final Optimal Pit & Pushbacks

Open Pit Mine Planning and Design 123

Reporting & Evaluation

Open Pit Mine Planning and Design 124

61
5/11/2014

Scheduling

Open Pit Mine Planning and Design 125

The Pushbacks Generation

Open Pit Mine Planning and Design 126

62
5/11/2014

Optimizing Production
Schedules

Open Pit Mine Planning and Design 127 of 26

Optimizing Production Schedules

+ =

Open Pit Mine Planning and Design 128

63
5/11/2014

Activity 6 :
Individual learning
Review the following technical paper:

Chanda, E.K., Spencer, E. (1999). Maximising Resource


Utilisation in Open Pit Design, in Proc. 28th International
Symposium on Computer Applications in the Minerals
Industry, 20-22 October, Colorado School of Mines, pp359-366,
(SME-AIME, Littleton).

1) What is unique about the the approach used by the


authors?
Open Pit Mine Planning and Design 129

waste dump planning

What you will learn:

• Principles of dump design and


• Dump optimisation

Open Pit Mine Planning and Design 130

64
5/11/2014

Why waste dump planning?

• A strip ratio of 10:1, say, implies that for every unit of


ore mined, 10 times of waste rock is mined.
• The waste rock ends up being stored in a waste
dump
• Traditionally little attention has been paid to dump
design and planning, the focus being on planning of
ore extraction
• It has been recognised that dump design and
planning is an integral part of pit design.

Open Pit Mine Planning and Design 131

Rock flow in an open pit mine

Yu (2014)
Open Pit Mine Planning and Design 132

65
5/11/2014

Waste Dump Design


• Two main approaches:

1) Top-down dumps – waste rock is dumped


over an advancing face (angle of repose)
– approx 38o from horizontal. After
dumping is complete . The dump is
reshaped to its intended configuration,
usually using bulldozers.

Open Pit Mine Planning and Design 133 of 10

Waste Dump Design

2) Bottom-up storage – waste rock


is dumped in series of piles ,
and then spread to form a
relatively thin layer. Also known
as paddock dumping.

Open Pit Mine Planning and Design 134 of 10

66
5/11/2014

Waste Dump Design

• Hybrid dumping– whereby top


down used is used to produce
relatively thick layers (10 or 15 m,
say), which are then overlain by
subsequent equally thick layers.
This approach is safer and
requires leas reshaping.

Open Pit Mine Planning and Design 135 of 10

Waste Dump Design

Dump progression with shortest haul first strategy

Open Pit Mine Planning and Design 136 of 10

67
5/11/2014

Waste Dump Design

Dump design considering NAF PAF material (Yu 2013)

Open Pit Mine Planning and Design 137 of 10

Waste Dump
Optimisation- how?
 MINEMAX Software
 Simultaneous pit and waste dump design
 Dump modelled as blocks

 WHITTLE Software
 Dump optimisation as mirror image of open pit
optimisation

 XPAC – Advanced Destination Scheduler) Software


 Module schedules rock placement

Open Pit Mine Planning and Design 138 of 10

68
5/11/2014

Waste Dump Optimisation-


Recent Developments

Integrated modelling of dumping system (Yu 2013)

Open Pit Mine Planning and Design 139 of 10

Module 3
PRODUCTION SCHEDULING
What you will learn:

• Principles of production scheduling

• Scheduling Software

Open Pit Mine Planning and Design 140

69
5/11/2014

Mine Scheduling (definition)


• A mining schedule, which tell us when things
occur, can be constructed by applying
production constraints to the mining
sequence
• Basis for preparing and controlling the
mine’s development and production
• A schedule determines the cash flow ($$$)
associated with mining.

Open Pit Mine Planning and Design 141

Typical Timeline

Year
-2 -1 +1 +2

Pre-production
(Development Production
Construction)

Open Pit Mine Planning and Design 142

70
5/11/2014

Inputs
• The scope of the work to be done from Mining
Layout Designs
• Rates at which this work is normally prepared,
from Key Performance Indicators (KPI)
• Labour working hours and rosters from
Strategic Planning module
• Plant capacities, from the Strategic Planning
modules
• Production schedules, Ore reserves, tonnes and
grades, recoveries and dilutions

Open Pit Mine Planning and Design 143

Types of Mining Schedule


• Production schedules
– Long Term or Life of Mine (10+ years)
– Medium Term (5 years approx.)
– Short Term (3 months – 2 years)
– Extremely Short Term (down to a shift, or for specific jobs)
• Exploration drilling schedules
• Development schedules
• Production drilling schedules
• Equipment schedules
• Labour schedules
• Filling schedules
• Consumable schedules
• Special project schedules
Open Pit Mine Planning and Design 144

71
5/11/2014

Scheduling Packages
• XPAC
• iGannt
• MS Project
• MS Excel
• Whittle 4D
• In-house

Open Pit Mine Planning and Design 145

XPAC
• Developed by Runge Software
• Business focussed mine scheduling application
• Specifically developed for forecasting, reserve
database and mine scheduling management of all
types of mineral deposits and mining methods
• Easy-to-use tools for the adaptation, analysis and
scheduling of mineral resources
• Designed for surface/underground coal mining
• Has limitations in underground mining or in pits with
complex geometries

Open Pit Mine Planning and Design 146

72
5/11/2014

iGantt
• Developed by MineMax

• Tool for open-pit and underground production


scheduling

• Integrates Gantt chart, 3D visualization and


spreadsheet views of a production schedule

• Used for scheduling a single operation or multiple


operations across an enterprise

Open Pit Mine Planning and Design 147

Open Pit Mine Planning and Design 148

73
5/11/2014

Open Pit Mine Planning and Design 149

Open Pit Mine Planning and Design 150

74
5/11/2014

Financial Technical Model


• Plant design
• Infrastructure (road, power, water, village, etc.)
• Equipment selection
• Capitals
• Operating costs
• Royalty
• Tax
• Revenue
• …
• NCF  NPV, IRR, PB, etc.

Open Pit Mine Planning and Design 151

Activity 8 :
Individual learning
Refer to worksheet 4
Production Scheduling

Calculate the monthly production figures for a small gold


mine

Open Pit Mine Planning and Design 152

75
5/11/2014

Module 4
Cut-off grade optimization
1. Background
2. The model
3. Example 1: an hypothetical case
4. Example 2: a copper open pit mine
& mill
5. Conclusions
6. References

Open Pit Mine Planning and Design 153

1. Background

• This model was developed in the early


1960s by Ken Lane, a mathematician who
made his professional career in the Rio
Tinto Group

• At the time, the model was used in various


mines of Rio Tinto – including Palabora
mine in South Africa, and Bougainville
mine in PNG.
Open Pit Mine Planning and Design 154

76
5/11/2014

2. The model
Final product

Concentrates Qr
Ore

Qc
R
C
Cut-off gx
Slag
Qm Tailings

Waste

M
Open Pit Mine Planning and Design 155

Variables used in Lane’s Model

M = Mine capacity per period (t of material)


C= Plant capacity per period (t of ore)
R= Refinery capacity per period (t of product)
Qm = Quantity of run-of-mine material (t of material)
Qc = Quantity of ore (t of ore)
Qr = Quantity of final product (t of product) = Qc·g·y
T= Time to mine, process or refine Qm
P= Profit

Open Pit Mine Planning and Design 156

77
5/11/2014

Model’s variables (cont’)

d= annual discount rate


m= mining costs ($/t of material)
c= concentrating costs ($/t of ore)
r= refining and marketing costs ($/t of product)
f= fixed costs, per period ($/period)
s= selling price ($/t of final product)
y= overall metallurgical recovery

Open Pit Mine Planning and Design 157

The profit equation for Qm

P  s - r  Qr  c  Qc  m  Qm  f  T (1)

As Q r  Q c· g · y

P  s - r  g  y  c  Qc  m  Qm  f  T (1a)

Open Pit Mine Planning and Design 158

78
5/11/2014

Profit from Qm and Present Value


f

Qm
Qc

V
W
gx Grade

V = Present value at the beginning of period T


W= Remaining present value after mining Qm

Open Pit Mine Planning and Design 159

P P2 P3 P4 Pn

••••••

0 Time
W

PW
V (2)
(1  d)T
Open Pit Mine Planning and Design 160

79
5/11/2014

If time T is small:

(1 + d)T  1 + d·T (3)

Replacing in (2):
PW
V (4)
(1  d  T)
Re-arranging:

V·(1 + d·T) = P + W (5)

