Declaration: By submitting this assessment (Parts 1 – 4) for marking I declare that it is entirely my work. I understand that falsely claiming that the
work is my own is malpractice and can lead to NEBOSH imposing severe penalties (see the NEBOSH Malpractice Policy for further information).
Important note: You must refer to the document ‘Unit IG2: risk assessment – Guidance and information for learners and Learning Partners’ while
completing all parts of this assessment. Your Learning Partner should provide you with a copy, but it can also be downloaded from the relevant
resources section for this qualification on the NEBOSH website.
Part 1: Background
Hazard Who might be harmed What are you already doing? What further controls/actions are Timescales for Responsible
category and and how? required? further actions person’s job
hazard to be completed title
(Within …)
Work at Height Workers working on the Preventive measures are told 1. A safe workplace should be 1. 2 days HSE Officer
Workers work third floor can fall and to the workers. placed for work. (Action
at the outer cause injuries after an Daily assign every worker his 2. Barrication of cross scaffold 2. 6 weeks 1,8,9)
edge of the 3rd accident, such as broken specific task. tubes should be provided at Finance
floor top, not bones, mental illness, Proper PPEs were provided to the outer edges of the roof.
Manager
wearing a broken elbows, internal the workers. 3. Safety nets should be provided 3. 1 Month (Action
safety organs, limb injuries, to prevent from falling.
harness. depression, and even 4. Airbags should be given where 2,3,4)
4. 2 Month
death. safety nets are Production
accommodating. Supervisor
5. Work must be under strict 5. 1 day (Action
supervision. 5,6,7)
6. The work area should be 6. 02 Days
clean, without any
obstructions.
7. Inspections are carried out on 7. 2 days
daily basis.
8. Enforce the workers to wear 8. 1 day
proper PPEs that prevent them
from danger.
9. Give the workers awareness 9. 1 day
about safety precautions.
Confined Entrants will be affected The worker is authorized to 1. Apply the permit-to-work 1. 03 HSE Officer
Space by the lack of oxygen and work in the pipeline. procedure on site. Weeks (Action
The worker will not be able to move Gloves, air plugs are provided 2. Before entering into a confined 2. 01 Week 1,3,6,8)
works in a freely through the pipes. to the workers. space test and monitor the Site
sewerage Entrants, supervisors, Proper training was provided to atmosphere that there are no Supervisor
pipeline for standby men will face the the workers for working in residues present. (Action
checking water explosion, loss of confined spaces. 3. Mechanical ventilation or 3. 02 2,4,5,7,9)
levels without consciousness, drowning, exhaust fans should provide to Months
a respiratory high temperature, and remove humidity and balance
system. contamination which can the oxygen content.
lead to death. 4. Enforce the workers to wear
breathing apparatus and 4. 01 Week
lighting equipment during work.
5. Give proper training to wear
scuba in an emergency
condition. 5. 01 Week
6. Provide a water flow meter that
will measure how much water
is present. 6. 01 Month
7. Provide proper PPEs to the
workers for safe working.
7. 03 Days
Hazardous The workers, visitors, Masks were provided to the 1. Give the workers Zelbuck Half 1. 01 Week Finance
Substances supervisors, and workers. Facepiece Respirator Mask Manager
High managers are also Gloves, long sleeve clothes, instead of simple masks. (Actions 1,4,6)
concentration affected by the dust due strong boots & eye protection 2. Provide local exhaust
Area
of dust to no extraction of the were provided. ventilation system for reducing 2. 02 Month
Supervisor
produced dust, which will cause Daily handwash routines were exposure to toxic gases etc. (Actions 2,3)
during the dermatitis due to the practiced. 3. Maintenance will be performed
mixing of the chronic effect, and due to on the VEL system. HSE Officer
cement repeated inhalation, it 4. Use machine handling instead 3. 02 (Actions
destroys lungs and leads of manual handling. Weeks 5,7,8,9)
to death. 5. Supervise and train the
workers to reduce the chance 4. 01 Month
of a hazard.
