Professional Documents
Culture Documents
Cipry - Short Status For Loan and Grant Projects July 2023
Cipry - Short Status For Loan and Grant Projects July 2023
Contractor / Original Contract Starting Completion Contract Revised Contract Issuance of Project Saving in Total Gender Based
No. Name of Project Progress (%) Issuance of PC Status of Essential documents Environmental Issue Resettlement Issue Outstading issue
Consultant Amount Date Date Amendment Amount TOC Contigency Item Disbursement Violance
On-going Projects
National Road No.1 Upgrading Project Sinohydro $ 3,355,671.24 as Performance security for PBM & Project Completion
$48,314,975.87 100.00 30-Jul-16 24-Feb-21 VO#2, CA#3 24-Feb-21 24-May-22 1.8 Mil of PBM covered by IF 42,506,025.29 completed
Dili - Manatuto (Package A01-01) per As-built report
1
Sta.7+660 to Sta.56+400 (Loan
JICA /TLS-P1)
Nippon Koei /
TST performing consultant tasks
TST
Nippon Koei /
TST performing consultant tasks
TST
VO#4 due to EOT 45days, was approved by Km. 58 need to use contigency for repaired the failures,
ADB on 18 may 2022, EOT DLP was extended km. 59+430 landslide & km 61+915 the slide material
Road Network Upgrading Sector $ 1,571,451.47 as
CBMI $20,748,566.21 99.40 5-Sep-17 5-Sep-21 VO#2, CA#1 20-Oct-21 until February 2023 and 2nd extention of DLP 17,764,636.09 completed pushed line dithc became narrow. Prepare to CAFI,
Project (additional financing) - per As-built
until 20 September 2023, first half retention Engineer has extended the DLP period to September
Upgrading and Maintenance of
4 money released 2023 for the completion of the work mentioned.
Maubara to Karimbala and Atabae to
Mota Ain Roads (ADB LOAN 3341 /
3342)
Road Network Upgrading Project VO#3, As-built docs. approved and NOL was
$ 5,069,974.47 As- Total: 72 APs Paid:
(Additional Financing – European Shanghai CG $5,083,696.15 100.00 18-May-18 9-Nov-19 9-Jun-20 to be issued (13,721.68) issued by ADB on 23-Feb-2022 and approved by mineral Tax issues - issue PC and Defects repair
built 72 Aps Unpaid: 0
Union) EUF District Roads MPW.
8 Rehabilitation and Maintenance
Project, C16/17, PACKAGE 1
AIPELO - BAZARTETE (L= 13.50
KM) (EU Grant No. 0504 TIM EF) KCI / TST Performed by TST
Road Network Upgrading Project Environmental License valid Total: 100 APs
(Additional Financing – European $6,207,902.71 as
Shanghai CG $5,730,438.78 67.66 21-May-19 30-Jun-23 Amentmend No. 2 signed on 13 january 2023 2,661,832.85 until 26-dec-2023, mineral Paid: 100 Aps Slow progress
Union) EUF District Roads per VO#2
Tax issues Unpaid: 0
Rehabilitation and Maintenance
9
Project, C16/17, Package 2 :
BAZARTETE - TOKOLULI Road
(L=16.025km) (EU Grant No. 0504
TIM EF) KCI /TST Performed by TST
$ 13,871.83 as As-built document was approved by VMPW on 5 no activity no need extend the Total: 27 APs Paid: Statement at completion has submitted to PMU,
China Wu Yi $12,964,487.49 100.00 28-Feb-17 30-Apr-21 5-Jul-22 11,143,038.31
per As-buil Jul 2022 license 27 Aps Unpaid: 0 processing of first half retention money, landslide issue
Road Network Upgrading Project
10 Section 2 – Tasitolu - Tibar Road
(ADB Loan 3181)
Council of Minister approved, now send to NPC
Katahira / TST $1,944,673.12
to prepare contract amendment
$ 331,330.63 as As-built docs. Was approved by VMPW on 5 24-Nov-2022 valid of Final Payment done and release retention money required
CNI22 $34,379,729.54 100.00 16-Mar-15 20-Nov-19 8-Nov-19 7-Nov-21 30,224,302.04
Upgrading and Maintenance Laclubar per As-built July 2022 contractor camp more justification of 7 damages
Junction - Natarbora Road Sta.
13
100+360 - 144+995 (ADB Loan
3020/3021)
contract amendment sent to Court of Audit for
Sinotech
VISA
Completed Projects
Upgrading and Maintenance of the Dili PBM period has expired on February 2022, Road
CICO $26,875,070.79 100.00 21-Aug-15 31-May-19 21-Feb-19 21-Feb-20
Ainaro Road, Lot 5: Aituto - Ainaro handed over to DRBFC on 9-Mar-22
16
Section (km 89+000 - 112+000) (IBRD
Loan No. 8290-TL) EGIS the contract completed
Upcoming Projects
22
ADB has provided NOL for the submitted
consultancy Services Contract and Expression
Supervision of 3 Bridges
date is 14 November 2022, supervision
Consultant will be on board on February 2023
Network Data Collection Issued RFP to the first rank PMU is evaluating the RFP