Open Pit Mine Planning and Design 161

Re-arranging:

v = V - W = P - d·V·T (6)

Where v is the contribution that the


fraction Qm of the ore deposit makes to
the present value of the business

As such, v is the variable to maximise


when choosing the optimum cut-off
grade
Open Pit Mine Planning and Design 162

80
5/11/2014

Replacing (1) in (6):


v  s  r  Qr  c  Qc  m  Qm  f  d  V  T (7)

But the optimum present value V on the


right side of equation (7) is unknown
until the cut-off grade policy is optimised

This “chicken and egg problem” is solved


by iterations, using an arbitrary value of
V in the first iteration and stoping when V
converges
Open Pit Mine Planning and Design 163

Economic cut-off grades

v  s  r  Qr  c  Qc  m  Qm  f  d  V  T (7)
In equation (7), time T depends on the
stage that limits the pace at which ore is
mined

That is, the quantities Qm, Qc or Qr and


their respective capacities M, C, or R

This leads to three economic cut-off


grades:
Open Pit Mine Planning and Design 164

81
5/11/2014

a) When the mine imposes a limit (M)

Qm
In this case, T
M

Replacing this in expression (7):

 m  f  d  V 
v m  s  r   Qr  c  Q c     Qm
 M

Max vm  v m
0
g

Open Pit Mine Planning and Design 165

As Qm is given, g only affects Qc and Qr

Then g must be chosen to make (s-r)·Qr - c·Qc


as large as possible

s - r  Qc  g  y  c  Qc
Therefore:
c
gm 
s  r   y
Open Pit Mine Planning and Design 166

82
5/11/2014

b) When the plant imposes a limit (M)

Qc
In this case, T
C

Replacing this in expression (7):

 f  d V 
v c  s  r   Qr  c   Q c  m  Qm
 C 

Max vc  v c
0
g

Open Pit Mine Planning and Design 167

In the same way, as Qm is given, g must be


chosen to maximise:

s - r  Qc  g  y  c  f  d  V   Qc
 C 

Therefore:
c
f  d  V 
gc  C
s  r   y

Open Pit Mine Planning and Design 168

83
5/11/2014

c) When the refinery imposes a limit (R)

Qr
In this case, T
R

Replacing this in expression (7):


v r  s  r 
f  d  V   Q  c  Q  m  Q
 R  r c m

Max vr  v r
0
g

Open Pit Mine Planning and Design 169

In the same way, as Qm is given, g


must be chosen to maximise:

s  r 
f  d  V   Q  g  y  c  Q
 R  c c

Therefore:
c
gr 

s  r 
f  d  V    y

 R 

Open Pit Mine Planning and Design 170

84
5/11/2014

Balancing cut-off grades


The operation is sometimes limited by two or
eventually three stages simultaneously

Then, three balancing cut-off grades can be


introduced into the analysis

gmc: Mine-Plant
gmr: Mine-Refinery
grc : Refinery-Plant

Open Pit Mine Planning and Design 171

Mine-mill example
f
Qm

gm gmc gc Grade

gmc fully utilises mine and mill capacities;


that is, maximum stripping ratio at the mine
and throughput at the mill

Open Pit Mine Planning and Design 172

85
5/11/2014

Mine capacity: 650,000 t/d


Mill capacity: 150,000 t/d
gm: 0.25 %Cu
gc: 0.65 %Cu
Possible throughputs:
Cut-off Mine Mill Grade
% Cu t/d t/d % Cu

0.25 450,000 150,000 0.9


0.50 650,000 150,000 1.2
0.65 650,000 120,000 1.3

0.5 %Cu is a balancing cut-off

Open Pit Mine Planning and Design 173

In summary, Lane’s model considers six


cut-off grades:
• three economic cut-off grades, and
• three balancing cut-off grades
The former depend on economic factors
and capacities whereas the latter are
determined by the grade distribution that
can vary widely throughout irregular ore
bodies
None of these considers mining costs!
Open Pit Mine Planning and Design 174

86
5/11/2014

Optimum cut-off grades

The overall optimum is one of the six cut-


off grades already defined:
1) gm
2) gc
3) gr
4) gmc
5) gmr
6) grc

To assess which one is the optimum it is


best to consider each pair of stages in
turn
Open Pit Mine Planning and Design 175

To see which one is the optimum it is best


to plot the value functions considering
each pair of stages in turn

Mine-Concentrator

 m  f  d  V 
v m  s  r   Qr  c  Q c     Qm
 M

 f  d V 
v c  s  r   Qr  c   Q c  m  Qm
 C 

Open Pit Mine Planning and Design 176

87
5/11/2014

Gmc = gmc
vm vc

gm gmc gc g

Gmc = gm
vm vc

gmc gm gc g

Open Pit Mine Planning and Design 177

Gmc = gc

vm vc

gm gc gmc g

In a similar way, by considering the other


pair of stages, it is possible to obtain Gmr
and Grc

Open Pit Mine Planning and Design 178

88
5/11/2014

The overall optimum cut-off grade is:

G = Middle value (Gmc,Gmr,Grc)

vr

vm vc

gm grc gmr gmc gc gr g

Open Pit Mine Planning and Design 179

3. Example 1: an hypothetical case


• Mine capacity (M) = 100
• Plant capacity (C) = 50
• Refinery capacity (R) = 40
• Mining costs (m) =1
• Concentrating costs (c)= 2
• Refining costs (r) =5
• Fixed costs (f) = 300
• Selling price (s) = 25
• Overall recovery (y) = 100 %
• Annual discount rate (d)= 15 %

Open Pit Mine Planning and Design 180

89
5/11/2014

Grade-tonne relationship
f(t)

Grade
Quantity
interval
0.0 – 0.1 100
0.1 – 0.2 100
0.2 – 0.3 100 100

. .
.
0.9 – 1.0 100
 1000

0 0.5 1.0 g

Open Pit Mine Planning and Design 181

Balancing cut-off grades


Tonnage Ratios
Cut-off
Mine Mill Grade Ref. M/C M/R C/R
0.0 1000 1000 0.50 500 1.00 2.00 2.00
0.1 1000 900 0.55 495 1.11 2.02 1.82
0.2 1000 800 0.60 480 1.25 2.08 1.66
0.3 1000 700 0.65 455 1.43 2.20 1.54
0.4 1000 600 0.70 420 1.67 2.38 1.43
0.5 1000 500 0.75 375 2.00 2.67 1.33
0.6 1000 400 0.80 320 2.50 3.13 1.25
0.7 1000 300 0.85 255 3.33 3.92 1.18
0.8 1000 200 0.90 180 5.00 5.56 1.11
0.9 1000 100 0.95 95 10.00 10.53 1.05

M/C = 100/50 = 2.00  gmc = 0.50


Balancing
M/R = 100/40 = 2.50  gmr = 0.45 cut-off grades
C/R = 50/40 = 1.25  grc = 0.60

Open Pit Mine Planning and Design 182

90
5/11/2014

Economic cut-off grades


c
gm   0.10
s  r   y

c
f  d  V  For V = 0
gc  C  0.40
s  r   y
c
gr   0.16

s r 
f  d  V 
y

 R 

Open Pit Mine Planning and Design 183

Optimum cut-off grades

Gmc = Mid (0.10, 0.40, 0.50) = 0.40

Gmr = Mid (0.10, 0.16, 0.45) = 0.16

Grc = Mid (0.16, 0.40, 0.60) = 0.40

G = Mid (0.16, 0.40, 0.40) = 0.40

Open Pit Mine Planning and Design 184

91
5/11/2014

Intermediate mine plan


Year Cut-off Mine Mill Ref. Profit
1 0.4 83.3 50 35 216.7
2 0.4 83.3 50 35 216.7
. . . . . .
. . . . . .
. . . . . .
12 0.4 83.3 50 35 216.7

P = (25 - 5)·35 – 2·50 – 1·83.3 – 300·1

P = 216.7
PV@12y and 15% = 1174

Open Pit Mine Planning and Design 185

Second iteration
c
gm   0.10
s  r   y

c
f
 d  V For V = 1174
gc  C  0.58
s  r   y
c
gr   0.25

s r 
f  d  V 
y

 R 

Open Pit Mine Planning and Design 186

92
5/11/2014

Optimum cut-off grades

Gmc = Mid (0.10, 0.50, 0.58) = 0.50

Gmr = Mid (0.10, 0.25, 0.45) = 0.25

Grc = Mid (0.25, 0.58, 0.60) = 0.58

G = Mid (0.25, 0.50, 0.58) = 0.50

Open Pit Mine Planning and Design 187

A new mine plan...

