Professional Documents
Culture Documents
Apti - Time and Work - Time Speed and Distance - 02 - 08 - 23
Apti - Time and Work - Time Speed and Distance - 02 - 08 - 23
Jain Global campus, Jakkasandra Post, Kanakapura Taluk, Ramanagara District -562112
Aptitude
Mr. SURESHA R.
Assistant Professor
Department of Mathematics,
FET, Jain(Deemed-to-be-University)
1
Mr. SURESHA R Department of Mathematics
Aptitude Test
Aptitude Test is an exam used to determine an individual Skill.
Questions in an aptitude test are based on concepts that test your cognitive
capacity for work
The questions are based on your ability to think and reason in an abstract way to
solve problems effectively and think deliberately
2
Mr. SURESHA R Department of Mathematics
Let us explain the one of the topic of Quantitative Ability.
3
Mr. SURESHA R Department of Mathematics
TIME AND WORK – CONCEPT
Mr. SURESHA R 5
Department of Mathematics
Work from Days:
Answer: C
Explanation:
If A can do a piece of work in ‘n’ days, then A's 1 day's work =1/n
1-day work of Somya = 1/50
Therefore, in 20 days she can do 20 × 1/50 = 20/50 = (2/5) th part of the work.
2. P1H1D1 = P2H2D2
P= Number of person
H=Number of hours
D=Number of days
W=Work
Mr. SURESHA R Department of Mathematics 10
1.15 men can type 3240 pages in 6 days working 2 hours per day. how many
men would be required to type 5400 pages working 4 hours per day for 3
days?
a. 15, b.25, c.50, d.100,
Answer: b
Explanation:Observe that in question work is given also so use formula 1
Given
P1=15, W1=3240 , D1=6 , H1=2
P2=?, W2=5400 , D2=3 , H2=4
P1H1D1/ P2H2D2 = W1/W2
15*2*6 / P2*4*3 = 3240/5400
P2 =5400*15*2*6/3240*4*3 =25
Mr. SURESHA R Department of Mathematics 11
2.If 72 men can build a wall of 280m length in 21 days, how many men to build
a similar type of wall of length 100m?could take 18 days
a. 65, b.45, c.90, d.30,
Answer: d
Explanation: Observe that in question work is given also so use formula 1 (but
hours are not given so alter formulae bit)
P1=72, W1=280 , D1=21 ,
P2=?, W2=100 , D2=18 ,
P1D1/ P2D2 = W1/W2
72*21 / P2*18 = 280/100
P2 =100*72*21/280*18 =30
Mr. SURESHA R Department of Mathematics 12
3. 39 persons can repair a road in 12 days working 5 hours a day. in how
many days will 30 persons working 6 hours a day complete the work?
a. 69, b.35, c.13, d.38,
Answer: C
Answer: B
Answer: A
Explanation: Observe that in question work is NOT given so use formula 2
P1=80, D1=16 , H1=6,
P2=64, D2=15 , H2=?,
P1H1D1 = P2H2D2
80*6*16= 64*H2*15
H2 = 80*6*16 /64*15= 8
Answer: c
Explanation:A + B = 1/12 ----(1)
B + C= 1/15 -----(2)
A=x days, C= 2x days
A=1/x one day of work and C=1/2x one day of work
Subtract (1)-(2) A-C=1/60, 1/x-1/2x=1/60, 1/2x=1/60 , 2x= 60, x=30
A=1/30 work then A=30 days
C=1/ 60 work then C=60 days
Use (1) A + B = 1/12 , (1/30)+B=1/12 , 12(1+30B)= 30, 12+360B=30, 360B=30-12,
360B=18, B=1/20 WORK
B alone takes a 20 days
Department of Mathematics
19
Mr. SURESHA R
3. Asha and Babu can do a job together in 7 days. Asha is 1(3/4) times more
efficient than babu. The same job can be done by Asha alone in
a.11, b.17, c.4, d.7,
Answer: a
Explanation: A + B = 1/7 ----(1)
A=x days, B= 1 (3/4) x days= (1+3/4) x = (7x/4 )
A= 4x days, B=7x days
A=1/4x one day of work and B=1/7x one day of work
(1) , 1/4x + 1/7x = 1/7 , 7(7x+4x)=28x^2 , 11=4x, x= 11/4
Asha alone can do the job A= 4x days
= 4(11/4) = 11 days
Answer: d
Explanation: A = 70 days B= x?
