Standard Project Risk Register
Standard Project Risk Register
Standard Project Risk Register
Negative impact on businesses throughout Claims for compensation due to Appropriate programming on all schemes.
1 SBC 3 3 2 0 9 6 0 2 2 2 0 4 4 0
construction. disruption of business. Communication with stakeholders.
Costs and time associated with Suitable on site supervision and management
Construction Damage to existing public utilities Contractor 3 4 2 0 12 6 0 2 3 2 0 6 4 0
repairs. systems in place to minimise risks.
Adverse weather conditions delay progress to the Programme slippage, additional costs Contingency allowed within programme for
3 SBC 4 3 3 0 12 12 0 2 3 3 0 6 6 0
construction works. incurred. days lost due to adverse weather.