• With the new cut-off grade of 0.5, a new


mine plan can be developed but this time
changing the present value from year to year
• If annual profits are discounted to time 0 and
added up, it gives another estimate of V
• If the difference of the initial and final value
of V exceeds a defined tolerance threshold,
the whole process is repeated

Open Pit Mine Planning and Design 188

93
5/11/2014

Annual profit for the first year...

For a 0.5 cut-off grade, the annual profit and


present value is as follow:

P = (25 - 5)·37.5 – 2·50 – 1·100 – 300·1


P = 250
PV@ 10y and 15% = 1255

Open Pit Mine Planning and Design 189

Optimum mine plan and cut-off grades policy


Year Cut-off Mine Mill Ref. Profit PV
1 0.50 100 50 37.5 250 1255
2 0.50 100 50 37.5 250 1194*
3 0.50 100 50 37.5 250 1123
4 0.50 100 50 37.5 250 1041
5 0.50 100 50 37.5 250 947
6 0.50 100 50 37.5 250 840
7 0.50 100 50 37.5 250 716
8 0.49 97 50 37.1 245 573
9 0.46 93 50 36.5 238 414
10 0.41 89 50 35.9 229 238
11 0.41 21 13 8.8 55 45

 1000  513  380.8  2517

PV @ 11y and 15%= 1256


* W = V·(1+d) - P
W = 1255 · 1.15 – 250 = 1194
Open Pit Mine Planning and Design 190

94
5/11/2014

4. Example 2: a copper open pit mine & mill


Relevant data:
• Mine capacity (M) = 18.9 Mt/a
• Plant capacity (C) = 7.2 Mt/a
• Mining costs (m) = 0.85 $/t material
• Milling costs (c) = 3.7 $/t ore
• Fixed costs (f) = 3.5 M$/a
• Copper price (s) = 2205 $/t Cu ($1.0 /lb)
• TC/RC & selling cost (r) = 705 $/t Cu ($0.32 /lb)
• Overall recovery (y) = 85 %
• Annual discount rate (d) = 10 %

Open Pit Mine Planning and Design 191

A set of four pushbacks

Open Pit Mine Planning and Design 192

95
5/11/2014

Input to the model: four scheduled, nested pits


(periods) from a preliminary mine plan

PP 1
1
3

1
3
2 4

Open Pit Mine Planning and Design 193

Grade-tonnage relationship for the four pits


Cut-off Period 1 Period 2 Period 3 Period 4
% Cu Mt % Cu Mt % Cu Mt % Cu Mt % Cu
0.0 20.3 1.05 36.5 0.79 56.3 0.57 80.1 0.59
0.2 18.7 1.13 30.1 0.92 40.8 0.76 60.4 0.77
0.4 15.3 1.32 24.4 1.08 28.5 0.97 50.2 0.87
0.6 12.9 1.47 19.7 1.22 21.7 1.11 38.3 0.98
0.8 11.0 1.61 13.7 1.45 15.1 1.30 22.7 1.18
1.0 8.6 1.80 10.2 1.64 10.0 1.49 14.6 1.35
1.2 7.1 1.95 7.6 1.83 6.9 1.67 9.0 1.49
1.4 5.9 2.08 5.6 2.02 4.4 1.88 5.0 1.65
1.6 4.4 2.27 4.0 2.24 2.7 2.11 2.9 1.75

Open Pit Mine Planning and Design 194

96
5/11/2014

Output for a “Base case”


Cut-off Mine Mill Ratio Profit PV
Year Period 1
(% Cu) (Mt) (Mt) (% Cu) (W/O) (M$) (M$)

1 1 0.85 14.2 7.2 1.67 0.97 110.3 475.5


2 1 0.78 6.1 3.4 1.59 0.82 49.6 412.8
2 2 0.78 9.8 3.8 1.43 1.56 44.8 412.8
3 2 0.72 16.8 7.2 1.37 1.34 81.3 359.6
4 2 0.67 9.9 4.7 1.31 1.13 50.4 314.2
4 3 0.61 6.7 2.5 1.12 1.62 19.4 314.2
5 3 0.61 18.9 7.2 1.12 1.62 56.3 275.8
6 3 0.60 18.6 7.2 1.11 1.58 55.8 247.0
7 3 0.56 12.1 4.9 1.08 1.45 36.5 215.9
7 4 0.56 4.5 2.3 0.96 0.98 14.9 215.9
8 4 0.53 13.6 7.2 0.94 0.89 44.5 186.1
9 4 0.50 13.1 7.2 0.92 0.82 43.3 160.3
10 4 0.47 12.6 7.2 0.91 0.75 42.4 132.9
11 4 0.44 12.1 7.2 0.89 0.68 41.4 103.9
12 4 0.41 11.6 7.2 0.87 0.61 40.2 72.9
13 4 0.37 11.2 7.2 0.86 0.55 38.9 39.9
14 4 0.33 1.5 1.0 0.84 0.50 5.1 5.0

 193.2  94.6  1.11  1.04 PV = 475.5


Open Pit Mine Planning and Design 195

Output for an expanded case (Mill from 7.2 to 9.0 Mt/a)


Cut-off Mine Mill Ratio Profit PV
Year Period 1
(% Cu) (Mt) (Mt) (% Cu) (W/O) (M$) (M$)

1 1 0.78 16.3 9.0 1.59 0.81 131.8 521.2


2 1 0.71 4.0 2.3 1.53 0.71 33.1 441.6
2 2 0.67 14.0 6.7 1.30 1.10 71.3 441.6
3 2 0.65 18.5 9.0 1.29 1.05 95.4 381.3
4 2 0.60 4.1 2.2 1.22 0.86 22.1 324.0
4 3 0.45 14.2 6.8 1.00 1.10 46.6 324.0
5 3 0.45 18.9 9.0 1.00 1.10 62.0 287.7
6 3 0.45 18.9 9.0 1.00 1.10 62.0 254.4
7 3 0.45 4.2 2.0 1.00 1.10 13.7 217.9
7 4 0.51 12.9 7.0 0.93 0.84 43.2 217.9
8 4 0.48 15.9 9.0 0.91 0.76 54.1 182.8
9 4 0.45 15.2 9.0 0.89 0.69 52.9 146.9
10 4 0.42 14.6 9.0 0.88 0.62 51.5 108.8
11 4 0.38 14.1 9.0 0.86 0.56 50.0 68.1
12 4 0.34 7.4 4.9 0.84 0.51 26.4 25.0

 193.2  103.9  1.06  0.86 PV = 521.2

Open Pit Mine Planning and Design 196

97
5/11/2014

Conclusion for this case


The “Base Case” produces a declining cut-off
grade policy starting at 0.85 %Cu and yielding
a PV of $ 475.5 million
The “Expanded Case” lowers the initial cut-off
from 0.85 to 0.78 %Cu and increases the PV
by $46 million – from $475.5 to $521.2 million
If the expansion capital investment is less than
$46 million, then it is worth going ahead

Open Pit Mine Planning and Design 197

5. Concluding remarks
Lane’s cut-off grade model is a first attempt to
define economically what material is ore in a
life-of-mine (LOM) plan
It requires a holistic view of mining in that the
optimisation needs a preliminary LOM plan.
That is, a final pit limit, pushbacks design and
scheduling based on a breakeven cut-off - the
mine or plant cut-off grade, for instance

Open Pit Mine Planning and Design 198

98
5/11/2014

Activity 8 :
Individual learning
Refer to worksheet 5
Cutoff Grade Optimisation

Follow the calculations to the problems

Open Pit Mine Planning and Design 199

Lane’s model considers various variables as


fixed input – capacities, and downstream cut-
offs such as metallurgical recovery at the mill
Most recent developments have expanded the
model to include some of these variables and
handle them simultaneously
When the problem becomes too complex, it is
solved using other mathematical tools, integer
linear programming being one of them

Open Pit Mine Planning and Design 200

99
5/11/2014

6. References
Kenneth F. Lane - The economic definition of ore, Mining
Journal Books, London 1988
Kenneth F. Lane - Choosing the optimum cut-off grade,
Colorado School of Mines Quarterly. Vol. 59-4, 1964, pp. 811-
829
Blackwell, M. Some aspects of the evaluation and planning of
the Bougainville copper project, Decision-Making in the
Mineral Industry, CIM Special Vol 12, 1971 pp. 261-269

