SATIP-P-103-02 Rev 1
SATIP-P-103-02 Rev 1
INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
Not Applicable
RECEIVING
2.0
INSPECTION
Page 1 of 4
11/27/2005 3:13 PM
SAUDI ARAMCO ID/PID- REV 1 - 3/01/05 (Standards Cutoff - August 2004)
SATIP No. APPROVED DATE DISCIPLINE:
SAUDI ARAMCO TYPICAL INSPECTION PLAN
Direct Current (DC) Power Systems SATIP-P-103-02 1-Oct-05 Electrical
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR
INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
3.0 INSTALLATION
Page 2 of 4
11/27/2005 3:13 PM
SAUDI ARAMCO ID/PID- REV 1 - 3/01/05 (Standards Cutoff - August 2004)
SATIP No. APPROVED DATE DISCIPLINE:
SAUDI ARAMCO TYPICAL INSPECTION PLAN
Direct Current (DC) Power Systems SATIP-P-103-02 1-Oct-05 Electrical
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR
INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
DC Equipment &
SATIP-P-104-01 LV Cable
Electrochemical Storage Battery See
3.4 See Remarks SA PID to be notified on start of this activity for each DC
Cable Pulling Remarks
system.
Visual Inspection
DC Equipment &
SATIP-P-104-01 LV Cable
Electrochemical Storage Battery
See SATIP-P-111-01 Grounding & Bonding
3.6 Cable Gland Installation, See Remarks
Remarks SA PID to be notified on start of this activity for each DC
Cable Dressing, Identification, &
system.
Termination Visual Inspection
4.0 PRE-COMMISSIONING
SATIP-P-104-01 LV Cable
Power Cable Termination See
4.2 See Remarks SA PID to be notified on start of this activity for each DC
Torque Testing Remarks
system.
Page 3 of 4
11/27/2005 3:13 PM
SAUDI ARAMCO ID/PID- REV 1 - 3/01/05 (Standards Cutoff - August 2004)
SATIP No. APPROVED DATE DISCIPLINE:
SAUDI ARAMCO TYPICAL INSPECTION PLAN
Direct Current (DC) Power Systems SATIP-P-103-02 1-Oct-05 Electrical
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR
INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
GENERAL NOTES
The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the
1
levels of Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC
3
organization representative is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization
4
representative in attendance.
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.
LEGEND
W1 100% Witness Inspection/Test H2 Sample Hold Point for QC Inspection or Test RH1 100% Review and Approval of Documents
W2 Sample Witness Inspection/Test R1 100% Review of Documents RH2 Sample Review and Approval of Documents
H1 100% Hold Point for QC Inspection or Test R2 Sample Review of Documents S Surveillance
Page 4 of 4