6. Construct a changing room for 5. 01 Week
removal of dust clothes etc.
7. Looking possibility, the health
plans for all workers. 6. 03
8. Implement a safe system of Weeks
work on the construction site.
9. Daily table talks with the 7. 02
workers. Weeks
8. 01 Week
Fire All the workers, people, Fire extinguishers are placed 1. A lot of specific areas for hot 1. 01 Week Safety Officer
At the visitors will be affected by on construction sites at work and smoking etc. (Actions
construction the sudden blast, will face different places. 2. Install smoke and heat 2. 02Months 1,5,6,7)
site welding, inhalation injury, direct Emergency escape routes are detectors.
Finance
smoking burn, and even death will provided in an alarming 3. Implement a Permit to Work 3. 06
Manager
damaged occur. situation. system for controlling hot work. Weeks (Actions 2,4,9)
electrical 4. Place pictograms at different
equipment places to cover any situation. 4. 01 Month HSE Officer
took place 5. Maintain proper best control (Actions 3, 8)
near cranes. and prevent rodent damage in 5. 02
wires and equipment. Weeks
6. Proper maintenance and
cleaning of the equipment will 6. 02
be carried out. Weeks
7. Emergency procedures are
inspected regularly. 7. 03 Days
8. A fire drill must be carried out
one time a month. 8. 02
9. Provide proper PPEs to the Months
workers.
9. 07 Days
Manual The workers unload the Provide work rotation and 1. Use the forklifted instead of 1. 02 Production
Handling vehicle and will be several breaks during their job. using force. Months Manager
Workers affected with back pain, Provide a safe system of work. (Actions 1,2)
unload musculoskeletal
Load Handling The worker, people, and The worker is authorized to the 1. Avoid from the work in unsafe 1. 01 day Safety Officer
Equipment visitors will face work. weather conditions. (Actions 1,4,8)
Crane was dangerous injuries, cut Proper training was provided to 2. Equipment is not handover to 2. 01 Day
lifting body parts and even the workers on how to drive the an unexperienced person. HSE Officer
(Actions 2,3,9)
overloaded I death will occur. crane. 3. Implement the Permit to Work 3. 03
bar in stormy system for operating the heavy Weeks
weather over equipment.
Work-related The workers will be The worker is authorized to 1. Change the working pattern. 1. 01 Week Area
upper limb harmed due to repetitive work. 2. Do a risk assessment about 2. 03 Supervisor
disorder tasks and face back pain, Proper lighting was provided the repetitive job. Weeks (Actions 1,3,5)
On stress, fatigue, and for overnight work. 3. Consult and involve your 3. 04
HSE Officer
construction fractures etc. Health and safety training workers and train them on how Weeks
(Actions
transportation about their work was provided. to report any injury. 2,7,8,9)
of bricks, tiles 4. All the processes will change 4. 02
to final to automation. Months Production
assembly line 5. Plan the workers' routine, set 5. 05 Days Manager
without break break time, that they will take (Actions 4,6)
for getting rest.
overtime. 6. Improve presentation of 6. 01 Week
information using signs,
displays, and color-coding, etc.
7. Provide a safe system of work
on the site. 7. 04
8. Implement ISO 27001 system Weeks
for controlling upper limb
disorders.
9. 02
Weeks
Health, The workers and peoples Competent workers are using. 1. The workplace should be 1. 02 Month Finance
Welfare and visit the site will be All workers are well trained to properly ventilated. Manger
working affected and they can work in any environment. 2. Maintain a reasonable 2. 04 (Actions
environment suffer from dehydration, Suitable PPEs were provided temperature at the workplace Weeks 1,2,4,5)
Workers were heat stress, muscle to the workers. that workers will bear.
