Professional Documents
Culture Documents
Daya CMT SDN BHD V Yuk Tung Construction SDN BHD
Daya CMT SDN BHD V Yuk Tung Construction SDN BHD
BETWEEN
AND
1
[2016] 1 LNS 649 Legal Network Series
BS Mount Sophia Pte Ltd v. Join-Aim Pte Ltd [2012] SGCA 28 (refd)
2
[2016] 1 LNS 649 Legal Network Series
Cocoa Processors Sdn Bhd v. United Malayan Banking Corp Bhd &
Ors [1989] 1 CLJ Rep 436 HC (refd)
Commercial Bank of Australia Ltd v. Amadio and Another [1983] 46
ALR 402 (refd)
El Traco International Pte Ltd v. CGH Development Pte Ltd [2000] 4
SLR 290 (refd)
GHL Pte Ltd v. Unitrak Building Construction Pte Ltd [1999] 3 SLR
604 (refd)
Min Thai Holdings Pte Ltd v. Sunlabel Pte Ltd [1999] 2 SLR 368
(refd)
Mitsubishi Corporation & Ors v. Sepangar Bay Power Corporation
Sdn Bhd & Ors [2009] 2 CLJ 515 HC (refd)
Nafas Abadi Holdings Sdn Bhd v. Putrajaya Holdings Sdn Bhd [2004]
1 LNS 127 HC (refd)
Raymond Construction Pte Ltd v. Low Yang Tong and AGF Insurance
(Singapore) Pte Ltd [1996] SGHC 136 (refd)
Royal Design Studio Pte Ltd v. Chang Development Pte Ltd [1990] 1
LNS 124 HC (refd)
3
[2016] 1 LNS 649 Legal Network Series
Sato Kogyo (M) Sdn Bhd v. Salini Malaysia Sdn Bhd [2013] 1 LNS
1114 HC (refd)
Subashini Rajasingam v. Saravanan Thangathoray & Other Appeals
[2008] 2 CLJ 1 FC (refd)
Sumatec Engineering And Construction Sdn Bhd v. Malaysian
Refining Company Sdn Bhd [2012] 3 CLJ 401 FC (refd)
Wong Heng Meng & Ors v. Prince Guneratnam & Ors [2010] 1 LNS
447 HC (refd)
JUDGMENT OF
Y.A. TUAN LEE SWEE SENG
[1] The dispute here between a main contractor and its principal
had been engaged by the main contractor, the Defendant here, with
landowner/developer as the Main Contractor for all the works under the
4
[2016] 1 LNS 649 Legal Network Series
Contractor, consisted of a Letter of Award dated 2 May 2012 and the PWD
[2] It was a term of the Conditions of Contract that the Plaintiff do furnish
under the Conditions of Contract, the Defendant may utilize and make
[3] The completion date of the Project was 14 November 2014 (“Original
Completion Date”) under clause 39. This was extended by 43 days under
Problem
[4] What happened was that there was substantial delay in the Project.
As is not uncommon, each blamed the other for it! One thing was clear: by
5
[2016] 1 LNS 649 Legal Network Series
October 2014 there was no way the Plaintiff could complete the Principal
units SOHO (22 storeys and 10 units shop offices); Block B of 365 units of
(21 storeys); including 7 1/2 storey podium car park and 2 storey basement
There was one exception though: the Liquidated and Ascertained Damages
RM40,000.00 per day; down from RM70,000.00 per day under clause 40 of
the Plaintiff had failed to complete the Principal Subcontract Works by the
Final Completion Date. It was only on 22 November 2015 that the Plaintiff
6
[2016] 1 LNS 649 Legal Network Series
the Principal Subcontract Works after the Revised Work Programme was
given by the Plaintiff. There were work stoppages and strikes by the
to remedy the defaults failing which the Defendant would terminate the
and the site memo, dated 14 December 2015 exhibited by the Defendant in
Affidavit.
Prayer
letter dated 22 December 2015 issued to Alliance Bank Malaysia Bhd (“the
Bank”). To bring the matter up-to-date, the Plaintiff filed a Writ and this
7
[2016] 1 LNS 649 Legal Network Series
the same day, to essentially restrain the Defendant from calling on the BG
or any part thereof pending the disposal of the suit or until further order of
the Court.
[8] The grounds are that the termination of the Principal Subcontract is
(a) The Defendant reneged on the parties agreement to allow the Plaintiff
the Supplemental Agreement for the benefit of the Defendant and the
8
[2016] 1 LNS 649 Legal Network Series
(d) To cap the atrocities, the Defendant by virtue of its superior position,
Project; and
(e) The encashment and paying out of the BG proceeds will result in the
[9] The Plaintiff stressed that the aforesaid unconscionable conduct are
the documents adduced and that far from it, the unconscionable conduct of
Principles
[10] Lest we forget, this Court must state at the outset that the BG is an
on-demand performance bond. This can be seen from the clear terms of
9
[2016] 1 LNS 649 Legal Network Series
party...”
terms of the bond or guarantee and not on proof of default of the underlying
contract. In Teknik Cekap Sdn Bhd v. Public Bank Bhd [1995] 3 MLJ 449
obligations of the bank, one need only to look at the written bond
itself to determine what are the terms and conditions agreed upon
10
[2016] 1 LNS 649 Legal Network Series
[12] Be that as it may, the cases have stated that between the beneficiary
and the party procuring the bond (the obligor) one is entitled to look at the
been firmly established since the decision of the Apex Court in the case of
Company Sdn Bhd [2012] 4 MLJ 1. The Federal Court speaking through
his Lordship Hamid Embong FCJ, endorsed the approach taken by the
“[17] The Court of Appeal used the following tests and principles in
11
[2016] 1 LNS 649 Legal Network Series
[1956] at p 682).
402).
