The document provides a work plan for civil works until November 18, 2023. It lists various construction items, their weight, planned progress, and current status. Many items are delayed or only partially completed. The cumulative planned progress is 12% but actual progress achieved so far is only 5.24%, resulting in a negative deviation of -6.76%.
The document provides a work plan for civil works until November 18, 2023. It lists various construction items, their weight, planned progress, and current status. Many items are delayed or only partially completed. The cumulative planned progress is 12% but actual progress achieved so far is only 5.24%, resulting in a negative deviation of -6.76%.
The document provides a work plan for civil works until November 18, 2023. It lists various construction items, their weight, planned progress, and current status. Many items are delayed or only partially completed. The cumulative planned progress is 12% but actual progress achieved so far is only 5.24%, resulting in a negative deviation of -6.76%.