Professional Documents
Culture Documents
LAVINE
LAVINE
MANAGEMENT
I hereby declare that this research project is my original work and has not been
Signature............................................... Date:..............................................
LAVINE MUYUKA
SUPERVISOR
This research project has been submitted with my approval as the Polytechnic Supervisor.
Signature:......................................................... Date:..............................................
MR ALOICE ONYANGO
I dedicate my project to my mum and dad for their financial support and their
unconditional love and support made me handle life’s challenges with a greater
resilience. Special credit goes to my parents, for their visionary thinking and for
My heart is sincerely grateful for your support. God bless you and Thank you for
ii
ACNKNOWLEDGEMENT
suggestions, right criticisms and guidance that helped me stay on course and to
finish this research project. I am also deeply indebted to my friends and course
colleagues for their contributions in various ways towards the completion of this
work.
business system users who patiently bore the displeasures of completing the
questionnaires.
I finally give thanks to the almighty God for granting me great guidance, energy,
iii
TABLE OF CONTENTS
Table of Contents
DECLARATION..........................................................................................................................i
DEDICATION.............................................................................................................................ii
ACNKNOWLEDGEMENT.......................................................................................................iii
TABLE OF CONTENTS.............................................................................................................4
LIST OF FIGURES.....................................................................................................................7
LIST OF TABLES.......................................................................................................................9
ABREVIATIONS AND ACRONYMS.....................................................................................10
OPERATIONAL DEFINITION OF TERMS............................................................................11
ABSTRACT...............................................................................................................................12
CHAPTER ONE: INTRODUCTION..........................................................................................1
1.1 Background to the Study...................................................................................................1
1.1.1 Enterprise Resource Planning Systems.............................................................................2
1.1.2 Organizational Performance..............................................................................................3
1.1.3 Selected manufacturing firms.............................................................................................5
1.2 Statement of the Problem..................................................................................................6
1.3 Objectives of the Study.....................................................................................................8
1.3.1 General Objective.............................................................................................................8
1.3.2 Specific Objectives...........................................................................................................8
1.4 Research Questions...........................................................................................................9
1.5 Significance of the Study..................................................................................................9
1.6 Scope of the Study..........................................................................................................11
1.7 Limitation of the study.........................................................................................................11
CHAPTER TWO: LITERATURE REVIEW............................................................................12
2.1 Introduction.....................................................................................................................12
2.2 Theoretical Review.........................................................................................................12
2.2.1 Contingency Theory........................................................................................................12
2.2.2 Balanced Scorecard.........................................................................................................12
2.3 Empirical Review............................................................................................................14
iv
2.3.1 Enterprise resource planning systems.............................................................................14
2.3.2 Indicators of quality organizational supply chain performance........................................15
2. Increased productivity..........................................................................................................15
2.3.3Relationship Between Enterprise resource planning And Organizational Supply Chain
Performance....................................................................................................................16
2.4 Summary and Research Gap...........................................................................................17
Locally, many studies recommend organizations to address the obstacles affecting proper
implementation ERP systems hence existence of a research gap on ERP system on
organizational performance.............................................................................................17
Figure2.1: Conceptual Framework............................................................................................18
2.5.1 Explanations of variables..................................................................................................18
CHAPTER THREE: RESEARCH METHODOLOGY............................................................19
3.1 Introduction.....................................................................................................................19
3.2 Research Design..............................................................................................................19
3.3 Target Population............................................................................................................19
Table3.1: Target Population.......................................................................................................20
Total 20
15 20
202 20
217 20
Source: Field data 2021..............................................................................................................20
3.4 Sampling Design and Sample Size.................................................................................20
3.4.1 Sample Design................................................................................................................20
3.4.2 Sample Size.....................................................................................................................18
3.5.1 Questionnaires.................................................................................................................19
3.6 Data Analysis and Presentation.......................................................................................19
4.8 CONCLUSION....................................................................................................................14
4.9 RECOMMENDATIONS.....................................................................................................15
The study recommends that the top management should provide the necessary resource in
terms of leadership financial support, to management may also be involve monitoring
and evaluating the implementation process trim time to time........................................15
The key performance indicator are patient part of measuring the success and failure of the
companies, it’s also allow companies owner and manager to get overview of individual
v
department is performing at any given time. its also recommend that enterprise resource
planning can improve a company business performance by developing the most
efficient way to plan and schedule resource and optimize productivity, it can also offer
data visibility to user customer and vender allowing them to view data in real time and
improve relationship in all aspect of your business........................................................15
REFERENCES...........................................................................................................................16
1
vi
LIST OF FIGURES
.......................................................................................................................................................
27
Figure4.1:Respondents’Gender
.......................................................................................................................................................
37
.......................................................................................................................................................
39
.......................................................................................................................................................
48
7
8
LIST OF TABLES
9
ABREVIATIONS AND ACRONYMS
CT Contingency Theory
IS Information Systems
IT Information Technology
ST Stakeholder Theory
10
OPERATIONAL DEFINITION OF TERMS
sourcing
11
ABSTRACT
Enterprise resource planning (ERP) is one of the major business systems that assist
Organization to manage their resource effectively.
In the era of information Technology, ERP system has become the necessary tool
to operate business efficiently. The purpose of study was to investigate effect of
enterprise resource planning system on procurement efficiency in determine the
effect of system control of enterprise resource planning on procurement efficiency
in selected manufacturing firm in Kisumu, The objective of the study were To
determine the type of enterprise resource planning system. To determine indicators
organization supply chain performance and to determine the relation between
enterprise resources planning system and organization supply chain performance.