(iii) In the Singapore High Court, Lai Kew Chai J in the case of Min
Thai Holdings Pte Ltd v. Suniable Pte Ltd & Anor [1999] 2 SLR
12
[2016] 1 LNS 649 Legal Network Series
Pte Ltd v. The Private Office of HRH Sheikh Sultan bin Khadifa
SLR 329)
(vi) In Bocotra Construction Pte Ltd v. AG [1995] 2 SLR (R) 262, the
13
[2016] 1 LNS 649 Legal Network Series
[14] In relation to restraining a beneficiary from calling the bond, the Court
Construction Sdn Bhd [2011] 7 CLJ 442 held that the provisions of the
beneficiary:
[15] With respect to the threshold test of a seriously arguable case, the
14
[2016] 1 LNS 649 Legal Network Series
“[39] We are of the considered view that the ‘seriously arguable and
relevant material facts before the court. The same test which results
the intermediate appeal stage. And the Court of Appeal said this of
15
[2016] 1 LNS 649 Legal Network Series
Bhd v. Nam Fatt Construction Sdn Bhd [2011] 7 CLJ 442 explained the
16
[2016] 1 LNS 649 Legal Network Series
that lack bona fides where there are an element of unfairness or some form
some very broad indications such as lack of bona fides. What kind
depend on the facts of each case. This is a question which the court
Sheikh Sultan bin Khalifa bin Zayed Al-Nahyan [2000] 1 SLR (R) 117;
17
[2016] 1 LNS 649 Legal Network Series
[19] The Singapore Court of Appeal in BS Mount Sophia Pte Ltd v. Join-
Aim Pte Ltd [2012] SGCA 28 at paragraph [36] and [37] said
tainted by bad faith. A precise definition of the concept would not be useful
call cannot be justified with clear evidence or in other situations where the
18
[2016] 1 LNS 649 Legal Network Series
beneficiary is less than certain about his entitlement to call on the bond and
“When determining if a strong prima facie case has been made out,
[20] In Raymond Construction Pte Ltd v. Low Yang Tong and AGF
Insurance (Singapore) Pte Ltd [1996] SGHC 136 Lai Kew Chai J at
either restrain the party or refuse to assist the party. Mere breaches of
unconscionable.
19
[2016] 1 LNS 649 Legal Network Series
that:
[22] It goes without saying that whether or not unconscionability has been
made out would depend on the particular and peculiar facts of each case
taken as a whole and that its determination is very much fact-centric. The
Construction Sdn Bhd [2011] 7 CLJ 442 at p 449 speaking through her
consider such a claim on a case by case basis and assess the totality
of the circumstances”
20
[2016] 1 LNS 649 Legal Network Series
[23] This Court agrees with learned counsel for the Defendant, Mr William
Leong, that mere breaches of the contract, without more, would not by
unconscionability: Sato Kogyo (M) Sdn Bhd v. Salini (M) Sdn Bhd
21
[2016] 1 LNS 649 Legal Network Series
SLR 290.
unconscionable to call on the performance bond where the obligor was not
bond. He cited examples culled from the cases below as illustrating the
a. The beneficiary and or its consultants failed to work with the obligor
unless they pay a bribe, upon the obligor refusing to pay the bribe
352;
22
[2016] 1 LNS 649 Legal Network Series
g. Where the beneficiary was aware that the obligor was entitled to
the benefit of a force majeure clause for not-fulfilling its
contractual
23
[2016] 1 LNS 649 Legal Network Series
performance bond: Min Thai Holdings Pte Ltd v. Sunlabel Pte Ltd
bond unless the obligor paid the lower tier subcontractor which had a
[25] Mr William Leong also distilled the following principle from his
analysis of the cases: that where the amount of the performance bond
called is excessive to the amount due to the beneficiary, the conduct of the
a. The beneficiary called for the full amount when part of the works
was not due, such part that was premature was unconscionable: El
Traco’s case;
b. The beneficiary called for the full amount of the performance bond
when the contractual amount had been reduced by 65%: GHL Pte
24
[2016] 1 LNS 649 Legal Network Series
c. The obligor had completed 95% of the works and the amount called
was more than the value of the remaining works and value for
bond a greater part of which had already been repaid: Olex Focas
Victoria.
[26] Bearing in mind then the above test, this Court shall proceed to
unconscionability.
25
[2016] 1 LNS 649 Legal Network Series
the Plaintiff is to give notice of the causes of delay and if in the opinion of
the SO that the delay is caused by any of the causes listed in sub-
paragraphs (a) - (k) therein the SO shall grant a fair and reasonable
[28] By clause 45 the Plaintiff is required to make good the defects within
the Defects Liability Period at its cost and if the Plaintiff fails to do so the
Defendant shall be entitled make good the defects and deduct the cost
from the retention sum or from the Bank Guarantee. The Defendant is
entitled under clause 50 to deduct any money owing by the Plaintiff from
by a new Clause 51(c)(iv)(a) has been added to provide that all progress
until receipt of the Final Contract Sum from the Employer or expiration of
the Defects Liability Period (whichever is the later) under the Contract and
26
[2016] 1 LNS 649 Legal Network Series
Subcontract Works and making good defects thereto, damages for delay
under the Contract] and all other costs, loss or expense incurred by the
[30] The Plaintiff took possession of the Site on 15 May 2012. The
Original Completion was 14 November 2014 and the Final Completion Date
dated 15 October 2012 accepted the Works Programme and agreed that
pursuant to paragraph 7.1 of the Letter of Award, all parties shall follow the
Exhibit D-4 in the Defendant’s 1 st Affidavit page 33-76 and the Architect’s
letter dated 15 October 2012 is Exhibit D-5 in the Defendant’s 1st Affidavit
page 77.
[31] There is evidence that the Plaintiff was unable to carry out the works
delay occurred almost from the beginning and continued to deteriorate over
27
[2016] 1 LNS 649 Legal Network Series
time. The Plaintiff failed to meet its Works Programme and had to revise it
4 times. The Defendant has produced a series of letters written by the
Defendant, the consultants and the Plaintiff itself contemporaneously
documenting the ever increasing accumulative delay. When it became
apparent that the Project could not be completed by the Original
Completion Date, the Defendant had to take stock of the situation and
confront the consequences of what may follow. A delay in handing over
vacant possession to the purchasers would result in the claims from
purchasers against the landowner/developer with the cascading
consequence of the landowner/developer claiming the same from the
defendant as main contractor.