Open Pit Mine Planning and Design 201

Module 5
Mine Planning Software

• Software Packages
• Categories
• Capabilities
• Providers

Open Pit Mine Planning and Design


202

100
5/11/2014

Common Software Packages

Open Pit Mine Planning and Design


203

Categories of Mining Software

Open Pit Mine Planning and Design


204

101
5/11/2014

Mapping Software

Open Pit Mine Planning and Design


205

Geological & Data managent

Source: (Sable, 2013)


Open Pit Mine Planning and Design
206

102
5/11/2014

Geological Modelling/
Resource Estimation

Drill hole display (Source: Geovia, SUPARC)

Open Pit Mine Planning and Design


207

Geological Modelling/
Resource Estimation

Ore body model(Source: CAE, STUDIO 3)

Open Pit Mine Planning and Design


208

103
5/11/2014

Mine Design

Pit Design (Source: Maptek, VULCAN)

Open Pit Mine Planning and Design


209

Planning and Scheduling

Pit Design (Source: Geovia, MineSched)

Open Pit Mine Planning and Design


210

104
5/11/2014

Financial Evaluation

Financial Analysis Software


(RungePincockMinarco)

Open Pit Mine Planning and Design


211

Optimisation/Risk Analysis

Pit Optimisation (Geovia, WHITTLE)

Open Pit Mine Planning and Design


212

105
5/11/2014

Monitoring & Control

Truck Dispatching (Modular Mining System; (DISPATCH)


Open Pit Mine Planning and Design
213

Simulators

Coal Mining Simulator (Immersive Technologies)


Open Pit Mine Planning and Design
214

106
5/11/2014

Virtual Reality

ViMine VR Software – 3D Ore body model


Open Pit Mine Planning and Design
215

Summary

• Advances in Computer technology has


made it possible to model complex mining
environments
• Most widely software is for Mine Design &
Planning
• Further developments in simulation and
risk modelling
• Mining software harmonisation by
suppliers

Open Pit Mine Planning and Design


216

107
5/11/2014

Module 6
mine to mill optimisation
• Concept embraced and practiced by mining
companies
• The philosophy is base on:
 Characterise
 Track
 Measure
 Model
• Potential to save mining companies thousands of
Dollars

Open Pit Mine Planning and Design


217

Mine production system processes

• Drilling
• Blasting
• Loading
• Hauling
• Milling (Crushing, grinding)

 Examine total “system” with regard to cost,


productivity, product quality, optimisation...

Open Pit Mine Planning and Design 218

108
5/11/2014

• Loading: increased fragmentation => higher rate of


shovel productivity, hence lower costs per BCM.
• Hauling: Truck production per hour will increase with
greater fragmentation due to faster shovel loading rates.
Reduced cycle time.
• Crushing: Lower crushing costs result from increased
fragmentation as more material pass through as under
size.
• Drilling and blasting costs are harder to relate to
fragmentation).

Open Pit Mine Planning and Design 219

Optimum Fragmentation Curves

• Unit costs as a function of the degree of


fragmentation
• Systems optimisation:

Overall Cost Curve

Degree of fragmentation

Open Pit Mine Planning and Design 220

109
5/11/2014

Exploration Drilling
Intact rock data
Crushing/grinding
Mineralogy data
Energy data Ore body modeling and
Bond's Work Index Fracture frequency data pit design
Settings

Hauling Blasthole Drilling


Payload data Bore diameter
Voids ratio* Hole deviation monitor
LCM Process Geophysical data
TKPM rating
Autonomy Optimization Real time drilling data
Routing data
Blast design,
Excavation/Loading
Load-Haul
Digability* S01U264007
Blast Design
Dig rate* 120

100 Pattern layout


Dipper design 80

60
S01U264007
35.2Mtpa ROM Target
VOID
Power consumption 40

20 Powder factor
Swing analysis 0
1 10
Size (mm)
100 1000

Explosive
Autonomy

Muckpile properties
Blast Modelling
Size distribution*
Displacement model
Voids ratio*
Fly rock
LCM
Heave mechanics
Visualization
Density

Optimum Fragmentation
• Examine individual components and the whole system
• Goal: “achieving a prescribed level of fragmentation at
minimum cost”
• In-situ ore with particle size considered to be very large
and reducing to size in the order microns (eg -80 mesh).
• Measuring Fragmentation, how?
 Diggability (BCM/HR)

 Size distribution of muckpile (WIPFrag Software),


Split-Desktop software
 Photographs are taken from muck pile, digging
face, moving truck, etc.
Open Pit Mine Planning and Design 222

110
5/11/2014

Drilling and Blasting SubSystem

Fragmentation evaluation
• Measurement of parameters- correlate with
fragmentation
 Photographs are taken from muck pile, digging face,
moving truck, etc.
 Crusher monitoring - energy, feed, product size,
throuputghput
 Shovel monitoring- load, wait, down time, swing, power

Open Pit Mine Planning and Design 223

Case Study

Open Pit Mine Planning and Design 224

111
5/11/2014

Case Study
Modeling Muck Pile Fragment Size to Optimize
Excavator Productivity in Open Pit Mining

Prominent Hill Copper Mine, South Australia

Open Pit Mine Planning and Design 225

Prominent Hill

Open Pit Mine Planning and Design 226

112
5/11/2014

Prominent Hill

Muckpile Image Analysis using SPLIT DESKTOP:

• The split desktop system uses digital image


analysis technology to convert an image
captured from a digital camera to a distribution
of defined areas within the photograph.

• The software was developed from a system of


manual image analysis where a photographic
image was manually delineated and the diameter
of each particle measured

Open Pit Mine Planning and Design 227

Prominent Hill

Camera

Photo of muckpile

Photo collection and scale placement on flitch face.

Open Pit Mine Planning and Design 228

113
5/11/2014

Prominent Hill

Blast master 10040RL


Open Pit Mine Planning and Design 229

Prominent Hill

Open Pit Mine Planning and Design 230

114
5/11/2014

Prominent Hill

Open Pit Mine Planning and Design 231

Prominent Hill

• Our modelling of the excavator production rates


has suggested that P80 of 800 mm would be the
optimal size to maximise excavator productivity
at 6300 t/hr.

• However due to mine machinery and crusher


constraints we believe a revised figure of 600
mm would be more appropriate

Open Pit Mine Planning and Design 232

115
5/11/2014

Module 7
Equipment Selection
• Simulation modelling using GPSS/H – Case Study

• Cost Estimation (Capital & Operating)

Open Pit Mine Planning and Design


233

Simulation and Animation of an


Australian Surface Mine
• Study Background
• Methodology
• Results
• Discussion
• Conclusion
• Recommendations

Open Pit Mine Planning and Design 234

116
5/11/2014

Wilcherry Hill Iron Ore Mine


• The Wilcherry Hill project is
located 30 km north of the
township of Kimba in South
Australia.
• The Wilcherry Hill project
comprises of four tenements
and covers an area of 976
square kilometres.
• The tenements are EL4162-
Wilcherry Hill, EL4286-Valley
Dam, EL4421- Peterlumbo,
EL3981-Eurilla Dam.

Open Pit Mine Planning and Design 235

Project Development
• Development at Wilcherry Hill is proposed in three
phases; stage 1, 2 and 3.

• Stage 1 will be the focus of this project

• Comprises mining, crushing and export of Direct


Shipping Ore (DSO)

• Ore sourced from the upper parts of the mining pits.

Open Pit Mine Planning and Design 236

117
5/11/2014

Methodology
Aim
• Simulation and animation model using the Stage
1 layout of the mine
• Determine the optimum number of shovels and
trucks required for this mining scenario
• Provide the company with a model they can use
for many “what if?” scenarios.