The study was carried out in two manufacturing organization which were randomly
sample in Kisumu County. The organizations are united Miller's and Equator
bottlers. The study adopted a quantities description research design and use
questionnaires as the Main data collection instrument. The target population was
all managers, senior and junior clerks in the procurement production and finance
department respectively. Data was analyzed by statistical packages for social
science was presented in form frequency table bar chats and bar graph .From the
study findings concluded that there are various type of ERP system use in the two
manufacturing firm, the Organization gives the employee efficiency work which
enhance accountability that ERP system reduce cost in the Organization supply
chain performance. The study concluded that the ERP system has come out to be
the best tool in coordinate and integration of organization procurement Process due
to its ability in processing information faster, track Order and inventory control.
automation of order and duplication in procurement in the procurement system
module .The most cover area in ERP was the customer relation management 80%
this implies that both the internal and external customer need had been well taken
care of by the system leading to a faster process in procurement.
The study recommended that organization should embrace technology change that
is rapidly changing on the environment that the organization exists. This was
evident with the effect of ERP on timely delivery of product, improves customer
relationship and was reliable information systems.
.
12
13
CHAPTER ONE: INTRODUCTION
This chapter comprises of the background to the study, statement of the problem,
objectives of the study, research questions, significance of the study, scope of the
goes beyond simply buying an office computer and connecting it to the internet. It
support the functional areas of the business .These areas include operations and
sales and distribution, human resource, supply chain, customer relationship and e-
Software (Torach, 2011).Tidier (2010), emphasizes that ERP systems are one
database, one application and a unified interface across the entire enterprise”. ERP
systems offer unique benefits to the organizations implementing them. This they
the best practices embedded in ERP systems, which ensure quality and
predictability in their global business interests by reducing cycle time from order to
delivery (Ross, 2013). With the evolvement of ERP systems, the interest in the
1
impact that these systems have on organizational performance has risen.
Enterprise Resource Planning (ERP) is the generic term used for management
software that include modules such as production, finance, marketing and human
resources and that allow companies to plan their goods and services (Stevenson,
customer relationship management, etc. ERP systems automate this activity with
Zhao and Fan (2007) suggested that new generation ERP systems should be
developed based on the principles of low cost, high quality and efficiency. In the
recent years, ERP software has become widely used in almost all sectors such as
business functions inside the boundaries of the organization and manage the
efficiency.
Kumar and Keshan (2009) explains that lacking an ERP solution, firms especially
2
that are functionally deficient, obsolete, and isolated from other applications and
data. According to Asemi and Jazi (2010) even though the price of prewritten
implementation could be three to five times the purchase price of the software.
Clemmons and Simon (2011) assert that nowadays human resources management
of the project management. HRM has changed from an inactive and problem-
solving role to a strategic, focusing on the retention and development of the best
Nowadays, HRM takes more of a full service role providing employee support
beyond pension planning and career development. With the arrival of ERP
systems, HR functions became fully integrated with the operations side of the
provides the purchasing firm with a considerable opportunity for cost reduction
through bargaining, and hence reduces the benefits and likelihood of JIT adoption).
Handfield’s (2013) also argue that if ERP systems provide reductions in material
be associated with an increased potential to benefit from the use of B2B market
3
Organizational performance is the final achievement of an organization and
achieving the targets and the realization of efficiency and effectiveness (Gibson,
Mundy & Sink, 2010). On the other hand, organizational performance refers to
large market share, good financial results, and survival at pre-determined time
using relevant strategy for action. Organizational performance can also be used to
view how an enterprise is doing in terms of level of profit, market share and
Delaney, Dess and Robinson (2010) assert that organization performance can be
the same way, Green et al (2011) identified that return on investment, sales and
market growth, and profit are important factors that be measured by organization
Incorporating supply chain practices into existing structures has the potential of
4
Finance always being disregarded in financial decision making since it involves
argue that financial integration has also been the primary concern of business
United millers
United Millers is primarily engaged in manufacturing and marketing of Fast Moving Consumer
Goods (FMCG) items of daily consumption and is deeply entrenched into processing and
marketing human food, like Wheat flours of different kind, Maize Meals, Bakery products,
Equator bottlers
Equator Bottlers Limited (EBL) is based in Kisumu, Kenya and was established in 1966. Equator
Bottlers is a subsidiary of Coca-Cola Beverages Africa (CCBA).CCBA produces and sells 40%
5
of all the Coca-Cola volumes on the African content. There are more than 30 bottling plants
ERP systems attempt to integrate all business processes into one enterprise wide
system platform that would provide integration for processes throughout the
ADC adopted the ERP system to streamline its support departments’ operations
with the eventual goal of efficiency in running its core business of revenue
collection. The purpose of the ERP was to modernize the support departments
department (ADC, 2017). This adoption has been marked by a mixture of success
and challenges. Reports on the adoption, state that customization of the ERP
software from the vendors to KRA business operations has been limited. The ERP
system has also been very expensive. ERP implementation is considerably also
more difficult and politically charged because the organization is structured in such
a way that there are in dependent support departments, each responsible for their
6
own reports, because they each have different processes, rules, data semantics,
7
of ERP leads to efficiency and his results show that at the organizational level,
ERP has very positive impact on the performance of companies. Therefore, this
The general objective of this study was to investigate effect of enterprise resource
in Kisumu County.