Area
working in a cramp and due to cardiac 3. Provide easy access to water 3. 02 Supervisor
hot arrest even death will to overcome their thrust. Weeks (Actions
environment occur. 4. Provide air-conditioned 3,6,8,9,10)
without an restrooms where workers will 4. 03
exhaust take rest at breaktime. Months HSE Officer
system in the 5. Provide toilet and clothing (Action 7)
building. places at accessible places. 5. 01 Month
6. Train the workers to identify
the health hazards. 6. 02
7. Arrange and maintain proper Weeks
health surveillance. 7. 01 Week
8. Provide and implement to wear
proper heat evaporating 8. 01 Month
uniform.
9. Provide cool places of shelter
where workers can stay to 9. 02
avoid heat. Weeks
10. Provide of time recess times
job rotation. 10. 01 Week
Work-Related The driver and public on The driver is authorized to 1. An extra driver must be along 1. 01 Month HSE
Driving the road will suffer a drive the vehicle. with the driver when going on a Supervisor
The vehicles serious accident and Proper training and driving ride. (Actions 1,3,6)
used for even the death of rules were taught to the driver. 2. Vehicles should be inspected 2. 02 Days
Finance
transferring someone will occur. regularly and maintained by
Manager
concrete the manufacturer’s (Action 5)
blocks from 3rd recommendation.
party were not 3. Encourage employees to
in good report all work-related injuries. 3. 01 Week
9. 02 Days
Moral, general legal and financial It's the employer's moral responsibility to provide a safe system of work to the workers. The peoples
arguments work in an organization for feed their families, and this is not acceptable that he/she killed or injured
by the job. It is a basic responsibility of a firm to implement positive safety culture because in the
absence of the safety culture worker will face lifetime injury, psychological stress and even a chance
of loss of job due to accident, not only the worker will suffer but also his family suffers a financial
crisis. Workers and society can’t accept putting their lives at risk, so the employer has to provide a
safe workplace for working without hazards.
In the case of if the worker is injured due to irresponsibility of the organization, the firm will face the
direct cost in the form of worker sick pays, immediate first aid treatment, cost of an accident, and in
the absence of the worker hiring of the new worker. Accident and ill health have a major effect on the
financial assists of company, replacement of the damaged tools and equipment’s, vehicle, etc and
the workers will not perform their regular job with focus due to investigation and will not feel safe at
the workplace. There will a major time loss to prepare reports for enforcement agencies and fines
from court during legal proceedings, and will face loss of company’s credibility, reduction in sales,
etc. In an HSE search, it was demonstrated that uninsured cost is 8 to 36% higher than insured cost.
The legal requirements of an employer are to provide a safe system of work to the workers, safety
equipment, safe machinery should be provided under strict supervision to prevent any hazard. If any
hazard will occur then enforcement agencies of the country will take action against the company, fine
from the court, hiring of lawyers, and even a major hazard will occur then enforcement agencies will
cancel the license of the company. So, it's the company's responsibility to follow the international
labor organization convention C155 and Recommendation R164 which tells us that employers
Barrication of cross scaffold tubes should be provided at the outer edges of the roof.
Action
(Hazard Category: Work at Height)
Specific legal arguments According to ILO Convention C155 - Occupational Safety and Health (Article 16) clearly state
that employers should be provided a safe workplace, machinery, process under their control is
without any risk. ILO Convention C167-Safety and Health in Construction (Article 18) stating that
necessary preventive measures should be taken against the falling of workers, equipment, and
objects from the roof. International labor office training programmed theme summary “Work at
Height” states that on roof work not work near the edge, the simple barrier should be provided
consisting of cross scaffold tubes from avoiding any risk.
Pakistan OSH Act 2018 states that the government of Pakistan should implement the Convention
and Recommendation given by the international labor organization (ILO).
Consideration of likelihood AND the The likelihood of the hazard is very likely because the worker working on the rooftop near the
severity edges, no safety harness worn by the worker which increases the falling chances of the worker
from the rooftop.