SUPPLEMENTAL AGREEMENT
28
[2016] 1 LNS 649 Legal Network Series
29
[2016] 1 LNS 649 Legal Network Series
as:-
circumstances in question; or
30
[2016] 1 LNS 649 Legal Network Series
Blocks B and C and the remainder works under Section 2. There was also
the reduction of LAD of RM70,000.00 per day to RM 30,000.00 per day for
Block A and RM40,000.00 per day for Blocks B and C. What is obvious is
that the more onerous operation of the LAD of RM70,000.00 per day is now
buffeted with a reduced LAD of RM30,000.00 for Block A with the hope that
stop to run and the Plaintiff may then concentrate on Section 2 of the works
and any delay would only attract the reduced LAD of RM40,000.00. It was a
[34] In the meanwhile the rights of both parties are reserved and
preserved under the original Principal Subcontract and that was clearly
were incorporated in the Plaintiff’s 3rd and 4th Works Programmes. Block A
was supposed to be completed by May 2015 but when the progress was
expressing its anxious concerns that Block A would not meet the target
date of May 2015 or even June 2015 and likewise too Blocks B and C
31
[2016] 1 LNS 649 Legal Network Series
targeted for completion by January 2016. The Defendant also reminded the
[35] The Plaintiff again fell behind schedule and submitted a 4 th Revised
was provided with instruction to catch up on the delay. See letter dated 14
[36] There were further delays on the 4th Revised Works Programme and
counsel for the Defendant submitted that the Defendant and the
consultants had given numerous warnings that the Plaintiff will be liable to
pay LAD for the delay and the Principal Subcontract will be terminated
32
[2016] 1 LNS 649 Legal Network Series
avail. See one such letter from the Defendant to the Plaintiff dated 30
September 2015 in Exhibit D-9 at p 134 in the Defendant’s 1st Affidavit.
[37] By that letter, the Defendant informed the Plaintiff, it was under
pressure to deliver the units to the purchasers and the Defendant cannot
accept delay beyond 31 March 2016 as indicated in Plaintiff’s 4 th Revised
Works Programme. However, delay, strikes and stoppages continued.
Therefore the Defendant issued a notice under Clause 51 on 3 December
2015 and terminated the Principal Subcontract on 22 December 2015 when
the default was not remedied. A summary of the documentary evidence
produced in Defendant’s 1 st Affidavit Volume 1 is set out at paragraph 40
pages 25-27 of the Defendant’s Main Submission.
[38] A copy of the said Notice to Rectify Breach dated 3 December 2015
is reproduced in full below for an appreciation of the context of the
termination:
33
[2016] 1 LNS 649 Legal Network Series
Attn : Mr. Nathan Tham Jooi Loon / / Mr. William Tham Wooi Loon /
Datuk T.S Lim
Dear Sir,
34
[2016] 1 LNS 649 Legal Network Series
and/or
failing to execute the Works in accordance with the Principal Sub-
Contract or persistently neglecting to carry out your obligations
under the Principal Sub-Contract in that you are seriously failing to
take such measures as to ensure that the completion of Section 2
of the Works are not further delayed beyond that we which we had
previously agreed, ie, end-March 2016.
We trust that the above is clear and that you will act accordingly
failing which we shall act in accordance with Clause 51(a) paragraph
(ii) and/or Clause 51(a) paragraph (iii) of the Conditions of Principal
Sub-Contract to determine your employment under the Principal Sub-
Contract.
Thank you.
Yours faithfully,
YUK TUNG CONSTRUCTION SDN BHD
- sgd -
LIM KIM CHAI, JP
35
[2016] 1 LNS 649 Legal Network Series
[40] The Plaintiff, on the other hand, contended that the Defendant’s own
contemporaneous correspondence reveals an agreement between parties
that the Plaintiff will be allowed to complete the Works by “end-March 2016”
as extracted from the above Notice to Rectify Breach:
36
[2016] 1 LNS 649 Legal Network Series
[41] The Plaintiff further argued that the facts also disclosed that the
counsel for the Plaintiff submitted that apart from substantially affecting the
[42] Learned counsel for the Plaintiff, Mr Alan Wong, drew the Court’s
(a) The Defendant will grant an extension of the Principal Subcontract for
June 2016;
(b) In consideration thereof, the Plaintiff will pay the Defendant LAD of
RM20,000,000.00;
37
[2016] 1 LNS 649 Legal Network Series
(d) In the event the Plaintiff fails to complete Section 2 by 30 June 2016,
and
completion date.
[43] Learned counsel for the Plaintiff was candid enough to admit that the
(a) The Defendant agreed to allow the Plaintiff to complete the Works by
(b) The Defendant was also prepared to have the Works completed by
38
[2016] 1 LNS 649 Legal Network Series
[44] Towards the last quarter of 2015, there was evidence of a chronic
cash flow problem on the part of the Plaintiff, with the Defendant having a
justifiable doubt as to the ability of the Defendant to catch up with time lag
the Plaintiff was responsible for the delay. He claimed that the Bank had
withdrawn the finance facility because the Plaintiff was unable to obtain the
EOT. The Plaintiff had requested the Defendant to allow the EOT in return
for the Plaintiff waiving any increase in preliminaries and undertaking to pay
the LAD for Blocks A, B and C purchasers directly and also to purchase
unsold units. He admitted that without financing, the Plaintiff would not be
stating that it had already rejected the terms that Mr Nathan had proposed
proposed a settlement for the reduction of the LAD payable by the Plaintiff
39
[2016] 1 LNS 649 Legal Network Series
[47] The Defendant denied this and took the Plaintiff’s reply in Exhibit P-9
as a rejection of the Defendant’s proposal in Exhibit P-8 and informed the
Plaintiff that the Defendant would charge the full LAD rate. The Defendant
also gave notice to the Plaintiff to comply with the 4th Revised Work
Programme. See Exhibit P-10 of the Plaintiff’s 1st Affidavit. The Defendant
then gave Notice to the Plaintiff to comply with the 4th Revised Work
Programme. See Exhibit P-10 of the Plaintiff’s 1st Affidavit which is
reproduced below to show the lack of a consensus ad idem as late as 12
November 2015:
40
[2016] 1 LNS 649 Legal Network Series
Penang.
Attn: Mr. Nathan Tham / Datuk T.S Lim / Mr. Joe Tan
Dear Sir,
Based upon your letter of 11 November 2015, we take it that you are
not agreeable to our proposal. In the circumstances we shall claim
the full amount of the LAD under Clause 40 and all rights and
remedies available to us under the Contract.