A=140% then B= 100%
Then 140% = 70 , 100% = x
(140/100=70/1) / (100/100 =x/1) , 140/100=70/x , 7/5 = 70/x ,
x= 70*5 / 7,
x = 50 days
Answer: a
Explanation: use case 4
B= x and A= x+50% of x , A= x+ 50*x/100, A= x + x/2,
A= 3x/2
then B=2x , A=3x
A + B =1/18
Now 1/3x + 1/2x = 1/18 , (2x+3x)/6*x^2 = 1/18 , 5/6*x = 1/18 , 18*5 = 6*x ,
x=15
B take =2x=2(15) =30 days
Mr. SURESHA R Department of Mathematics 22
Fraction of Work
1. A can complete (2/3)rd work in 10 days. In how many total days is
required A alone to complete the work =?
2/3 work = 10 days
1 work (Total work ) = 10*(3/2)
Work = 15 days required to complete the work for A.
complete work done by A in 15 days
2. A completes a piece of work in 20 days. Find how many days are required.
to complete 2/5 of the work,
Ie 20 * 2/5 = 40/5 = 8 days
Answer: a
Explanation:
A can complete 2/3 of the work in 4 days
Total Work A= (3/2)*4 = 6 days
B can complete 3/5 of the work in 6 days
Total work B =( 5/3)*6 = 10 days
A+B =?
1/6+1/10= (10+6)/60 = 16/60 =8/30=4/15
Then 15/4 days ( in fraction)
3 (3/4) days (in mixed fraction)
Mr. SURESHA R Department of Mathematics 24
2. A can do 1/2 of a piece of work in 5 days, B can do 3/5 of the same work in 9
days and C can do 2/3 of that work in 8 days. In how many days can all of
them together do the work?
a. 3, b.4, c.5, d.12,
Answer: a
Explanation:
Total Work A = (2/1) *5=10 days
Total work B =( 5/3)*9 = 15 days
Total work C =( 3/2)*8 = 12 days
A+B+C=?
1/10+1/15+1/12= 1/4
Then 4 days
Mr. SURESHA R Department of Mathematics 25
3.P can complete 1/4 of a work in 10 days, Q can complete 40% of the same
work in 15 days, R, completes 1/3 of the work in 13 days and S, 1/6 of the
work in 7 days. Who will be able to complete the work first?
a. P, b.S, c.Q, d.R,
Answer: C
Explanation:
Total Work P = (4/1) *10=40 days
Total work Q =( 5/2)*15 = 75/2 =37 (½)days ( 40% = 40/100=4/10=2/5 )
Total work R =( 3/1)*13 = 39 days
Total work S =( 6/1)*7 = 42 days
Q complete the work first.
Answer: b
Explanation:1 work = 4/5 of work completed by A in 20 days and 1-4/5= 1/5 work is
remaining ( 1/5 work is done by A and B in 3days)
Total Work A = (5/4) *20=25 days
1/5(A+B)= 3 , A+B=15
A+B=1/15
1/25 + B =1/15 , B=1/15 – 1/25 =(25-15)/15*25 = 10/375 = 2/75
B=75/2 days = 37 (1/2) days
Answer: c
Explanation:1 work = 7/10 of work completed by A in 15 days and 1-7/10= 3/10
work is remaining ( 3/10 work is done by A and B in 4 days)
3/10(A+B)= 4 ,
A+B=40/3
=13 (1/3) (mixed fraction)
Answer: d
Explanation:1 work = 2/5 of work completed by A in 6 days and
1 work = 1/3 of work completed by B in 10 days
A+B can cultivate 4/5 th of the land
1-4/5= 1/5 work is remaining ( 1/5 work is done by A and B in 3days)
Total Work A = (5/2) *6=15 days
Total Work B = (3/1) *10=30 days
A+B=?