8
1.4 Research Questions
iii. What are the relationship between enterprise resource planning systems
There are various benefits that the findings would accrue to the field of enterprise
sector. These benefits are indicative of the significance of the study and the
justifications for the same. The findings of this study would help identify the
challenges that are faced by organizations when they are adopting new
technologies in Africa, and especially in Kisumu County. This knowledge will help
managers and other stakeholders in the organization to come up with strategies that
can be used to increase the benefits that the organization can accrue from a new
technology.
This study would offer valuable contribution to theory and practice. This study
could be seen in the fact that the outcome can be applied in the development of an
ICT policy framework as a guide for ERP adoption, which is relevant in most
9
The study would create a forum for further discussions on best practices to
implement an ERP system. This would help organizations in not only looking at
ERP just as any other technological adoption but looking at it as a strategic tool
that would help an organization to improve its performance and also towards
The study would also act as a source of reference material for future researchers on
other related topics. Further, it would help other academicians who will undertake
the same topic in their studies. Apart from this, it would also emphasize on other
significant relationships that require further research. This may be in the area of
10
1.6 Scope of the Study
engaged in giving their views on ERP system, and to what level it affects
The objective of the research were achieved but with various limitations. Due to the different
scope of operations among the different departments across selected manufacturing firms in
Kisumu County, the safety and health measures and practices were different in findings based on
mere judgments of the respondents. Because of the confidentiality policy of some departments,
the respondents from other departments did not answer the questionnaires or failed to give all the
11
CHAPTER TWO: LITERATURE REVIEW
2.1 Introduction
This chapter dealt with the theoretical review, empirical review based on specific
objectives of the study, summary and research gaps and conceptual framework.
The study was guided by Contingency Theory (CT) developed by Lawrence and
Lorsch (1967).In this study, as the two levels in the research framework are
and so forth. CT assumes the existence of rational actors and often researchers
using it narrow their focus to deterministic models (i.e., only the arrows
representing a required association are shown and the effects of other factors are
ignored)(Weill & Olson, 1989). Due to the limitations in CT and its gradually
diminishing influence among researchers in IS and related field, Weill and Olson
12
This study was guided by Balanced score card by Kaplan & Norton (1995).
objectives and measures of BSC are derived from an organization’s vision and
framework that translates a company’s vision and strategy into a coherent set of
scorecard not only allows the monitoring of present performance, but also tries to
Balanced Scorecard has evolved to become a core management tool, in that it helps
CEOs not only to clarify and communicate strategy, but also to manage strategy. In
practice, companies use the BSC approach to accomplish four critical management
processes, clarify and translate vision and strategy, communicate and link strategic
objectives and measures, plan, set targets, and align strategic initiatives and
The Balanced Score Card (BSC) is a management system used to align business
activities to the vision and strategy of the organization, improve internal and
13
goals. It is a performance measurement tool that considers not only financial
measures but also customer satisfaction, business process and learning measures
performance measurement tool and recommends that the company should provide
enoughresourcesespeciallyforfundingfurthercomprehensivesensitizationon the
Here are examples of ERP systems that can help you automate your company processes.
Our first example of an ERP system is probably one you’ve heard of before. Founded in 2012,
Oracle ERP Cloud is modern, dynamic software that’s used by a wide range of customers. The
suite of cloud applications leverages artificial intelligence (AI) and machine learning to automate
everyday tasks.
SAP S/4HANA. This next-generation service is known for its far-reaching compatibility with
Oracle Cloud ERP. Oracle is one of the most well-established software companies in the
world. They boast a broad range of capabilities within their ERP solution, including
Sage Intact. This company is known for its extensive third-party integration capabilities
14
and being useful for smaller, high-growth companies.
EPCOR ERP. EPCOR offers a high degree of scalability and customizability for
businesses of different sizes. Also includes options for in-house or cloud-based usability.
1. Increase efficiency
One of the most useful indicators of organizational effectiveness is how well an organization
1. Comparing actual achievements against set goals. Comparing the projected aims, such as
2. Measuring the efficiency of business functions, areas, and processes. How cost-effectively,
investment, and the results of that process as the return on that investment.
Organizations that meet or exceed their set aims would be considered more effective than those
that don’t.
2. Increased productivity
Employee’s performances directly affects their contribution to the efficiency and results of a
business unit.
And the performance of each business unit, in turn, affects the organization’s overall
15
performance.
above, values, and mission, tools and technology, the work environment.
3. Reduced cost
Without the right tools, an organization simply cannot keep up with its competitors.
The right tools and technology positively impact theworkforce experience. A digitally-powered
workplace also improves the employee experience. Effective digital tools and training can
other things.
Chain Performance
This paper has empirically tested a framework identifying the relationships among SCM
practices, ERP systems, competitive advantage and firm performance. The primary goal of this
research has been investigate the effects of SCM practices and ERP systems on competitive
advantage and firm performance. To test the research hypotheses, a path analysis using AMOS
4.0 program was applied. Our results show that most of the hypotheses were supported. For
example, SCM practices have a greater positive impact on competitive advantage and firm
performance. The standardized path coefficients for SCM practices on competitive advantage
and firm performance were 0.77 and 0.50, respectively. ERP practices do not have any effect on
competitive advantage but they have a positive impact on firm performance. The standardized
16
path coefficients for SCM practices on competitive advantage and firm performance were 0.12
and 0.27, respectively. Finally, competitive advantage does not have any effect on firm
performance. These findings support our conceptual model and offer a number of managerial
implications. First, this study provides a practical tool for managers to evaluate the SCM
practices and ERP systems, through the development and the validation of these systems. Also,
we showed the effectiveness of SCM practices and ERP success in increasing the performance
and competitive advantage. In order to achieve higher competitive advantage, managers should
adopt SCM practices. Since the competition is moving from to reduce supply chain costs and
secures competitive advantage. The results of this research support that SCM practices can have
discernible impact on competitive advantage and firm performance. It should be noted that SCM
practices and ERP systems may be influenced by contextual factors, such as the type of the
industry, firm size, etc. This study integrates the all the activities of the SCM and ERP systems
and links these activities with competitive advantage and firm performance.