41
[2016] 1 LNS 649 Legal Network Series
Thank you.
Yours faithfully,
YUK TUNG CONSTRUCTION SDN BHD
- sgd -
LAY KOK KEONG
Contracts Manager
[48] Learned counsel for the Plaintiff was also careful to state that, as a
matter of fact, there was no concluded settlement. Be that as it may,
learned counsel for the Plaintiff proceeded to argue that as the parties
were still negotiating, the Defendant should not have, in the midst of the
negotiation, issued a Notice to Rectify Breach and thereafter to terminate
the Principal Subcontract. Going back to basics, when parties are
negotiating, there would of course be offers and counter-offers and when
the Defendant takes the view that the negotiations have come to an end as
in a stalemate, it would mean that there has been no successful negotiated
42
[2016] 1 LNS 649 Legal Network Series
would have to contend with a new proposition of law that unless both
parties agree that the negotiations have ended, parties must continue to
understood for as long as contract law has been around, cancels the
“justify” the Defendant to call upon the BG, thus unjustifiably denying the
to proceed regularly and diligently with the works, the employer may give a
43
[2016] 1 LNS 649 Legal Network Series
words, the employer does not have to wait until after the completion date is
over before his right to terminate arises. Otherwise the employer would
have to endure what may be a painfully slow progress in the works,
unrealistically hopeful against hope that the contract would be completed
on time when every bit of evidence points to the contrary. Clause 51(a)
paragraph (ii) of the Conditions of Contract allows the Defendant to so
terminate the Principal Subcontract for the Plaintiff’s failure to proceed
regularly and diligently with the Works and Clause 51(a) paragraph (iii) for
the Plaintiff’s failure to execute the Works in accordance with the Principal
Subcontract or persistently neglecting to carry out its obligations under the
Principal Subcontract, respectively.
44
[2016] 1 LNS 649 Legal Network Series
Contract, or
continue such default for fourteen (14) days after receipt of such
added.)
[52] The meaning of the expression “to proceed regularly and diligently”
“In the JCT contracts the phrase requiring the contractor ‘to proceed
regularly and diligently with the works’ means that the contractor must
45
[2016] 1 LNS 649 Legal Network Series
contract.”
[53] That right was available to the Defendant before the Original
Completion Date and by extension the Revised Completion Date. That right
could not have vaporized and vanished after the expiry of the Completion
Dates when in fact the Supplemental Agreement entered into when there
parties under the Conditions of Contract. The Defendant has the option
On the one hand there are the repeated overtures from the Plaintiff that
things would improve at its end and with the change in their main
lost time. With that in place the Plaintiff submitted their 3rd Revised Works
46
[2016] 1 LNS 649 Legal Network Series
the other hand the Defendant has to weigh the further delay in the Works
the balance Works and the corresponding increase in costs and the LAD
[54] Surely it cannot be a case that when the Plaintiff submitted the target
date for Sectional Completion with its Revised Works Programme and the
Defendant having accepted it, the Plaintiff now has the advantage that the
reduced LAD and a Sectional Completion and yet being required to endure
however agonizingly slow the progress in the balance Works even when
end March 2015 or June 2015 or for that matter January 2016, the
Defendant has affirmed the breach and can only claim damages for
Defendant, after the CNC had been issued, for the Defendant to request
47
[2016] 1 LNS 649 Legal Network Series
the Plaintiff to submit the Revised Works Programme with a target date for
Works Programme are target dates for completion and they do not take
away the right of the Defendant to terminate the Principal Subcontract for
and subsisting, unless varied to the limited extent provided under the
[56] The learned author I.N. Duncan Wallace Q.C. in Hudson’s Building
proceed with the [works] .......but in fact, even in the absence of such
48
[2016] 1 LNS 649 Legal Network Series
[57] Looking at the dispute that has arisen over the different
interpretations on the Supplemental Agreement and the conduct of the
parties subsequent to it, and putting the Plaintiff’s case at its highest, what
we have is a contractual dispute over the validity of termination of the
Principal Subcontract, not uncommon in a termination of a construction
contract. Whilst one may believe in the rightness and even the
righteousness of one’s claim as is the Plaintiff’s stand and stance here, that
does not, in the absence of cogent evidence, convert the Defendant’s
conduct into something unconscionable altogether.
49
[2016] 1 LNS 649 Legal Network Series
[58] The Plaintiff accepts that fact that the veracity of the VO claims and
following in the hope of persuading the Court that the Defendant’s actions
(a) There are various outstanding VO and EOT Claims that remains as
(b) The Project was fraught with legacy issues, which the Plaintiff
(c) Pertinently is the issue surrounding the Caisson Wall where the
(d) Arising from the various disputes, including the outstanding EOT
50
[2016] 1 LNS 649 Legal Network Series
[59] In all this debate about who would suffer more and who would be in a
more dire financial stress or distress, it must not be forgotten the plight of
the purchasers of the uncompleted units; they have every right to damages
for late delivery. They have to look to the landowner/developer to pay who
in turn would look to the Defendant, who would in turn look to the Plaintiff
under the LAD Clause. The Plaintiff’s applications for EOT has been
rejected and only 43 days granted. The Plaintiff wanted to appeal and they
would have every right to. The Consultants have replied to say that whilst
the Plaintiff may appeal, they were not inclined to change their minds
unless there are fresh grounds submitted for the appeal for EOT. See
Exhibit D-90 of the Defendant’s 1st Affidavit 2nd Volume p 409 and Exhibits
D-68, D-69, D-70, D-71 and D-72 of the Defendant’s 1 st Affidavit 2nd
51
[2016] 1 LNS 649 Legal Network Series
[60] The Consultants have given their reasons for rejecting the EOTs
trial. For the moment, this Court must ask if the evidence challenging their
Consultants as follows:
1. No extension was given for EOT 1 because the Caisson Wall which
reinforced concrete wall which was to take 138 days. There should
thus have been a saving of 55 days. The delay in the Caisson Wall
Volume 2 p 271.