When signifying the severity, I concern about the following table
Negligible: No injury will be happened
Minor: Minor abrasions, bruises, cuts, first-aid type injury
Serious: Non-fatal injury, hospital treatment, disability may occur
Fatal: Permanent disability, Major property damage, equipment, and machine loss
Catastrophic: Irretrievable property loss and production, Death will happen
The severity of the hazard I will be rate from the table fatal to catastrophic because in the case of
falling the worker from the 3rd floor top requires immediate hospital treatment and should lead to be
fractures, mental illness, elbow fractures, internal organs, or limb injuries, depression, backbone,
and even death.
How effective the action is likely to be in
Availability of the scaffold cross tubes at the roof edges will efficiently reduce the chance of falling
controlling the risk. This should include:
from the roof and will ensure the worker works safely without any fear.
Introduce residual current devices to save human beings from sudden electric shock.
Action
Hazard Category (Electricity)
Specific legal arguments The ILO Convention C155 and Recommendation R164 require from employees that the
workplace and the processes under their control are safe for the workers. The ILO convention C167
- Safety and Health in Construction (Article 26) states that appropriate measures should be
taken before and during construction to determine that any live cable or electrical equipment at the
site or the site exposes a risk to workers. In the ILO encyclopedia, general hazards in chapter
40 state that residual current devices should be used from preventing the live cables touch at the
site because they can trip by currents as low as 30 mA with potentials as low as 30 ms. Pakistan
OSH Act 2018 states that the government of Pakistan should enforce the workers and implement
the Convention and Recommendation given by the international labor organization (ILO).
Consideration of likelihood AND severity The likelihood of the associated hazard is frequent that live cables are hinged everywhere at a
construction site, no safety shoes were worn by the workers, no residual devices were installed that
will high the risk of the hazard occurring.
When signifying the severity, I concern about the following table
Negligible: No injury will be happened
Minor: Minor abrasions, bruises, cuts, first-aid type injury
Serious: Non-fatal injury, hospital treatment, disability may occur
Fatal: Permanent disability, Major property damage, equipment, and machine loss
Catastrophic: Irretrievable property loss and production, Death will happen
Mechanical ventilation or exhaust fans should provide to remove humidity and balance the oxygen
Action
content. Hazard Category (Confined Space)
Specific legal arguments The ILO convention C164 and Recommendation R164 describes that employees should ensure
that processes running under their control are safe for the workers. The ILO convention C152 -
Occupational Safety and Health (Dock Work) Article 32 describes that take appropriate
measures to prevent accidents or harm to health when an employee is asked to enter a confined
space where toxic or harmful substances have been found or there may be no oxygen etc. The ILO
Recommendation R097 - Protection of Workers' Health Recommendation states that avoiding
exposure by removing dust, smoke, gas, fibers, fog, or fountains at or near the site of origin by
using mechanical exhaust ventilation systems and other suitable methods. Pakistan OSH Act 2018
states that the government of Pakistan should enforce the workers and implement the Convention
and Recommendation given by the international labor organization (ILO).
Consideration of likelihood AND severity The likelihood of this hazard is very likely because at any time a heavy amount of water will come
out then there will be a loss of life. After all, the worker was gone in the pipeline without the
respiratory system that will enhance the chances of the hazard occurring.
When signifying the severity, I concern about the following table
Negligible: No injury will be happened
Minor: Minor abrasions, bruises, cuts, first-aid type injury
Planned review date/period with It's company policy that they review risk assessments after 12 months. So, I am setting the date of
reasoning reviewing the risk assessment as 30 July 2022. However, it is also be reviewed that before the date
of risk assessment is there will be any change occur like
Number of workers, working time, company policy will be change
New machinery or any new equipment will be installed
Working standards, Health and Safety Rules will be change
How the risk assessment findings will be I will call a meeting in which the Finance Manager, HSE Officer, Supervisors, Procurement
communicated AND who you need to tell department will come, and I tell them to implement the necessary actions describes in the risk
assessment report. I will also provide a summary of the risk assessment report and findings, actions
for the site. The findings of the risk assessment report will be included in the upcoming toolbox talk