Locally, many studies recommend organizations to address the obstacles affecting proper
organizational performance.
17
2.5 Conceptual framework in dependent variables
18
Figure 2.1 shows the relationship between independent variables and dependent
variable. The independent variable is ERP which include oracle ERP cloud,
SAP S/4HANA and EPCOR ERP. The dependent variable is the organizational
RESEARCH METHODOLOGY
3.1 Introduction
This chapter comprised of the research design, target population, sampling design
and sample size, data collection instruments, pilot study, data collection
This study employed a descriptive research design. According to Kothari (2004) descriptive
research design is recommended for studies that are concerned with specific predictions, with
Cooper and Schindler (2003), a descriptive study is concerned with finding out what, where
and how of a phenomenon. Descriptive research includes survey and fact finding inquiries
and is applied where the study is using comparative variables in the field of study and the
case at hand has no control over the variables and the researcher can only report on what
happened or what is happening (Mathooko et al., 2011). Descriptive research design was
provided quantitative data from cross-section of the chosen population. The study sought to
19
performance.
research. The target population in this study was three selected manufacturing
Finance Department 3 84 87
Procurement Department 3 28 30
20
Sampling procedures refers to how cases are to be selected for observation. It
how these are to be selected from the target group. Stratified sampling was used to
sample the respondents from the selected four departments (finance, human
resource, CT and procurement). A census method was used to select the managers
21
3.4.2 Sample Size
The study of sample size involves two firms because they were already accessible to the
researcher thus minimizing the study cost and reduce time spent for data collection.
Table 1
Equator Bottle 20 40 6 66
From the population size per firm 30% of the two firms sample per department were selected
to allow for full representation of all groups in the entire firm total selected sample 75 as shown.
United millers 5 20 5 40
Equator 12 10 13 35
Total 17 40 18 75
18
3.5 DATA COLLECTION METHODS
The data collection instrument are tool used for collection data during study .The
study only the questionnaire it's the most preffered as being economical in as for
3.5.1 Questionnaires
information while section B-f were structure to measure each of the study objective
The research got an introductory letter from the department of business and
presents it to the National Commission for Science and Technology and Innovation
organization was informed on the data collection period. The researcher hired two
questionnaire from the sample respondent during the data collection the researcher
19
The data of the study was from primary source which involved the use of structure
20
CHAPTER 4: DATA ANALYSIS , FINDINGS CONCLUSION AND
RECOMMENDATION.
4.1 Introduction
This chapter is a presentation of results and findings obtained from the field of responses and
data, broken into two parts. The first section discusses the background information of the
respondents, while the other sections present findings of the analysis. The study used descriptive
and inferential statistics in the analysis and discussed the issues in the best way possible.
Out of 120 questionnaires which had been administered to the interviewees, 88 of them were
returned for analysis. This translates to 73 percent return rate of the respondents. Overall, the
response rate can be considered to have been very high as shown in table 4. According to
Mugenda and Mugenda (2003) a 50% response rate is adequate, 60% good and above,70% rated
very good. This also corroborates Bailey (2000) assertion that a response rate of 50% is
adequate, while a response rate greater than 70% is very good. This implies that based on this
21
Response rate Frequency Percent
Returned 88 73
Not returned 32 27
22
4.2.2 Organization in the Study
The organizations
. The respondents attributed in the staff
to the study are shown
working below. The figure
in the procurement, finance 4 shows the organizations
that respondents in this worked, 65% were of the respondents were from united Miller's,while
And operations departments in the selected manufacturing organizations. United Miller's had
the least number of staff respondents (25%) mostly from procurement filling the questionnaires,
while Equator bottles had more staff respondents (45%) offering information in relation to the study
objectives.
Figure 4
The study sought to find out which position the respondent held in the organization. The
Figure 5 below shows the results. Majority of the respondents were junior clerks (68.77%),
Followed by senior officers who were 11.14% and managers who were 9.10% of the respondents.
The manager’s response can be attributed to the busy schedule they have in their work schedule
30
23
Organization in study
24
Thus, having limited time for data filling. The junior clerks were readily available because of the
limited duties they have at work while others were flexible enough to meet after office hours for
FIGURE 5
JOB POSITION HELD
The study sought to establish how long the respondents had been working at their
respective organizations to ascertain to what extent their responses could be relied upon to make
conclusions for the study based on experience. From the study findings as indicated in figure 6,
majority (42%) indicated that they had been working at their respective organizations for a
period between 1-5 years, 31% indicated they had been working for 5-10 years, 23% for less
than 1 year a few (4%) indicated they had been working for a period more that 10 years. It can be
noted that the 31% of the respondents were mostly senior officers and managers who had
attributed that they had got promotions to senior ranks after working for over five years and had
furthered their studies which was a factor promoting the rise in ranks. The 23% of the
respondents who had worked for less than a year were procurement officers who had modern IT
skills which facilitated efficiency in e-procurement. It can be asserted that employee retention in
the manufacturing organizations was poor as only 4% of the respondents had worked over 10
years.