2. Only 23 days was granted for EOT 2 and the others were rejected as
Engineer did not grant the extension due to delay caused by the
52
[2016] 1 LNS 649 Legal Network Series
3. Only 20 days was granted for EOT 3 on the condition that the Plaintiff
can justify that the events fell on the critical path. The additional
works did not fall on the critical path and therefore no extension was
given for the rest. No extension was given for the claim of 118 days
because the delay was due to the Plaintiff’s own poor coordination
[61] The dates of the various submissions of the EOT 1, EOT 2 and EOT
days for EOT 3 was also granted on the same day. The many letters
chronic and critical delays and the lamentable slow progress in the Works
with LAD increasing by the days, are summarised in a table at pages 25-27
14 letters all in and were written contemporaneously with key events such
as different milestones in the delay, LAD kicking in, strikes and work
stoppages and finally a Notice dated 30 September 2015 for the Plaintiff to
53
[2016] 1 LNS 649 Legal Network Series
rectify the breaches and to catch up with the schedule provided by the
[62] One would have expected a vigorous objection from the Plaintiff if
factually, the various concerns addressed in the above letters were not
true. Indeed the Plaintiff by their letter to the Defendant dated 14 March
hours to catch up with the delay. The Plaintiff also pledged its commitment
October 2014 and also place orders for major equipment. Further the
Plaintiff also acknowledge the delay and replaced its main subcontractor
Works.
applications which they did, being dissatisfied with the decisions of the
Consultants. The Defendant and the Consultants informed the Plaintiff that
unless there were fresh grounds, they would not change their mind.
54
[2016] 1 LNS 649 Legal Network Series
Exhibits D-68, D-69, D-70, D-71 and D-72 Defendant’s 1st Affidavit Volume
balance had not been certified because the Plaintiff had failed to provide
Plaintiff. Even if there is a balance sum owing, that has been overtaken by
Clause 51(c)(iv)(a) where parties have agreed that all progress payments
[65] At this stage this Court cannot conclude that a strong prima facie
case has been made out by the Plaintiff, such that it would be
Applications
[66] Learned counsel for the Plaintiff, Mr Alan Wong, submitted that it
is clear from the Supplemental Agreement that the disputes on the EOT
55
[2016] 1 LNS 649 Legal Network Series
words, the actual time for completion is still very much a “live” issue when
the Defendant wrongfully terminated the Plaintiff and called upon the BG.
Supplemental Agreement.
Ramly Ali JCA (now FCJ) in the earlier cited Kejuruteraan Bintai
“[43] It was also held in that case (Commercial Bank v. Amadio) that
56
[2016] 1 LNS 649 Legal Network Series
(emphasis added)
57
[2016] 1 LNS 649 Legal Network Series
something for the Plaintiff to prove and not a given as is clear from the
qualification in the words “(if any)”. In as much as the Plaintiff may put in
fresh application for EOT, the Consultants are not required to re-assess it
especially if no fresh grounds are canvassed. All that the Consultants have
said is that if the application is based on the same reason, then what they
[70] The Defendant and its Consultants have written letters to the Plaintiff
stating that the delay on the Plaintiff’s part was due to 6 factors referred to
58
[2016] 1 LNS 649 Legal Network Series
[71] The Plaintiff’s tacit admission and acceptance of responsibility for the
delay is reflected in its letter dated 14 March 2013 where the Plaintiff had
directed the blame to the festive season and the shortage of sand in the
market. The Plaintiff proposed in its letter a mitigation plan and a catch-up
machinery and equipment planning and to appoint full time dedicated staff
[72] The Plaintiff by its letter of 8 April 2013 admitted the delay was due to
the non-performance of its subcontractor, Million Aim Sdn Bhd and agreed
time and the number of days of entitlement are a fertile area of conflict in a
what is reasonably applied for, this Court would not at this stage conclude
that a strong prima facie case of unconscionability has been made out.
Whether or not an EOT application should have been granted and if so for
how long, would be a matter for trial. At this stage even if an EOT
59
[2016] 1 LNS 649 Legal Network Series
Agreement that the Agreement had been executed at the request of the
Plaintiff.
[74] It has often been stated that if a party acts within his contractual
rights, then his motive is immaterial. Here there was no complaint of the
million. It was part of a public listed company and would stand to gain a
above and there is nothing unfairly oppressive to the Plaintiff; if at all it has
RM40,000.00 per day for Section 1 and Section 2 Works respectively. All
the other rights and obligations of the parties are reserved and preserved
60
[2016] 1 LNS 649 Legal Network Series
case where a party with a superior bargaining power has sought to bully
also patently clear that the Defendant had interfered with the Plaintiff’s
61
[2016] 1 LNS 649 Legal Network Series
for advance payment from the Plaintiff (and its collaborative partner),
put to greater financial hardship, apart from the hardship already suffered
arising from:
Applications; and
[77] Learned counsel for the Plaintiff contended that the Defendant
that the alleged breach was as a result of the Defendant’s own doing in:
and
62
[2016] 1 LNS 649 Legal Network Series
Plaintiff’s subcontractors.
[78] Learned counsel for the Plaintiff concluded that the alleged breach
“If the Contractor fails to execute the Contract or commits any breach
its behalf may utilize and make payments out of or deductions from
the said Performance Bond or any part thereof in accordance with the
thereafter rely on the same to terminate the Contract as well as to call upon
63
[2016] 1 LNS 649 Legal Network Series
be applicable are:
unquestioningly the allegation that the Defendant had instigated the strikes
and undeniable: the list of some 7 subcontractors and suppliers who have
not been paid by the Plaintiff to the tune of RM 5.2 million at paragraph
15.1 of the Defendant’s 2nd Affidavit and in Exhibit D-10. The Plaintiff had
claimed that the strikes and stoppages were due to the subcontractors’ and
asserted that they had been paying their subcontractors and workers
truth emerged that the subcontractors, suppliers and workers have not been
paid. Some were owed more than RM 2 million like the air-conditioner
subcontractor. Others like the plumber has not been paid since April 2015.
