5 STAR
1
Vision Mission Core value
2
Company Brief Introduction
Bevel Gear Pole wheel Synchrocone Cam Ring Gear shift sleeve Shaft Bevel Gear
3
CUSTOMERS
4
5
v QUALITY CIRCLE CFT
KUMARAN K ATHIBAN V
COORDINATOR FACILITATOR
SURESH S
LEADER
ALWIN
J SATHISH SATHISH DHARMA RANJITH CHANDRU
PETER
TEAM MEMBERS
6
v Steps in Quality circle methodology
Identification
of Problems
Selection of
1 the Problem
Follow Up and
review
12 2 Define the
Problem
3
Regular
implementatio
11
n Analysis of the
4 Problem
Identification
5 of Causes
LOGO
10
Trial
implementation &
Check performance
6
Finding out the
Root causes
9
Foreseeing
Probable
Resistance
8 7
Developing Data Analysis
Solution 7
JULY‘23 AUG’23 SEPTEMBER’23
SI NO Action Plan
1W 2W 3W 4W 1W 2W 3W 4W 1W 2W 3W 4W
P
1 Identification of Problems
a
P
2 Selection of the Problem
A
P
3 Define the Problem
A
P
4 Analysis of the Problem
A
P
5 Identification of Causes
A
P
6 Finding out the Root causes
A
P
7 Data Analysis
a
P
8 Developing Solution
A
P
9 Foreseeing Probable Resistance
A
Team Brainstorming
9
IDENTIFY & CATEGORY OF PROBLEMS – Part No.328
Category
S.NO. Problem Description
A B C
1 Bore over size P
2 Datum under size P
3 Bore Line Mark P
4 Bore Unclear P
10
11
HARDTURN PART NO.328 – DEFECT WISE
BORE OVER SIZE DATUM UNDER SIZE BORE LINE BORE UNCLEAR
325
290 294
149
105
55
10 4 20 16
12
Part No.328 is a low tolerance component (Bore Spec:12.002 - 12.015 mm) and in that
bore over size rejection is a major problem.So we have chosen 328 bore over size as our
problem.
99% 100% 100% 100%
1200
83% 90%
1000 80%
70%
800 60%
50%
600
1058 40%
400 30%
20%
200
196 10%
10 4
0 0%
BORE OVER SIZE DATUM UNDER SIZE BORE LINE BORE UNCLEAR
WHEN ? JUNE-2023
14
Process Flow Diagram – Gear &Pinion Manufacturing – OCF Plant 2
Shot blasting Deburring Hard Turn
Selected Area
for
Heat Improvement
Treatment
15
16
Brainstorming on Possible causes
17
CAUSE & EFFECT DIAGRAM
18
S. No Possible Causes Validation / Verification Result
19
S. No Possible Causes Validation / Verification Result
20
S. No Possible Causes Validation / Verification Result
21
Why - Why Analysis for Wrong Offset
Insufficient training
22
Why-Why Analysis for using Re-lapped inserts
23
Why – Why Analysis for Operator Skipping Inspection
Insufficient Training
24
BORE OVERSIZE QUANTITY FROM MARCH,2023 TO JULY,2023
350 325
290 294
300
250
250
QUANTITY
200
149
150
100
50
0
Mar-23 Apr-23 May-23 Jun-23 Jul-23
MONTH 25
• Macro Implementation to control offsets ( Max 10 microns at a time adding up
to 30 microns maximum)
• Using Fresh inserts instead of Re-lapped inserts.
• Implementing Auto Offset Correction(AOC).
• Machine should only be run by regular operator and the adequate training must
be given to new operators.
26
SOLUTIONS PROBABABLE RESISTANCES
27
Macro Implementation
• Macro has implemented to control offsets • An alarm has been set to indicate if the given
(Max 10 microns at a time adding up to 30 offset is more than 10 microns(0.01 mm)
microns maximum)
28
Auto Offset Correction(AOC) Implementation
• Auto Offset Correction(AOC) has been implemented to give auto offsets based on the previous job
that ran on the machine and the CNC machine is interlocked with AOC.
29
RE-LAPPED INSERT FRESH INSERT
NO GAP
GAP
30
BORE OVERSIZE QUANTITY FROM JUNE,2023 TO OCTOBER,2023
QUANTITY
325
264
149
63
9
JUN-23 JUL-23 AUG-23 SEP-23 OCT-23
MONTH
BEFORE QC AFTER QC
vFrom the above graph, the bore oversized jobs was 9 Nos for the month of
October and the PPM for the month of October has came down to less than 400
PPM.
vAnd from the above graph we can notice the significant reduction in bore over
size defects due to the implementations we have done.
31
• Auto Offset Correction (AOC) & Macro offset are implemented in the CNC
machine and training has given to the concerned CNC operators, Cell leaders,
Quality department and Production team .
32
• Implemented solutions are being monitored continuously through Daily trend
graph and data’s are being recorded on a daily basis.
33
Cost benefits:-
PRICE OF A 328 PINION :- Rs.48
August Month Bore over size scrap value :- 264(Quantity) * 48(Price) = Rs.12,672 (A)
September Month Bore over size scrap value :- 63(Quantity) * 48(Price) = Rs.3024 (B)
October Month Bore over size scrap value :- 9(Quantity) * 48(Price) = Rs.432 (C)
34
Intangible benefits:-
35