31
19
FIGURE 6
LENGTH OF TIME WORKED FOR THE ORGANIZATION
The study sought the number of employees from each of the organization in the study. As
shown in figure 7 below, 80% of the organizations had employees ranging from 200-300 while
20% of the organizations had employees ranging from 400-500. Of the five organizations
selected only EABL had the 20% employee ranging from 400-500. This implies that the market
demand for EABL products is more as compared to the products from other organizations.
FIGURE 7
NUMBER OF EMPLOYEES IN ORGANIZATION
100
80
60
40
20
0
less than 100 201-300 301-400 401-500
employees employees employees employees
32
20
4.3 System Controls in the Organization
The study established which systems were used by the company before the ERP
implementation. Figure 8 shows the response. Majority (80%) indicated that they used legacy
systems while a small no. (20%) indicated that they didn’t have any system. Many organizations
preferred the legacy system because the operators were familiar with the process and could easily
track any data because of continual usage. However, the maintenance and staffing cost of the
FIGURE 8
SYSTEMS USED BY THE COMPANY BEFORE ERP IMPLEMENTATION
Previous operating
system
20%
legacysystem
none
80%
4.3.2 Main challenges the company faced with the old system
The study sought to determine the main challenges faced in the company. The response
33
21
TABLE 5
As shown in Table 5 above, 88% of the respondent felt that bloated purchasing
department, 77% identified slower and less flexible purchasing process, 82% indicated that
maverick buying, 81% identified higher clerical and administrative cost as a challenge, 85% of
the respondents felt that high process inaccuracy due to high manual component was a challenge
in their organizations. 89% identified bigger space required to archive fiscal documentation as a
challenge. 76% found less efficient process as a challenge and 72 % indicated that not being able
The study sought to determine which ERP systems the organizations in the study used.
The responses are displayed in the figure 9 below; 60% of the organizations used SAP R/3, 20%
of the organizations use Iscala and another 20% use Navison financials. This implies that SAP
R/3 is the most preferred ERP system by many manufacturing organizations. SAP R/3 also is the
34
22
most advanced ERP system in the market currently serving both internal and external
FIGURE 9
ERP SYSTEMS USED IN YOUR ORGANIZATION
The study sought to find out the driving force for these organizations to adopt the ERP.
TABLE 6
35
23
As shown in Table 6 above, 80% of the respondents indicated that reducing direct operation cost
was a driving force for the organization, 86% identified quickened information response time as
a driving force, 93% indicated that improved order management, 98% identified that lowered
inventory levels was also a driving force. The study also found 82% of the respondents felt that
it helped increase interaction across enterprise and so making it a driving force, 91% indicated it
improved on time delivery, 97% being the highest response on any driving force being on
improved cash management. Eighty three percent indicated that it helped in interaction with
suppliers and 88% indicated it was driven by the ability to improve interaction with customers.
The study sought to find out whether the adoption happened was finished on time. The
figure 10 below shows the response from the respondents where the majority (60%) indicated it
was completed on time while 40% responded that it wasn’t adopted in time. The 40% attributed
challenges like lack of proper analysis of requirements during implementation and thereafter,
inadequate training of personnel’s and cost overheads. Majority attributed to completion on time
due to adequate support from senior management and good investment in infrastructure. The
organizations also did a proper analysis of the requirements thus had the essential functionalities.
This indicates that absence of senior management support may delay ERP implementation in an
organization
36
24
FIGURE 10
TIME FOR ADOPTION OFERP
The study sought to determine the cost of implementing an ERP system in these
organizations. The responses are shown in the figure 11. According to the findings 20% of the
organization had used cost ranging from Ksh 1-5 million, 60% of the organizations had used a
cost ranging from Ksh 5-10 million while 20% had used a cost of over 10 million. This implies
that the cost of ERP implementation is high and thus organizations with limited funds may not be
able to implement the system. The cost is related to the ERP software’s involved, planning,
customization and configuration which requires IT experts, testing and the actual
implementation.
37
25
FIGURE 11
TOTAL COST OF IMPLEMENTING THE ERP SYSTEM
Cost incurred
million
The study sought to determine which factors affect the implementation and adoption of
TABLE 7
As shown in Table 7 above, 89% identified skill and knowledge as a factor affecting the
implementation and adoption of ERP systems, 91% indicated that budgetary allocation does
affect the implementation of ERP systems, 76% identified top management support as a factor.
Lastly the respondents (93%) indicated that firm size does act as a factor affecting the
38
1
TABLE 8
From the results in the Table 8 above 59% indicated that IT infrastructure did lead to ERP
systems, 25% indicated that information security also lead to the implementation of the ERP
systems and 16% of the respondents identified the rapid change of technologies.
The study sought to find out the extent in which ERP system meets the overall needs of
the organization. The figure 12 below shows how the majority (75%) felt that it met the needs to
a larger extent while 25% felt it met to lesser extent. The majority cited that ERP offered
complete visibility of all the important processes across various departments, reduced costs of
departmental software’s, created an automatic and coherent flow from one department to another
and some ERP systems like Sap R/3 provided business intelligence functionalities. On the hand
however, the 25% of the respondent cited the ERP deployments were highly time consuming and
the cost of ERP software, planning and customization were too high. The fact that ERP
implementation also made some organizations single vendors lock in limited organizations
39
2
FIGURE 12
The study put several statements to investigate the areas in which the organizations had
cost saved. The Table 4.6 below shows statements that aimed to investigate these areas.