64
[2016] 1 LNS 649 Legal Network Series
said that they had at their end, being mindful of this, paid the Plaintiff
promptly and even in advance. However, this did not cascade down such
that the subcontractors, suppliers and workers were not paid. Without
payments, they have to dump their tools for that is the natural response of
[82] Seeing that there are 2 versions on the strikes and stoppage of
financial strains and the other, the subcontractors, suppliers and workers
not being paid, this Court will have to ask which is more probable at this
stage. The Plaintiff has not refuted the allegation of non-payment to the
the construction ladder are practical people; if they have been paid, why
should they succumb to rumors? If they have not been paid than it is like a
car without fuel. The engine just would not start to run. Work is stalled;
[83] The Defendant is candid in admitting that they did meet up with the
subcontractors, but this was at their expressed request, as they had failed
to obtain payment from the Plaintiff. The Defendant agreed to meet with the
65
[2016] 1 LNS 649 Legal Network Series
[84] The Defendant could not conceal their disappointment with the
Plaintiff here, describing their conduct of blaming the Defendant for the
assisted the Plaintiff on various occasions with their cash flow. The
Defendant reminded the Plaintiff that they did not deduct the LAD from the
the Plaintiff’s cash flow so that the Plaintiff may be able to pay its
[85] Lest the Plaintiff might have forgotten, the Defendant sought to
refresh its memory by referring to the Plaintiff’s request for early release of
carpenters, bar benders and plasterers who had all stopped work. See the
66
[2016] 1 LNS 649 Legal Network Series
[86] It is said that the faintest ink is better than the most retentive memory,
letter from the Plaintiff dated 29 May 2015 requesting for an interest-free
the Plaintiff could give its consent for the payment to be made directly to
the subcontractors and suppliers. However, for reasons best known to the
Plaintiff, it was not keen to give this consent. References are made to the
Plaintiff’s letter dated 29 May 2015 in Exhibit D-61(d) of the Defendant’s 1st
Affidavit Volume 1 page 263 and the Defendant’s letter dated 8 July 2015
hold that a strong prima facie case of unconscionable conduct on the part
whether the Defendant had engineered the default and termination or was
it a case of the Plaintiff trying to engineer itself out of paying its contractual
thus unconscionable
67
[2016] 1 LNS 649 Legal Network Series
[88] Perhaps the most persuasive argument of the Plaintiff is that the
encashment of the BG will also result in the Defendant being unjustly
enriched. That if true would be unconscionable indeed. Learned counsel for
the Plaintiff, Mr Alan Wong, laid the planks for this attack on the call on the
BG as follows:
68
[2016] 1 LNS 649 Legal Network Series
[89] He pointed out that, notwithstanding the LAD provisions under the
Contract, the Defendant now claims that its estimated losses is in the
conduct of the Defendant mentioned aforesaid as well as the fact that the
Defendant itself is not sure of the amount that it is allegedly entitled to, the
He submitted most vigorously that the Plaintiff had approached the LAD
delay. He argued from that which was not disputed i.e. that there had
already been 361 days of delay. The LAD payable by the Plaintiff at RM
24,310,000.00. Had the LAD continued until 30 June 2016 which is what
69
[2016] 1 LNS 649 Legal Network Series
the Plaintiff said should be the extended completion date before which the
purpose and cannot be used to pay the LAD and the new contractor. There
would be rewriting the contract for the parties having in mind the purpose of
Works.
[91] The Defendant in paragraph 7(c) of its 1st Affidavit has set out in
Court needs to be satisfied that there is some basis for the Defendant’s
Subcontract. It is only too true that there would be the purchasers’ LAD
claim against the Developer for late delivery under the standard form sale
and purchase agreement entered into with the Developer under the
Housing Development (Control and Licensing) Act 1966 and they in turn
70
[2016] 1 LNS 649 Legal Network Series
would look to the Defendant as Main Contractor to pay them what they
have to pay out. That claim by the purchasers for LAD is a continuing claim
Even taking generously that Block B and C should have been completed by
30 June 2016 which is nigh soon, the purchasers’ claim for LAD alone was
estimated to be RM11,056,009.42.
[92] The Defendant has also given notice to the Plaintiff that it would have
to be responsible for all GST payments because no GST would have been
payable if the project had been completed by the Final Completion Date. It
was submitted that this Court may take judicial notice of the fact that GST
[93] Then there are the usual loss and expense damages heads of claim
Defendant’s 1st Affidavit. These will be confirmed upon the taking of final
Defendant submitted that these are fair estimates of the cost, expenses
71
[2016] 1 LNS 649 Legal Network Series
incurred and damage suffered by them and therefore there is no basis for
lambasting the Defendant for what the Plaintiff has perceived as unjustly
enriching the Defendant at the expense of the Plaintiff if the full amount of
[94] At any rate under Clause 37 (d) of the Conditions of Contract, if there
good of all defects, shrinkages or other faults which may appear during the
Making Good Defects for the whole of the Works, the surplus shall be
[95] Learned counsel for the Defendant concluded that the Defendant is
Subcontract and calling on the BG. The Plaintiff failed to carry out the
delay and increasingly frequent strikes and work stoppages. The Defendant
a delay of 361 days and the total amount of losses and damages payable
72
[2016] 1 LNS 649 Legal Network Series
basis for the Defendant to call on the BG. With that this Court is inclined to
the Defendant
[96] As the Plaintiff has not discharged the burden of showing a strong
Court shall nevertheless weigh and consider where the balance should tilt.
[97] The Plaintiff sought to persuade the Court that the balance of
Defendant’s security until the alleged breaches and losses are proved.
73
[2016] 1 LNS 649 Legal Network Series
[98] In support thereof, the Plaintiff referred to the following passage from
Ltd & Anor (supra), “we agree that a beneficiary under a performance
added)
74
[2016] 1 LNS 649 Legal Network Series
[99] Learned counsel for the Plaintiff summoned the following factors to
(a) The BG is currently still valid and as long as the BG is kept valid, the
ultimate employer, i.e. the Developer Yuk Tung Land Sdn Bhd (“Yuk
Tung Land”);
(c) It is instructive that both the Defendant and Yuk Tung Land shares
(e) In other words and especially considering that the amount under the
there is high likelihood that the Plaintiff will be unable to recover any
75
[2016] 1 LNS 649 Legal Network Series
(f) Last but not least, the Plaintiff’s reputation as well as that of its parent
[100] Considering the above and especially the fact that the BG is still valid,
the Plaintiff implored upon this Court to restrain the Defendant from calling
and/or receiving payments under the BG in light of what the Plaintiff has
following passage of Ramly Ali JCA (now FCJ) in the earlier cited
76
[2016] 1 LNS 649 Legal Network Series
[102] The Defendant, on the other hand, submitted that it is critical to the
completion of the Project for the Defendant to obtain the proceeds of the
BG to pay for the cost and expenditure that the Defendant had paid or are
immediately payable. The cost and expenditure for the completion of the
Affidavit was filed. This is set out in paragraph 7(c) of the Defendant’s 1st
Affidavit.