Open Pit Mine Planning and Design 237

Programming in GPSS/H
• Approximately 1,200 lines of computer code were
used to model this mining scenario

• Over 60,000 command lines were used to generate


this animation

Open Pit Mine Planning and Design 238

118
5/11/2014

Methodology
GPSS/H Simulation Main Commands

Open Pit Mine Planning and Design 239

Methodology
Variables, User Information and Generate
• Variables:
REAL &X,&Y,&Z,&A,&B,&C,&D,&E,&F,&G,&H,&I

• User Information:
PUTSTRING (' ')
PUTSTRING ('HOW MANY TRUCKS?')
PUTSTRING (' ')
INTEGER &TRUCKS
GETLIST &TRUCKS

• Generate:
GENERATE 3,,0,&TRUCKS,,12PH,12PL

Open Pit Mine Planning and Design 240

119
5/11/2014

Methodology

Animation

Open Pit Mine Planning and Design 241

Methodology
Mine Layout (Draw, Class and Paths)

Open Pit Mine Planning and Design 242

120
5/11/2014

Methodology

Run

Open Pit Mine Planning and Design 243

Methodology

Animation

Open Pit Mine Planning and Design 244

121
5/11/2014

Methodology
Animation

Open Pit Mine Planning and Design 245

Results

Assumptions

HD 785
EMPTY: 72 t
LOADED: 164 t
LOADED SF: 147.6 t
ORE WEIGHT: 75.6 t
STRUCK BODY CAPACITY: 40 m3
ORE SPECIFIC GRAVITY: 4
FULL STRUCK LOAD ORE WEIGHT: 160 t
HOURS PER SHIFT: 8

Open Pit Mine Planning and Design 246

122
5/11/2014

Results

Ore Results

TRUCKS: 3 4 5 6 7
ORE DUMPS PER SHIFT: 9 13 17 20 23 DUMPS
STOCKPILE DEPOSITION PER SHIFT: 1440 2080 2720 3200 3680 T
STOCKPILE WITHDRAWAL RATE: 180 260 340 400 460 T/HR
COMPARISON (IRONCLAD): 291 T/HR

Open Pit Mine Planning and Design 247

Results

Ore Results

Open Pit Mine Planning and Design 248

123
5/11/2014

Results

Waste Results

TRUCKS: 3 4 5 6 7
WASTE DUMPS PER SHIFT: 68 87 104 123 142 DUMPS
DUMP DEPOSITION PER SHIFT: 5140.8 6577.2 7862.4 9298.8 10735.2 T
DUMP RATE: 642.6 822.15 982.8 1162.35 1341.9 T/HR
COMPARISON (IRONCLAD): 885 T/HR

Open Pit Mine Planning and Design 249

Results

Waste Results

Open Pit Mine Planning and Design 250

124
5/11/2014

Conclusion

• GPSS/H Simulation and Animation


– Number of shovels: one shovel
– Number of trucks: five trucks and possibly an
extra standby truck

• TALPAC simulations
– Number of shovels: one shovel
– Number of trucks: six trucks
Open Pit Mine Planning and Design 251

Acknowledgements
Postgraduate Students:
• Sophie Mellor
• Jian Liu

Open Pit Mine Planning and Design 252

125
5/11/2014

Cost Estimation

• Capital Costs

• Operating Costs

Capital cost estimation: general


considerations
• Indicative capital cost estimates
– Based on empirical data from other
projects
– Estimates are within +/- 30% accuracy
– Suitable for scoping or pre-feasibility
studies
– Often use “rules-of-thumb” to estimate
costs

Open Pit Mine Planning and


254 of 10
Design

126
5/11/2014

Capital cost estimation: general


considerations:
• Indicative capital cost estimates (cont.)
– The sixth-tenths rule (Mular, 1978):
• Cost 1 / Cost 2 = (Capacity 1 / Capacity 2)0.6
• Capacity 2 and Cost 2 relate to a known similar
operation in a similar environment
• Capacity 1 relates to the operation being
studied
• Cost 1 is then estimated
– Annualised cost per tonne rule:
• Annualised cost per tonne of a known operation
= {Total capital cost} ÷ {tonnes per year}
• Use this factor directly to estimate capex for
another, similar operation.
Open Pit Mine Planning and Design 255

Capital cost estimation: general


considerations
• Cost indices
– Most cost estimations are based on historical
data available to the estimator.
– These data date and cost indices can be used to
update them:
Cost now = {cost then}{cost index now/cost index
then}
– Indices available from Cost Guides

Open Pit Mine Planning and Design 256

127
5/11/2014

Capital cost estimation: general


considerations
• Working capital
– This is the capital component of operating
costs needed to support the operation
prior to substantial revenue inflows.
– Often underestimated and can result in
project failure.
– Sometimes a factor (such as 10% of fixed
capital cost) is applied. However a more
detailed analysis is usually good practice.

Open Pit Mine Planning and


257 of 10
Design

Capital cost estimation: general


considerations
• Options for capital equipment
– Contract mining
• capital not available;
• short duration;
• specialist skills required; and/or
• specialist equipment required.
– Hired equipment
– machine only and hirer responsible for fuel,
oil, servicing and operation (dry hire); or
– full hire (all inclusive), usually hourly rate
with standby rate.

Open Pit Mine


258
Planning
of 10 and Design

128
5/11/2014

Capital cost estimation: general


considerations
• Ownership cost
– Fixed cost per hour irrespective of whether
the machine is working or not
– It is a function of:
• purchase price
• cost of any extras
• freight charges
• tyre costs
• resale value
• depreciation period

Open Pit Mine Planning and Design 259

Capital cost estimation: general


considerations
• Ownership cost (cont.)
– Straight-line depreciation formula:
– D = (P - R) / (N.H) where D is depreciation per
hour, P is purchase price, R is residual value, N is
useful life in years, H is hours of service per year.
– Interest component of the cost:
– I = P(r + i)(N + 1) / 200 N.H where I is interest cost
per hour, r is interest rate on capital (%), i is
insurance rate (%).
– Total hourly ownership charge in $/hour, C = D + I

Open Pit Mine Planning and Design 260

129
5/11/2014

Capital cost estimation: general


considerations
• Ownership cost example:
– Assume:
• Cost $400,000;
• Life 10,000 hours over seven years;
• residual value 35% of capital cost; and
• interest and insurance is 12% per year.
– D = (400,000 - 140,000) / 10,000 = $26.00/hour
– I = (400,000 x 12 x 8) / (200 x 10,000) =
$19.20/hour
– C = 26 + 19.20 = $45.20/hour

Open Pit Mine Planning and Design 261

Capital cost estimation: general considerations


• Equipment replacement
– Equipment becomes uneconomic when actual owning and
operating cost exceeds that of a new unit
– Overhaul or replace?
• Cost of overhaul?
• Time to overhaul and requirement for temporary
replacement?
• How long will economic life be extended?
• Other work required during the extension of life?
• Rate charged to mining operation to cover cost compared
with cost of new equipment and economics of mine?
• Will overhauled equipment have acceptable availability?

Open Pit Mine Planning and


262 of 10
Design

130
5/11/2014

Infrastructure capital (cont.)


• Access and site works
– location and logistics
– access and service roads ($65,000 to $230,000/km
depending on purpose)
– port facilities
– airstrips ($700,000 to $4.5 million)
– site works (highly variable; $65,000 to
$400,000/ha).
– drainage
– fencing and security

Open Pit Mine


263
Planning
of 10 and Design

Infrastructure capital (cont.)


• Industrial facilities
– workshops and servicing facilities
– warehouses
– materials handling
– mobile equipment
• Utilities
– power generation, transmission, distribution
– water supply (source, quantities, storage,
distribution)
– fuel storage and distribution
– sewerage and solid waste disposal
Open Pit Mine Planning and Design 264

131
5/11/2014

Infrastructure capital (cont.)


• Communications
– external
– internal
• Port and marine facilities
• Waste disposal systems
– overburden dumps
– water management
– tailings handling and storage
– solid wastes

Open Pit Mine Planning and Design 265

Infrastructure capital (cont.)


• Administration facilities
– administration building
– laboratories
– training facilities
– change rooms
– crib/lunch rooms
– safety and medical facilities
– fire station
– core storage
– security

Open Pit Mine Planning and


266 of 10
Design

132
5/11/2014

Infrastructure capital (cont.)


• Transportation
– road transport
– rail transport
– slurry pipeline
– overland conveyors
– sea or river transport
– cableways (aerial ropeways)

Open Pit Mine Planning and Design 267

Infrastructure capital (cont.)


• Townships
– housing
– roads
– services
– recreation facilities
– shopping facilities
– medical facilities
– educational facilities
– service industries
• Construction facilities

Open Pit Mine Planning and Design 268

133
5/11/2014

Estimating of Operation Costs


• Before any economic analysis or decision-making can be
undertaken the operating and capital costs of equipment
must be estimated.
• Equipment operating costs vary between mine sites and
there is no cost which can be applied universally.
• Equipment costs are generally derived from mine
statistics, from suppliers or estimated from first
principles.
• The standard presentation of costs is Dollars per
Operating Hour or Dollars per Tonne
• Make sure to cross-check your estimated costs with
currently prevailing mine sites.