TABLE 9
AREAS OF COST SAVINGS
1 2 3 4 5 Mean Std
Statement DEV
Procurement Cycle
0 0 0 38 62 4.6 0.26
Inventory Management
0 0 0 19 81 4.8 0.32
Contracts Management
0 0 10 29 62 4.6 0.24
The Table 9 above shows that a majority (62%) indicated that there organizations had saved cost
in the procurement cycle, 81% indicated a saving cost in inventory management while 62%
40
3
4 .4.3 Overall Benefits of Using ERP System
The study put several statements to investigate the benefits in which the organizations
had acquired in using an ERP system. The Table 4.7 below shows statements that aimed to
TABLE 10
OVERALL BENEFITS OF USING ERP SYSTEM
1 2 3 4 5 Mean Std
Statement DEV
As shown in Table 10 above, reliable information was the most overall benefit (70%) of the ERP
system in the selected manufacturing companies while global outreach had the least (5%) benefit
. ERP system reduced costs by 59%, enhanced e-business by 41% contributed to delivery and
cycle time reduction by 39% and was easily adaptable by 31%. This implies that ERP systems
The study sought to find out how the ERP system works in this organization and the
response was as follows. Request starts from the customer or user through e-business which is a
software fitted to customers linking them with Tetra Pak to be able to: View prices (quotes),
41
4
view physical stocks from spare parts stores, view their credit financial status, view order status
and follow-up, send orders on-line to Tetra Pak spare parts sale points overseas, receive order
acknowledgement, receive out bond deliveries (parking list), and monitor order status (progress)
order acknowledgement is triggered in outlook indicating an order received from the customer:
Lu (2011) defines an order confirmation as a triggered system based in SAP R/3 generating a
unique number to the order which is also sent to the customer on email as a notification as well.
In SAP R/3 inbox, any order request without issues was triggered straight in creating an out bond
delivery and creating a purchase order. When items are in stock, an out bond delivery is created,
and if not, the system automatically created a purchase order to where it is available in Tetra Pak
sale points i.e. Tetra Pak Dubai, Tetra Pak Sweden (HQ). This is possible since the entire Tetra
Pak sale / buying points are connected in the same data base worldwide:
If items are available, using the out bond delivery produced by the system, the storekeeper /
spare parts administrator picks items from the store, confirming with the order out bond delivery
then goes to SAP R/3 to generate and produce the out bond delivery. After executing, the system
prompts the customer that goods are ready for collection of which an invoice is generated and
accompanies the items during collection. A purchase order for the item is created online when
items are not in stock. At this point, the purchasing administrator opens the respective purchase
orders in SAP R/3 to check for special conditions from the customer i.e. urgency, lead time,
delivery terms. This is to enable the purchaser be able to execute those specific special
conditions before the order is transmitted to the supplier. Changes can also be on quantities
42
5
Once the purchaser is satisfied that the order is okay, he clicks save and the order is
automatically sent to the suppliers and he gets an email notification of the same. The system
triggers an order confirmation online after an order is sent and received. This then updates on the
order of the dispatch dates against the respective items ordered followed by an out bond delivery.
The purchasing administrator can be able to view in SAP R/3 all this information by opening the
respective orders. The systems prompts the supplier on email to release items on its date of
dispatch, thereafter, a shipping notification is released online followed with an invoice generated
immediately on the same date. An invoice notification is also sent on email to the purchasing
administrator. It is important to note that if the items are for customers outside Kenya, the items
are sent direct to the customer. The purchasing administrator conveys the supply information on
email or on phone with details i.e. AWB (Air Way Bill) which shows the delivery details.
On the arrival in the airport, Tetra Pak Purchasing Administrator creates an invoice for
the buyer (customer) with Tetra Pak Kenya own terms i.e. local prices which have the mark-up
and VAT, which is sent to the customer, then Tetra Pak credit controls follows for payment
based on agreed terms and conditions, and at the same time Tetra Pak Kenya pays Tetra Pak
Global as per set company group rules. The same process is followed for replenishment of local
stocks for selling to customers as per need and request of which goods receipts has to be done in
SAP R/3 under MIGO goods receipts to reflect actual stocks received.
As shown in Table 11 below, the major areas that ERP covered were; customer
relationship management (4.7), sales and distribution management (4.7 and production
management (4.6). The least covered areas by the ERP system were human resource
management (3.7), accounting management (3.6) and financial management (3.6). This implies
43
6
that ERP system were more efficient in serving both external stakeholders who are customers
and internal stakeholders that is production. However, the internal system like human resource
management and accounting management were not adequately covered by ERP as compared to
TABLE 11
MODULES COVERED BY YOUR ORGANIZATIONS ERP SYSTEM
1 2 3 4 5 Mean Std
Statement DEV
Accounting management
0 0 0 37 63 3.6 0.16
Financial management
0 0 0 29 71 3.7 0.18
Manufacturing management
0 0 0 29 62 4.6 0.24
Production management
0 0 0 44 56 3.9 0.18
Transportation management
0 0 0 21 79 4.1 0.22
Sales & distribution management
0 0 0 31 69 4.7 0.05
Human resources management
0 0 0 25 75 3.7 0.18
Supply chain management 0 0 0 34 66 4.1 0.22
Customer relationship management
0 0 0 20 80 4.7 0.05
The section below presents a regression analysis of the study variables namely; Control
44
7
TABLE 12
An inverse model was applied in determining the relationship between the effects of system
controls of Enterprise Resource Planning and procurement efficiency. Results in table 12 above
indicate that the system controls was efficient. This finding was supported by an R Squared of
0.366. An R Squared of 0.366 indicates that 56.6% of variation in system control of ERP affects
procurement efficiency.