issued by the Defendant, its consultants and even the Plaintiff himself. The
1st Affidavit. Where the Plaintiff has a prima facie reasonable basis to
and diligently proceed with the Works, the Defendant would have every
contractual right to call on the BG. Both parties have at the outset of the
Defendant this on-demand BG which the Defendant may call upon if there
77
[2016] 1 LNS 649 Legal Network Series
a reasonable ground for terminating the contract, there is then no basis for
[104] To allow a restrain each time the default is being challenged together
with the termination, the efficacy of a BG would be diluted and more dire
than that, denuded altogether such that what has been bargained for is not
what one is getting. The law realizing that this is not what a BG is supposed
to be in practice, has declared that there must be a strong prima facie case
is not open to the Plaintiff as obligor of the BG to tell the Defendant that they
should use their own funds to finance the balance of the Project and not the
[106] There is also the public element in the interest of the purchasers to
common knowledge that besides from LAD claims, there is the increased
78
[2016] 1 LNS 649 Legal Network Series
costs in the tender for a new contractor to finish completing the balance
Works. The purpose of the BG is to provide for this buffer and cushion the
consequences arising out of the termination and any surplus, upon the
[107] This Court is not persuaded that the Defendant would not be in a
position to pay back the Plaintiff should the Plaintiff succeed at the trial.
The Defendant’s financial resources can be seen in the audited accounts
exhibited as Exhibits D-95 and D-96 of the Defendant’s 1 st Affidavit
Volume 2 pages 433 -458. Yuk Tung Land has current assets of RM
137,084,569 and net assets of RM35,961,962.00 as at 31 December
2014. The Defendant has current assets of RM59,331,248.00 and net
purchasers.
79
[2016] 1 LNS 649 Legal Network Series
position to pay back the Plaintiff should they succeed at the trial or for that
the Defendant must continue to manage cash flow for the balance Works to
further obligation to complete the Works. It only has to suffer what Banks
realize their security for the BG. This is a risk which the Plaintiff would have
appraised itself at the outset when the BG was procured as part of the
[109] The so-called dent and damage to the reputation of the Plaintiff must
Yuk Tung Land together with its Main Contractor Yuk Tung Construction
Sdn Bhd (the Defendant here) would suffer in its reputation in not being
practical completion and with it the need to pay promptly the purchasers’
LAD claims.
[110] The Defendant also drew the Court’s attention to the fact that the
80
[2016] 1 LNS 649 Legal Network Series
the parent company had been disposed of to a RM10.00 company and the
public listed parent company had refused to provide an extension of its
corporate guarantee to guarantee that the Plaintiff would complete the
Project according to the terms of the Principal Subcontract.
[111] I am not satisfied that the balance of convenience would tilt or tip in
favour of the Plaintiff such that the injunction to restrain the call on the BG
should be granted.
Pronouncement
[112] Taking into considerations all the arguments for and against the
injunction, this Court is satisfied that the Plaintiff has not shown a strong
prima case of unconscionable conduct on the part of the Defendant to
justify a restrain on the Defendant from making a call on the BG or to
receive the proceeds from the BG. The Plaintiff’s case taken at its highest
would show a bona fide dispute on the termination of the Principal
Subcontract that would have to go for trial. Nothing had come near to
shocking the conscience or pricking it to the point of a reflex reaction of
revulsion at the so-called reprehensible conduct of the Defendant.
81
[2016] 1 LNS 649 Legal Network Series
or to receive the proceeds from the BG. At any rate, damages would be
more than an adequate remedy being a monetary sum that the parties are
disputing over and that overall, the balance of convenience would tilt in
[114] Damages shall be assessed for the time when the injunction was in
place pursuant to the usual undertaking on damages that the Plaintiff had
to the Defendant. Allocator shall be paid before the extraction of the order
of costs.
[116] Upon the order being given discharging the injunction, learned
counsel for the Plaintiff informed the Court that he had his client’s
instruction to appeal and that he would file in the Notice of Appeal the next
day. He asked for an interim stay of the order pending the filing of an
Erinford injunction.
[117] Learned counsel for the Defendant asked the Court to hear the
82
[2016] 1 LNS 649 Legal Network Series
[118] The Court was of the opinion that a formal application for an Erinford
a temporary stay of the order discharging the injunction until the disposal of
[119] The power of the Court in granting an Erinford injunction has been
clearly spelled out in the case that bears its name in Erinford Properties
pending the trial. On the trial, the question is whether the plaintiff has
sufficiently proved his case. On the other hand, where the application
judgment that has been given is one on which the successful party
83
[2016] 1 LNS 649 Legal Network Series
decide cases even if they are hesitant in their conclusions; and at the
other extreme a judge may be very clear in his conclusions and yet
preserve the status quo pending the appeal. I cannot see that a
the trial the judge becomes functus officio quoad granting any
84
[2016] 1 LNS 649 Legal Network Series
[120] The above passage and the principle that it enunciated have been
Bhd. & Ors. [1989] 1 CLJ (Rep) p 436 the plaintiff owed the 1 st and 2 nd
Upon default receivers and managers were appointed over the properties
and assets of the plaintiff. The plaintiff claimed for damages for wrongful
with its assets pending trial of the action was dismissed. The Court held
that there was no serious issue to be tried. Pending appeal to the Supreme
Court then, the plaintiff applied for an Erinford injunction to preserve the
“ ... I am of the view that whether or not the plaintiff succeeds in the
appeal and in the main action will not be affected by its failure to
85
[2016] 1 LNS 649 Legal Network Series
event the plaintiff’s claim being dismissed, the assets having been
reap the fruits of their success under the debentures. On the other
hand, should the plaintiff succeed in its claim ultimately, for damages,
Lastly, I agree with Tunku Alina that in the present case damages
86
[2016] 1 LNS 649 Legal Network Series
between now and the date when its appeal is heard if my decision is
the banks as defendants could satisfy any judgment that may be granted in
the plaintiff’s favour and not so much that the plaintiff’s assets having been
[123] A similar approach was taken in Kilang Kosfarm Sdn Bhd v. Kosma
Nusantara Bhd (No. 2) [2002] 5 MLJ 662. There the plaintiff had failed in
vacant possession of the defendant’s land to the plaintiff and to restrain the
defendant from interfering and obstructing the plaintiff in carrying out its
obligations under the “Oil Palm Operation and Maintenance Contract”. The
main reliefs in the writ action was a declaration that the defendant had
damages to be assessed and for accounts inquiry into the fruits harvested. In
his Lordship Ramly Ali J (now FCJ) set out his reasoning as follows at p
174:
87
[2016] 1 LNS 649 Legal Network Series
have scrutinised all the prayers in the plaintiff’s statement of claim (as
listed above) and satisfied that whether or not the plaintiff succeeds in
the appeal and in the main action will not be effected (sic) by its
[124] It is trite law that the Plaintiff as Applicant must show that should its
88
[2016] 1 LNS 649 Legal Network Series
towards the balance of the Principal Subcontract Works to be done for the
have every right to claim for the money back from the Defendant.