Open Pit Mine Planning and Design 269

Major Mine Equipment Operating Costs

Open Pit Mine Planning and Design 270

134
5/11/2014

Open Pit Mine Planning and Design 271

Cost Calculation Steps Some equipment needs to be


replaced. Equipments have
lifetime as 5, 10, 20 yrs.
Ownership Costs consists
ore and Capital and Owning depreciation and average annual
investment cost.
Daily Production waste Costs for the
Rate equipment AAI=(n+1)Capital Cost / 2n

AAI should include tax, interest,


Shovels, insurance. So AAIC with a
Mine buildings
trucks, percent
and costs
drills,
excavators
associated with Other capital AAIC=P x AAI
the mine
Select Equipment etc.
development expenditures
Ownership Cost = Depreciation +
period AAIC

Direct operating
# of Milling Costs costs, total
machines operating costs,
Production Rate for (ownership and direct operating
required
each equipment capital costs) costs +
maintenance -
Ore and Waste

Mining Costs

# of production &
support employees Productivity
(tonnes/manshift)
salaries
Total Mining Cost = Total
Operating Cost + ownership Cost
Other Costs Materials,
supplies, power
and labour costs Total Mining Cost
($/hr or $/m or
$/tonnes)
Ore and waste
Operating Costs separation will be
Open Pit Mine
madePlanning and Design 272

135
5/11/2014

Module 8
Financial Technical Modelling

• What is Financial Technical Modeling?


• Revenue Assumptions
• Project Financing
• Evaluation Guidelines
• The Frame Work of Evaluation
• Project Cost of Capital
• Conclusions

Open Pit Mine Planning and Design


273

WHAT IS A FINANCIAL TECHNICAL MODEL


(FTM)?
• Financial/technical models of mining projects are
spreadsheets in which the technical processes of
ore and waste mining, ore processing and
production of salable product are incorporated as
quantities mined, processed and sold and, in turn,
as generating the revenues earned and costs
incurred in such processes.
• The revenues earned depend on forecasts of
product prices, generally supplied by sources
external to the mining operation.
• The costs are determined by technical analysis of
the project by project staff.

Open Pit Mine Planning and Design 274

136
5/11/2014

• Other financial inputs, such as interest rates,


debt raisings and repayments and
depreciation schedules will normally be
supplied by head office corporate staff.

• Forecasts of future inflation rates and


exchange rates may well be supplied by
external sources.

• Example 1 of Financial Technical Model

Open Pit Mine Planning and Design 275

REVENUE ASSUMPTIONS - 1
• World market prices dominant but hard to
predict
• World economic conditions are volatile
• Uneven outlook throughout the world
• Supply and demand dominates - excess
supply is usual but not now (China!)
• Potential for major economic disruptions,
e.g. oil price shocks, Soviet collapse, GFC,
war, China effect, etc.

Open Pit Mine Planning and Design 276

137
5/11/2014

PROJECT FINANCE

• Money lent for developing a project


• Secured against assets and cash flow
of project
• Repayable from earnings of project
• Limited recourse (sometimes no
recourse) to other assets of project
owners

Open Pit Mine Planning and Design 277

SOURCES OF FINANCE
• EQUITY:
– New Issues (shares, options, hybrids, units)
– Asset sales
– Retained earnings
– Term loans
– Securities (bills, bonds, notes, debentures)
– Commodity loans-Leases
– Project finance

• DEBT: security, recourse to borrowing

Open Pit Mine Planning and Design 278

138
5/11/2014

ADVANTAGES OF EQUITY FINANCING


• It's less risky than a loan because you don't have to pay
it back, and it's a good option if you can't afford to take
on debt.
• You tap into the investor's network, which may add
more credibility to your business.
• Investors take a long-term view, and most don't expect
a return on their investment immediately.
• You won't have to channel profits into loan repayment.
• You'll have more cash on hand for expanding the
business.
• There's no requirement to pay back the investment if
the business fails.

Open Pit Mine Planning and Design 279

DISADVANTAGES OF EQUITY FINANCING


• It may require returns that could be more than the rate
you would pay for a bank loan.
• The investor will require some ownership of your
company and a percentage of the profits. You may not
want to give up this kind of control.
• You will have to consult with investors before making
big (or even routine) decisions -- and you may disagree
with your investors.
• In the case of irreconcilable disagreements with
investors, you may need to cash in your portion of the
business and allow the investors to run the company
without you.
• It takes time and effort to find the right investor for your
company.
Open Pit Mine Planning and Design 280

139
5/11/2014

ADVANTAGES OF DEBT FINANCING

• The bank or lending institution has no say in the way


you run your company and does not have any
ownership in your business.
• The business relationship ends once the money is paid
back.
• The interest on the loan is tax deductible.
• Loans can be short term or long term.
• Principal and interest are known figures you can plan in
a budget (provided that you don't take a variable rate
loan).

Open Pit Mine Planning and Design 281

DISADVANTAGES OF DEBT FINANCING


• Money must paid back within a fixed amount of
time.
• If you rely too much on debt and have cash flow
problems, you will have trouble paying the loan
back.
• If you carry too much debt you will be seen as
"high risk" by potential investors – which will limit
your ability to raise capital by equity financing in
the future.
• Debt financing can leave the business vulnerable
during hard times when sales take a dip.
• Debt can make it difficult for a business to grow
because of the high cost of repaying the loan.
• Assets of the business can be held as collateral to
the lender.
Open Pit Mine Planning and Design 282

140
5/11/2014

EQUITY/DEBT FINANCING MIX

• Most businesses opt for a blend of both equity and


debt financing to meet their needs when expanding
a business.

• The two forms of financing together can work well


to reduce the downsides of each.

• The right ratio will vary according to your type of


business, cash flow, profits and the amount of
money you need to expand your business (50:50;
30:70, etc)

Open Pit Mine Planning and Design 283

EVALUATION GUIDELINES
• Made at a point in time
• Sunk costs (don’t worry!)
• Constant $ or current $
• For comparing alternatives, make sure
techniques used permit fair comparisons
• Computer financial models (spreadsheet
modeling)
• Investment decision versus sale/purchase
evaluation

Open Pit Mine Planning and Design 284

141
5/11/2014

FRAMEWORK OF EVALUATION
• A construction of cash flows - in and out
• Express every aspect in terms of cash
• Express uncertainty in ranges of values,
creating multiple models of the one project
• Cash flows not accounting profits
• Evaluate on a stand alone basis
• Ignore side issues unless the side issue is the
purpose of the project

Open Pit Mine Planning and Design 285

MAJOR ITEMS IN FTM

CASH ($):
• Cash is the lifeblood of the enterprise
• “Cash flows” are actual $ spent or received
• Non-cash items (e.g. depreciation) are important as
far as they affect cash flows
• Project cash flows for a period are inflows minus
outflows - may be +ve or -ve
• Periods are usually years; may be quarters or
months, depending on the size of the project

Open Pit Mine Planning and Design 286

142
5/11/2014

INFLOWS AND OUTFLOWS*

• Inflows: sales revenue; may include other


minor items
• Outflows: Initial capital expenditure, working
capital, maintaining capital, operating costs,
taxes, royalties, rehabilitation costs, etc
• Royalties: ?Treat as reductions in revenue
• Off site costs, such as realisation costs, ?
Treat as reductions in revenue

Open Pit Mine Planning and Design * Very important! 287

WORKING CAPITAL
• Component of initial Cap. ex. - to fund op.
costs until sales revenues arrive - in theory
recovered at end of mine life
• Required throughout project life but generally
supplied by sales revenues
• Itemised on a period by period basis in
detailed financial models
• Avoid double counting in financial model but
must be counted in initial funding
requirement

Open Pit Mine Planning and Design 288

143
5/11/2014

CURRENCY
• Local currency (A$ for Australian projects in Australia)
• Because costs in local currency
• Convert revenues to local currency
• Forecast exchange rates can dominate the evaluation
• Foreign projects in host country currency - limited
conversion to A$ needed
• In cases of foreign country hyperinflation, use a stable
currency, e.g. US$, if sales revenues in US$

Open Pit Mine Planning and Design 289

EXCHANGE RATES
• $ EXCHANGE RATE IS QUITE VOLATILE
• Moves with commodity prices but affected by other
influences as well.
• Forex turnover in all currencies in Australian market
represents 4.3% of global turnover, 7th largest forex
market in the world.
• A$/US$ pair ~45% of total turnover. Euro/US$ pair ~14%.
A$/JPY only 1%
• Aust. forex market grew with world market. Also, helped
by carry trade and hedge fund activity, plus growing funds
under management in Australia seeking to invest
overseas. Bulk of trades with overseas FIs
• Aust. banks hedge ~ 100% of forex deals.

