OHSE MANAGEMENT SYSTEM PROCESSES Doc. No.

AFC/1706/HSE/01
(ISO 45001: 2018 & ISO 14001: 2015) Job code-1706
CONSTRUCTION OF MUMBAI – AHMEDABAD HIGH SPEED Rev. No:00
RAIL Package No: MAHSR – C 2
Date: 26.05.2023
Page:

Hot Work Permit


No. Item Addressed Compliant Comments
Y N N/A
1 Is the activity has clear method for work along with risk assessment?

2 Is the cutting and/or welding equipment’s are thoroughly inspected and


found to defect free and in good working condition?

3 Is Hot work operator is competent to perform the work and equipped with
communication device and protective equipment?
4 Is floor area under and at least 35 feet around the cutting and welding
operation is kept free from combustible and flammable materials or
protected from fire?
5 Is the area is cordoned off to prevent unauthorised access during hot work
activities?

6 is the fire watcher with adequate extinguisher ( with him or nearby) is


available at the location of work where hot work is being conducted and
the fire watcher is trained for use of relevant extinguisher
7 Are near by opening/holes are covered to prevent spread of welding
sparks/slag from traveling to other unprotected areas.

8 Is adequate ventilation provided to disperse fumes generated during hot


work?

9 Is fire wither is instructed to inspect area for at least 30minutes after all
hot work is ceased for the day or time.

10 are gas cylinders have been provided with flash back arrestors and gas
cylinders are kept vertical and secured to prevent fall

11 Is that adequate, sufficient and required signage’s and posters are


provided for awareness of persons working nearby?

12 Are the protective screens positioned to protect nearby personnel from


hazardous light generated from welding or cutting operation.

Assessment Completed By : Responsibility Accepted By