TABLE 13
Regression results in Table 13 indicate that the inverse of system controls of ERP is positively
value = 0.003). The relationship was significant at 0.05 critical value since the reported p value
0.003 was less than the critical value of 0.05. An increase in system controls of ERP by one unit
45
8
4.6.2 Cost saving
TABLE 14
An analysis was done to determine the relationship between the effects of cost saving of
Enterprise Resource Planning and procurement efficiency. Result in table 14 indicates that the
cost saving was not effective with regard to procurement efficiency. This finding was supported
by an R squared of 0.053.An R squared of 0.053 indicates that 5.6% variation in the cost saving
on procurement efficiency. This implies that ERP system was not cost effective with regard to
procurement efficiency
TABLE 15
ANALYSIS OF VARIANCE OF COST SAVING
An Analysis of Variance (ANOVA) results in Table 15 indicates that the overall model was
significant. This was supported by an F statistic of 9.216 (p value = 0.003). The ANOVA results
demonstrated that the independent variable (cost saving) affected procurement efficiency.
46
9
TABLE 16
REGRESSION COEFFICIENTS OF COST SAVING
Unstandardized Standardized
Model Coefficients Coefficients t Sig.
B Std. Error Beta
1 (Constant) 2.875 .256 11.211 .000
Cost effectiveness .212 .070 .230 3.036 .003
Regression results in Table 16 indicate that the inverse cost of ERP system is positively related
0.003). The relationship was significant at 0.05 critical value since the reported p value 0.003
was less than the critical value of 0.05. An increase in cost effectiveness by one unit leads to a
efficiency was done. Results in table 17 indicate that the process flexibility was effective with
squared of 0.685 indicates that process flexibility of ERP system was 68.5% effective in
procurement efficiency.
47
10
TABLE 18
ANALYSIS OF VARIANCE OF PROCESS FLRXIBILITY
Model Sum of Squares df Mean Square F Sig.
1 Regression 2.057 1 2.057 15.303 .000a
Residual 22.181 165 .134
Total 24.238 166
Results in Table 18 present an Analysis of Variance (ANOVA). Results indicate that the overall
model was significant. This was supported by an F statistic of 15.303 (p value = 0.006). The
ANOVA results demonstrated that the independent variable process flexibility affects
TABLE 19
Unstandardized Standardized
Model Coefficients Coefficients t Sig.
B Std. Error Beta
1 (Constant) 2.928 .186 15.726 .000
Process flexibility .893 .050 .291 3.912 .006
Regression results in Table 19 indicate that process flexibility in ERP system affected
procurement efficiency in a positive way. This was evidence by a regression coefficient of 0.893
(p value = 0.006). The relationship was significant at 0.05 critical value since the reported p
value 0.006 was more than the critical value of 0.05. This indicates that process flexibility in the
TABLE 20
48
11
MODEL OF FASTER PROCESS
efficiency was done. Results in table 20 indicate that the faster process was positively effective
with regard to procurement efficiency. This finding was supported by an R squared of 0.832. An
R squared of 0.832 indicates that faster process of ERP system contributed to 83.2% in
procurement efficiency.
TABLE 21
ANALYSYS OF VARIANCE OF FASTER PROCESS
Model Sum of Squares df Mean Square F Sig.
1 Regression 3.167 1 3.167 15.303 .000a
Residual 24.181 172 .134
Total 27.134 169
Results in Table 21 present an Analysis of Variance (ANOVA). Results indicate that the overall
model was significant. This was supported by an F statistic of 15.303 (p value = 0.006). The
ANOVA results demonstrated that the independent variable process flexibility affects
TABLE 22
Unstandardized Standardized
Model Coefficients Coefficients t Sig.
49
12
Unstandardized Standardized
Model Coefficients Coefficients t Sig.
B Std. Error Beta
1 (Constant) 2.928 .186 15.726 .000
Faster process .973 .050 .291 3.912 .006
Regression results in Table 22 indicate that faster process ERP system affected procurement
efficiency in a positive way. This was evidence by a regression coefficient of 0.213 (p value =
0.008). The relationship was significant at 0.05 critical value since the reported p value 0.008
was more than the critical value of 0.05. This indicates that faster process in the ERP system
enhances procurement efficiency more effectively.
50
13
4.7 FINDING
That enterprise resource planning enable companies to break down traditional organization, they
have replace them with a tightly integrated horizontal structure by using integration technology
An enterprise resource planning enable most companies to forecast accuracy time delivery
and performance against date logistics and planned performance, in practice many metrics and
3. To establish relation between enterprise resource planning System and organization supply
chain performance.
4.8 CONCLUSION.
The study findings indicates that enterprise resource planning process has met 65% of the
The most are covered were customer relation management .80% both internal and external
customer relations needs had been well taken care by the system leading to faster process in the
14
procurement.
4.9 RECOMMENDATIONS
The study recommends that the top management should provide the necessary resource in terms
of leadership financial support, to management may also be involve monitoring and evaluating
The key performance indicator are patient part of measuring the success and failure of the
companies, it’s also allow companies owner and manager to get overview of individual
department is performing at any given time. its also recommend that enterprise resource planning
can improve a company business performance by developing the most efficient way to plan and
schedule resource and optimize productivity, it can also offer data visibility to user customer and
vender allowing them to view data in real time and improve relationship in all aspect of your
business.