Open Pit Mine Planning and Design 290

144
5/11/2014

CONSTANT VS CURRENT $
• $ change in value over time
• Constant $ - generally average value of $ of the day
at time of evaluation, preserved throughout project
life.
• Current $ - $ of the day for each period in the future
- requires calculation of the change in value from
period to period, i.e. usually inflation rates
• Costs affected by local inflation, revenues by world
inflation, up to a point. Mineral commodity
revenues controlled by supply and demand most of
the time.

Open Pit Mine Planning and Design 291

MORE CONSTANT VS CURRENT $


• Constant $ evaluation easier
• Present day costs known but not future revenues
• Current $ evaluation both costs and revenues based
on forecasts of future events
• But current $ are the real world - constant $ is
artificial simplification
• Constant $ evaluations can be misleading by ignoring
inflation but can be very effective in choosing
between alternatives
• Constant $ cost of funds different from current $ cost
of funds

Open Pit Mine Planning and Design 292

145
5/11/2014

INTEREST RATES
• A function of the time value of money
• On debt, represent low risk return
• Therefore, risky investments offer higher
return
• Diversified equity investments offer about
6% above the risk free rate
• Government bonds represent risk free rate
• Interest rates and discount rates closely
linked

Open Pit Mine Planning and Design 293

PROJECT COST OF CAPITAL


• Invested funds are recovered from future
returns with interest
• What rate of interest is appropriate for using
funds in this project?
• Must be above the risk free rate but how much
above?
• Individual resource projects generally have a
slightly higher cost of capital than the
company as a whole
• Function of project risk, diminishing reserves
and need for exploration
• The appropriate cost of capital should be the
discount rate for project evaluation purposes.

Open Pit Mine Planning and Design 294

146
5/11/2014

COMPANY COST OF CAPITAL


• Co funds - equity plus debt
• Cost of equity - empirical measures
• Cost of debt - average after tax interest rate on debt
- factual
• Cost of funds = weighted average cost of equity and
debt
• Current $ cost of capital - includes allowance for
inflation -can be converted to constant $

Open Pit Mine Planning and Design 295

CURRENT $ TO CONSTANT $

1 + CONSTANT $ COST OF CAPITAL


= (1+ CURRENT $ COST OF CAP)/(1+ INFLATION
RATE)

Open Pit Mine Planning and Design 296

147
5/11/2014

MORE ON COST OF CAPITAL


• Cost of equity capital applies for 100% equity
funding
• Debt lowers the cost of capital but increases
risk
• What is the minimum acceptable return on
equity?
• Historically, 8% real on all equities - therefore,
higher in current $ terms
• Should it be higher for “risky” mining
investments?

Open Pit Mine Planning and Design 297

CAPITAL ASSET PRICING MODEL


Developed from long term studies of equity markets
in USA:
R = Rf + B(Rm -Rf)
Where:
• R = required rate of return
• Rf = risk free interest rate
• B =relative risk of particular stock
• Rm = average market return

Open Pit Mine Planning and Design 298

148
5/11/2014

MARKET RISK PREMIUM


• Rm-Rf = market risk premium
• Expected premium, but based on historical data as
proxy
• Australian data over 100 years indicates 5% to 6%
arithmetic average - 6% geometric average
• US data indicates 5% to 6% geometric average
• Volatility of returns means (Rm-Rf) geometric
average is 2% to 10% with 95% confidence. A pretty
big range.

Open Pit Mine Planning and Design 299

WEIGHTED AVERAGE COST OF


CAPITAL
WACC* = (E/A)R +(D/A)Rd(1-tc)
Where;
• E = market value of equity
• D = debt
• A =debt + equity
• R = cost of capital, from CAPM
• Rd = interest rate on debt
• and tc = corporate tax rate
• R is after tax, Rd is pre-tax
*used where a mix of DEBT & EQUITY applies

Open Pit Mine Planning and Design 300

149
5/11/2014

PROJECT PERIODS
• Equal length periods cover entire life of project
• Permits use of standard compound interest
relationships and rules
• Periods = years, generally
• May be quarters or months for small projects
• Project commences with the first period of
investment
• Evaluation relates to beginning of first period

Open Pit Mine Planning and Design 301

SUNK COSTS:
• Past expenditures have no bearing on the
evaluation,e.g., exploration expenditure.

• The evaluation is considering future expenditures


and revenues resulting from a decision yet to be
made.

• True of cost of evaluation and confirmatory work


except for tax benefits

Open Pit Mine Planning and Design 302

150
5/11/2014

END OF PERIOD CONVENTION


• Expenditures and receipts occur irregularly
through time - but, for purposes of
evaluation, all cash flows are deemed to take
place at the end of the period

• Generally conservative

• Midpoint of period can be used

Open Pit Mine Planning and Design 303

PAUSE – REFLECT!
• Revenue assumptions
• Sources of finance
• Cash
• In- Outflow $
• Lagged revenue
• Sunk Costs
• Project periods
•WACC
• Cost of Capital
• Currency, Exchange rates
• Constant vs Current $
• Working Capital

• CAPM
• Interest rates
• Equity vs Debt Financing
• Royalties
• End of period convention

Open Pit Mine Planning and Design 304

151
5/11/2014

DEPRECIATION
• Depreciation is the means of recovering capital
expenditure
• Depreciation deducted from cash flow to
determine taxable income, and thus tax payable
• Depreciation then added back to after tax profit
to determine period cash flow
• Dividend payments are not part of the project
evaluation.
• Positive NPV of cash flows mean capital has
been serviced at the discount rate while
invested, has been recovered and excess return
has been received

Open Pit Mine Planning and Design 305

Capital Expenditure
• Expenditure providing for mine operations for
longer than one year

• Expenditure for operations within the year are


expensed, not capitalised

• Depreciation schedules – straight line over life of


asset, life of mine or 10 years; declining balance
depreciation can defer tax but eventually returns to
straight line.

Open Pit Mine Planning and Design 306

152
5/11/2014

Tax payable calculations

• Taxable income = sales revenue for year


minus all operating costs, overhead costs,
interest payments and depreciation
• Tax rate 30% at present (Australia)
• Negative taxable income, no tax paid and no
tax refund except where group taxation
makes immediate use of tax losses possible
• Usually, tax losses carried forward to reduce
taxable income in later years

Open Pit Mine Planning and Design 307

Period cash flows


• Project cash flows for each year (or shorter period)
made up of:
 After tax profit or loss
 Plus any depreciation added back
 Plus adjustments for any after tax items such as
capital expenditures, loan drawdowns or loan
repayments made or received during the year.

Open Pit Mine Planning and Design 308

153
5/11/2014

ROYALTIES
• Charge levied by State or Federal Government in
return for permission to mine

• Reflects “Crown” ownership of minerals

• Various forms of royalty: ad valorem, pro rata, profit


share, resource rent taxation in different
jurisdictions

• Check what applies to specific project and treat as a


reduction in revenues

Open Pit Mine Planning and Design 309

LAGGED REVENUE
• Example: Smelter pays to the company based
on the waiting period to produce the expected
amount of product depending to the shipping
capacity.

• For gold it is not much time to produce gold from


ore/concentrate to gold bullion, say1 week, but
base metals may take more time, say 2-3 months
lagged.