the money. As the balance of the Project for all practical purposes is
unlikely to be completed until the end of the first quarter of 2017, the
the Owner/Developer who would have received the payment of the balance
purchase price for the units from the end financiers and who would in turn
also have to pay the Defendant for the balance Principal Subcontract
Works done. Both the trial in this Court, realistically rescheduled to 22 till 26
August 2016, as well as the appeal to the Court of Appeal, would in all
[125] I agree with Mr Wiliam Leong for the Defendant that the subject
89
[2016] 1 LNS 649 Legal Network Series
[126] In Mitsubishi Corp & Ors v. Sepangar Bay Power Corp Sdn Bhd &
Ors [2009] 9 MLJ 121 at p 140 it was held that the no Erinford injunction
collected from the financial institutions in the event the applicant succeeds
in the Court of Appeal. On the argument that the financial statement does
not show the beneficiary of the bond to have a good financial health, the
High Court held that that is not the sole criterion for determining its
solvency.
expressed by the Plaintiff that the Defendant does not have the financial
capabilities to repay back the RM13.5 million BG. Here, Yuk Tung Land as
Developer of the Project has given its direct undertaking to the Court that it
would repay the Plaintiff the sum of RM13.5 million in the event the
Leong, should the Plaintiff be successful in its appeal. The usual penal
90
[2016] 1 LNS 649 Legal Network Series
clause shall be included in the order of the Court with the directors name
being mentioned such that upon a failure to comply, a contempt action may
[128] Mr Alan Wong for the Plaintiff conceded that the direct undertaking of
Project is developed to also make a refund of the said sum released under the
BG, is not common and not usually procured or offered. Here the
Defendant and its related company Yuk Tung Land as Developer have
the Plaintiff has to be satisfied with the Defendant showing sufficient means
[129] Quite apart from the undertakings of the Defendant and the
91
[2016] 1 LNS 649 Legal Network Series
its 2014 audited financial statements. See Exhibit P-9 of the Plaintiff’s
same Plaintiff’s Affidavit. The Plaintiff’s allegation that the Defendant’s trade
trade receivables are collectable under normal credit terms granted to trade
clients ranging from 30 days to 120 days. Note 4 further states that the said
sum is due from a company in which certain directors have an interest ie,
that the audited accounts were that of 31 December 2014. As the audited
92
[2016] 1 LNS 649 Legal Network Series
2015 to show that the trade receivables have not vanished or written off but
very much intact. See Exhibit D-115 in Enclosure 31.
[131] Subsequent to the date of the Defendant’s 1st Affidavit, the Defendant
affirmed an Affidavit to oppose the Erinford injunction in Enclosure 29. It
detailed that the actual cost and expenses incurred or to be incurred by the
Defendant is RM68,418,598.95 at paragraph 10.2. A sum of
RM41,760,612.24 is paid or payable as at at 31 March 2016. Particulars of
these cost and expenses are set out in the table below:
GST Charges:
2.
(a) from 1.4.2015 to 2,496,736.23 - 2,496,736.23
22.12.2015
93
[2016] 1 LNS 649 Legal Network Series
94
[2016] 1 LNS 649 Legal Network Series
[132] In the Defendant’s Affidavit in Enclosure 29, the Defendant also set
out the cost incurred to rectify defects as at 31 March 2016 is
RM2,794,633.83, the estimated costs to rectify defects from 1 April 2016
until the estimated completion date of 31 March 2017 for Blocks A, B & C is
RM4,928,557.51. The supporting documents for the cost are marked
collectively as Exhibit “D-112”. Particulars of these costs are as follows in
paragraph 11 of Enclosure 29:
95
[2016] 1 LNS 649 Legal Network Series
and hence conduct unconscionable, if the sum of RM13.5 million under the
BG is released.
[134] In addition, the new contractor, R & C Cergas Teguh Sdn Bhd had
Defendant stated that they needed to release the money requested in order
for the new contractor to continue with the Project and for catching-up on
the delay caused by the Plaintiff. See Exhibit D-113 (Enclosure 29) a copy
of a letter dated 31 March 2016 from R & C Cergas Teguh Sdn Bhd.
Pronouncement
[135] Taking all the above factors into consideration, the Plaintiff has not
shown that if it is successful, the appeal would be nugatory or that there are
[136] As only the Writ has been filed so far by the Plaintiff without a
Statement of Claim being filed, the Court directed the Plaintiff to file the
Statement of Claim and serve the same within 2 weeks. The Defendant is
96
[2016] 1 LNS 649 Legal Network Series
to file its Defence and Counterclaim if any, 2 weeks thereafter. Trial dates
were fixed from 22-26 August 2016. On 26 May 2016 when the Court
delivered this decision, Mr Alan Wong applied for a stay of the Court’s
order dismissing the Erinford application pending his client’s application on
an urgent basis to the Court of Appeal. The Court granted a temporary stay
of the order until Tuesday 5pm of 31 May 2016.
Counsel:
For the plaintiff/applicant - Alan Wong & Andrew Heng; M/s Zain
Megat & Murad
97