15
REFERENCES
Journal,1(2)
Akoth,M.(2014).E-ProcurementandOrganizationalPerformanceofNon-
GovernmentalOrganizationsinNairobi,Kisumucounty.UnpublishedMBA
Exchange .JournalofManagementResearch,4(2),266.
International Journal,2(5),99-110.
practices. InternationalJournalofProjectManagement,26(1),44-50.
16
Cooper,D.R. &Schindler,S., (2011).Survey design. Thousand Oaks, CA: Sage
ServiceDelivery,Trivandrum,India,December,11-13.
Dobni, C. B. (2012).Theinnovationblueprint.BusinessHorizons,49(4),329-339.
ICIS,Washington,UnitedStates.
Technology,66,418–423.
Gibson, B. J., Mundy, R.A., Sink, H. L., (2012). Supplier certification: application
to
17
Retrieved: atwww.apsea.or.ke/.../76-report-of-presidential-taskforce-
on-parastatal- reforms
Working Paper Series, Paper No. 11, Manchester, UK: IDPM, University
of Manchester. Available
at:http://hasp.axesnet.com/contenido/documentos/eGovernance%20for
%20Development%20UNPAN.pdf(accessed29June2013)
Hunton,J.E.,LippincottB.,ReckJ.L.,
ofAccountingInformationSystems,4
Hunton,J.E.,Lippincott,B.,&Reck,J.L.
InternationalJournalofAccountingInformationSystems,4, 165-184.
18
Kakwezi,P.,&Nyeko,S. (2010).Procurement processes and performance:
3,2011.
county.
county.
International.Kumar,S.,&Keshan,A.
(2009).ERPimplementationinTatasteel:focusonbenefitsandROI.
JournalofInformationTechnologyCaseand ApplicationResearch,11(3),68-103.
19
APPENDICES
APPENDIX 1
QUESTIONNAIRE
Kindly fill the questionnaire and tick where appropriate. The information provided will be
-------------------------------------------------------------------------------------------------------
-------------------------------------------------------------------------------------------------------
Manager
Senior Officer
Junior Clerk
Packaging material
Alcohol Beverages
Food Products
-------------------------------------------------------------------------------------------------------
1
Between 1 and 5 years
51 – 200 employees
Legacy systems
None
9. What two main challenges did the company face with the old system?
64
2
vi. Bigger space required to archive fiscal documentation.
viii. Could not perform some advanced functions i.e. send orders online, online order
SAP R/3
Oracle
Ariba
11. What was the driving force in terms of benefits motivated your firm to adopt ERP system in
------------------------------------------------------------------------------------------------------
65
3
------------------------------------------------------------------------------------------------------
12. Was the project of adopting ERP system in your organization completed on time?
Yes No.
13. What was the total cost of implementing the ERP System you are using?
1 mio – 5 mioKes
14. Did the actual budget of ERP implementation exceed the planned budget?
Yes No.
15. From the following organizational and relational factors, tick the ones that mostly affect the
i. Firm’s size
v. Others(Please Specify)
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
66
4
16. Choose the technological factors that lead to ERP System implementation.
i. IT infrastructure
17. To what extent has the ERP system met the overall needs of your department?
Larger Lesser
18. What savings has your organization generated in the adoption of ERP System?
-------------------------------------------------------------------------------------------------------
-------------------------------------------------------------------------------------------------------
-------------------------------------------------------------------------------------------------------
-------------------------------------------------------------------------------------------------------
-------------------------------------------------------------------------------------------------------
-------------------------------------------------------------------------------------------------------
19. Which of the following areas of cost savings is your organization focusing brought about by
Please us the scale below to rank your opinion. 1 –Not at all; 2 - to a less extent; 3 –to a
Procurement Cycle
Inventory Management
Contracts Management
67
5
Others (Please Specify)
-------------------------------------------------------------------------------------------------------
-------------------------------------------------------------------------------------------------------
20. What are the overall challenges of using ERP system in your organisation?
-------------------------------------------------------------------------------------------------------
-------------------------------------------------------------------------------------------------------
-------------------------------------------------------------------------------------------------------
-------------------------------------------------------------------------------------------------------
-------------------------------------------------------------------------------------------------------
-------------------------------------------------------------------------------------------------------
-------------------------------------------------------------------------------------------------------
-------------------------------------------------------------------------------------------------------
-------------------------------------------------------------------------------------------------------
-------------------------------------------------------------------------------------------------------
22. In your opinion do you think the use of ERP systems has any benefits on the following areas?
Please indicate your choice of answer to the question by marking the preferred box.
Disagree Agree
Cost reduction
68
6
Easy adaptability
Improved maintenance
Global outreach
E-Commerce, e-business
-------------------------------------------------------------------------------------------------------
-------------------------------------------------------------------------------------------------------
-------------------------------------------------------------------------------------------------------
23. Describe your e-procurement process using the ERP system in place.
-------------------------------------------------------------------------------------------------------
-------------------------------------------------------------------------------------------------------
-------------------------------------------------------------------------------------------------------
-------------------------------------------------------------------------------------------------------
-------------------------------------------------------------------------------------------------------
-------------------------------------------------------------------------------------------------------
24. Which of the following areas (modules) does your organizations ERP system cover?
Please us the scale below to rank your opinion. 1 –Not at all; 2 to a less extent; 3 –to a
Accounting management
Financial management
69
7
Manufacturing management
Production management
Transportation management
8
70