Open Pit Mine Planning and Design 310

154
5/11/2014

Module 9
Dewatering and Pump
Selection

• Case Study
• Pump & Pipe Selection
• Pumping Costs

Open Pit Mine Planning and Design


311

Introduction
• Proposed mine is in the Mudgee area of NSW
– Populated towns nearby in every direction
– Long history of coal mining in the Central West
NSW with several active coal mines nearby;
deposits of high-grade coking coal are endemic
• The old abandoned open cut mine had 4 identical
pits. Water has filled these pits to an average depth
of 50m
• Coking coal prices are expected to rise, thus
prompting a review of the feasibility of
recommissioning and extending the abandoned
mine pits

Open Pit Mine Planning and Design 312

155
5/11/2014

Dogweed Coking Coal Mine

Mudgee

Sydney

Open Pit Mine Planning and Design 313

Objectives

• Design a suitable
system to dewater the
pits ahead of the
mining operation
– Determine capital
costs and pump
operating costs per
year

Open Pit Mine Planning and Design 314

156
5/11/2014

Methodology
• 3 methods of water volume estimation:
– Volume by Integration
– Volume by Parts
– Volume by using a modelling program eg
AutoDesk Inventor
 Dewatering times, depth of water with time
 Calculation of required pump head over water
depth at different velocities/pipe diameters
 Pipe system selection and costing

Open Pit Mine Planning and Design 315

Geometry of the Pit

 Dimension
 70m wide, 75o highwall, 36 lowwall of spoil
 80m high, 9m thick, dipping at 6
 Depth of water – 50m
 Infrastructure setting
Top Overburden
 In – situ density
lowwall
highwall α=36⁰
89 m
β=75⁰
 Waste 2.3t/BCM
Bottom
Overburden

 Coal 1.4t/BCM

Open Pit Mine Planning and Design 316

157
5/11/2014

Volume of water estimation

Dimensions of the water in pit

Open Pit Mine Planning and Design 317

Method#1
Estimate volume by parts
• The dimension of the water in the pit can be
considered as different parts adding together:
Volume/m3 Formula
Rectangle 𝑥×𝑦×ℎ
Low Wall 𝑎×ℎ×𝑦
Edge 2
High Wall 𝑏×ℎ×𝑦 Paramete Formula Value
Edge 2 r
Sides 2×𝑏×ℎ×𝑥 x 70
2 y 1km-2b 973.21
Corners 1 2 × ℎ × 𝑏2 h 50
3 a ℎ 68.82
Corners 2 2×ℎ×𝑎×𝑏 tan 36𝑜
3 b ℎ 13.40
Open Pit Mine Planning and Design tan 75𝑜 318

158
5/11/2014

Method #2
Estimate volume by integration
• Looking at the model from top, we can evaluate width X and length Y
in terms of the
incremental height Z:
𝑎(ℎ−𝑍) 𝑏(ℎ−𝑍)
𝑋= ℎ
+ ℎ +𝑥
2𝑏(ℎ−𝑍)
𝑌= ℎ
+𝑦
Therefore, the volume is calculated by integrating the area of the cross
section over the height of the model:
ℎ ℎ
𝑉𝑜𝑙𝑢𝑚𝑒 = 𝐴𝑟𝑒𝑎 𝑐𝑟𝑜𝑠𝑠 𝑠𝑒𝑐𝑡𝑖𝑜𝑛 𝑑𝑍 = 𝑋𝑌 . 𝑑𝑍
0 0
2𝑎𝑏ℎ 2𝑏2 ℎ 𝑎𝑦ℎ 𝑏𝑦ℎ
That is, 𝑉𝑜𝑙𝑢𝑚𝑒 = 3
+ 3 + 2 + 2 + 𝑏𝑥ℎ + 𝑥𝑦ℎ
This confirms the volume by parts. By inputting known variables,
volume of the water in the pit is 5.49x106 m3
Open Pit Mine Planning and Design 319

Method #3
Estimate volume by using Inventor

Open Pit Mine Planning and Design 320

159
5/11/2014

Method #3
Estimate volume by using
Inventor

Open Pit Mine Planning and Design 321

Dewatering time
• The disposal flow rate limit is 200 L/s,
therefore the dewatering time can be
calculated:
Volume of Rate of de- Time to Number of Total time
water per watering dewater pits taken for
pit (m3) (m3/s) one pit dewatered dewatering
(days) per year (years)
V Q T=V/(Qx24x N=365/T TT=Nx4
60)
5490065 0.2 317.7 1.15 3.48

Open Pit Mine Planning and Design 322

160
5/11/2014

Depth of Water Over Time


Depth Of Water In Pit Over Time
60.00

50.00

40.00
y = -0.0001837707x2 - 0.0958277546x + 49.5843902089
Depth of Water

R² = 0.9996479452
30.00
Depth

20.00

10.00

0.00
0 50 100 150 200 250 300 350
Days Since Dewatering Commenced

Open Pit Mine Planning and Design 323

Calculating Pump Head


• Pressure drop: Bernoulli’s Equation
𝑝1 𝑉12 𝑝2 𝑉22
+ 𝛼1 + 𝑧1 = + 𝛼2 + 𝑧2 + Σℎ𝐿
𝛾 2𝑔 𝛾 2𝑔
• Major head loss:
𝐿 𝑉2
ℎ𝐿𝑚𝑎𝑗𝑜𝑟 = 𝑓
𝐷 2𝑔
• Minor head loss:
𝑉2
ℎ𝐿𝑚𝑖𝑛𝑜𝑟 = 𝐾𝐿
2𝑔

• Friction factor: Reynold’s number and Moody Chart


Open Pit Mine Planning and Design 324

161
5/11/2014

Pipe System Model

Open Pit Mine Planning and Design 325

Calculation Example

Dept Target Pipe Diameter Pipe Length Reynolds Friction


h Velocity (m) (m) Number Factor
30 2 0.356825 76.25 71364.96 0.022

hZ hV hP hLM hLm V (m/s) L (m) (0 if negligible)


0 30 0 0 0 0 0 0
1 30.5 0.20408 -0.70408 0 0 2
2 30.5 0.20408 61.75476 0 0 2 0
3 30.5 0.20408 61.74711 0 0.007653 2 0
4 30.5 0.20408 60.66451 1.082598 0 2 86.039
5 80 0.20408 10.08396 1.070343 0.010204 2 85.065
6 80 0.20408 0 10.06611 0.017857 2 800

TOTAL PUMP PRESSURE HEAD (m) 62.46

Open Pit Mine Planning and Design 326

162
5/11/2014

Variation of Pump Head with


Depth
Pump Pressure Head wrt Velocity (V)/Pipe Diameter (D)
115

105

95
Required Pump Pressure Head

85

2.829421211 0.3
75
0.439714514 0.761
1.123896216 0.476
65
1.390120911 0.428
y = -x + 109.53
55 1.763489674 0.38
2.228982782 0.338
45 y = -x + 96.312

y = -x + 89.115
35 y = -x + 85.056
y = -x + 82.993
y = -x + 80.325
25
0 10 20 30 40 50 60
Water Depth
Open Pit Mine Planning and Design 327

Pump selection
• Must be capable of meeting largest flow rate
• Must be capable of pumping largest pressure head
• Relatively acceptable costs

– ALLIGHT SYKES-HH220I

Open Pit Mine Planning and Design 328

163
5/11/2014

Pump Power Curve


HH220i Power Curve at 200 L/s
400

350

300

250
y = -0.0003x3 + 0.0837x2 - 4.411x + 187.66
kW

200

150

100

50

0
20 40 60 80 100 120 140
Total Head (m)

Open Pit Mine Planning and Design 329

Pump selection
• Features:
 Diesel, electric or hydraulic drive
 Low fuel usage, reduced engine size
 Lower maintenance costs

Open Pit Mine Planning and Design 330

164
5/11/2014

Pipe system selection


• Pipe type: HDPE
– Suited to butt welding
– Corrosion, abrasion, weathering and chemical
resistant
– Relatively low item cost
– Easy installation
– Flexible and resilient

• Keep in mind:
– Velocity must be high enough to prevent too
much settling

Open Pit Mine Planning and Design 331

Electricity Consumed by Pump


kW-Hours Consumed by Pump During Dewatering of a Pit for Different
Pipe Diameters
330

280
kW Required by Pump

230 0.761
0.476
0.428
180 0.38
0.338
0.3
130

80
0 50 100 150 200 250 300 350
Time (Days)

Open Pit Mine Planning and Design 332

165
5/11/2014

System Costs
Change in Costs per System with Increasing Pipe Diameter
700000

600000

500000

400000
Cost ($)

Cap cost of pipes

300000 Op cost of system


Total

200000

100000

0
0.25 0.35 0.45 0.55 0.65 0.75 0.85
Pipe Diameter (m)

Open Pit Mine Planning and Design 333

Optimised System Costs


• Optimal pipe diameter = 380mm
– Costs from R2, Australian suppliers,

PIPE DIAMETER 380mm

Capital cost of pipe $115697.7 Pipe, transport, installation

Capital cost of pump $81960 Installation costs required

Electricity costs $174935.6 At 10.2 c/kWh

TOTAL $303301.5

Open Pit Mine Planning and Design 334

166
5/11/2014

What Have We
Achieved?
 Fundamentals of open pit mine design and
current developments in planning and design
methodology,
 Current industry practices to maximise
economic return (technology, operations).
 Open pit mine planning and design process in
theory and practice,
 Unit Operations – Drill-Blast-Load-Haul
 Mining Economics
 Apply this knowledge to plan/evaluate new open
pit projects and/or existing mines.
Open Pit Mine Planning and Design 335

Bottom Line is…..

We mine for profit !!!

Open Pit Mine Planning and Design 336

167

You might also like