1/15 +1/30 =30+15/30*15 =45/30*15 =3/30=1/10
A+B = 10 Days
To find 4/5 th of land is cultivated A+B= (4/5)*10 = 8 days
or 4/5(A+B)= 1/10 , A+B=5/40, A+B=1/8, A+B= 8 days 29
Mr. SURESHA R Department of Mathematics
7.A can complete a work in 6 days while B can complete the same work in 12
days. If they work together and complete it, the portion of the work done by
A is
a. 2/3 , b. 4/7, c. 1/2, d. 5/8 ,
Answer: a
Explanation:
A= 6 days then A’s for one day work is A=1/6
B= 12 days then B’s for one day work is B=1/12
A+B= 1/6 + 1/12 = 12+6 / 72 =18/72 = 1/4
the portion of the work done by A alone = 4 Days * 1/6 = 2/3
Answer: c
Explanation:
1 work = 2/3 of work completed by A in 10 days
A alone done work is 10*3/2 = 15 days to complete work and
3/5 of work completed by SAME WORK in ? days
Note:
1. If a person works more hours then wages also be high
2. If a person works less hours then wages also be low
3. Example if two person A and B working in a ratio of 5:2, A does the 5 parts of
the work out of 7 and B do the 2 part of the work out of 7 then A works 5/7
part of the work and B works 2/7 part of the work, who will get the highest
wages obviously A
Answer: d
Explanation: Step 1:
One day work of A= 1/6
One day work of B=1/4
One day work of C=1/9
Step 2: Ratio A:B:C = 5:6:4
Step 3: Share of A = (5/(5+6+4))*1800 =600
Finally, share of the person A is Rupees 600
Answer: b
Explanation:
Man + Boy = 5 days = Rs. 800
The man's efficiency in the work was three times that of the boy
In terms of Days, x:3x ie 5:15
In terms of work, 3:1 ( boys does 1 part of the work at the same time, whereas man does 3
part of the work. So we can say that man eff in work 3 times greater than boy)
The total wage of boy = 1/(3+1) * 800 = 200
Daily wages of the boy= 200/5 = Rs 40
To understand the concept of boats and streams. It is important to know the basics of Time, Speed and
Distance.
• Speed = Distance/Time
• Time = Distance/Speed
• Distance = Speed * Time
• Average Speed = Total distance/Total Time
42
Mr. SURESHA R Department of Mathematics
Some basic types of questions asked in exam
43
Mr. SURESHA R Department of Mathematics
Problems on Time, Speed and Distance
a) 5000 km/hr
b) 50 km/hr
c) 490 km/hr
d) None of these.
Answer: b. 50 km/hr
Explanation:
Speed = Distance/Time
= 500/10
= 50 km/hr.
44
Mr. SURESHA R Department of Mathematics
Problems on Time, Speed and Distance
A boy walks at a speed of 4 kmph. How much time does he take to walk a distance of 20 km?
a) 1 hrs
b) 12 hrs
c) 5 hrs
d) 4 hrs
Answer: c. 5 hrs
Explanation :
Time = Distance / speed
= 20/4
= 5 hours.
45
Mr. SURESHA R Department of Mathematics
Problems on Time, Speed and Distance
If a man can cover 12 metres in one second, how many kilometres can he cover in 3 hours 45 minutes?
a) 150 kms
b) 156 kms
c) 162 kms
d) 168 kms
Explanation :
Distance = ?
Conversion : Speed = 12 m/s = 12 * 18/5 kmph
46
Mr. SURESHA R Department of Mathematics
Problems on Time, Speed and Distance
A man can run a distance of 100 m in 20 seconds. Find the speed of A man in km/hr.
a) 5 km/hr
b) 2000 km/hr
c) 18 km/hr
d) None of these.
Answer: c. 18 km/hr
Explanation:
Distance = 100m = 100/1000 = 1/10 km
Time = 20s = 20/60*60 = 1/180 hr
Speed= distance/time = (1/10) / (1/180) = 180/10 = 18 km/hr
Speed = Distance/Time
= (100/20)*(18/5)
= 18 km/hr.
47
Mr. SURESHA R Department of Mathematics
Problems on Time, Speed and Distance
A cyclist covers a distance of 750 m in 2 min 30 sec. What is the speed in km/hr of the cyclist?
a) 5 km/hr
b) 2000 km/hr
c) 18 km/hr
d) None of these.
Answer: c. 18 km/hr
Explanation:
Distance = 750m = 750/1000 = 75/100 =3/4 km
Time = 2 min 30s = 120s+30s=150s= 150/60*60 = 1/24 hr
Speed= distance/time = (3/4) / (1/24) = 3*6 = 18 km/hr
48
Mr. SURESHA R Department of Mathematics
Problems on Time, Speed and Distance
A train covered first 120 km at a speed of 20 km an hour and then covered the remaining 180 km at a speed of 45
km an hour. Find its average speed.
a) 10 km/hr
b) 20 km/hr
c) 30 km/hr
d) None of these.
Answer: c. 30 km/hr
Explanation:
Total distance = 120 + 180 = 300 km.
Time taken for the first 120 km = 120/20 → 6 hrs.
Time taken for the next 180 km = 180/45 → 4 hrs.
Total time taken = 6 + 4 = 10 hrs.
Average Speed =Total Distance Travelled/Total Time Taken
= 300/10 = 30 km/hr.
49
Mr. SURESHA R Department of Mathematics
How to crack the test?
Books
• Quantitative Aptitude for Competitive Examinations by Dr. R.S. Aggarwal
50
Mr. SURESHA R Department of Mathematics
Thank you
51
Mr. SURESHA R Department of Mathematics