Rencana Pekerjaan Civil sampai dengan 18 November 2023

NO ITEM PEKERJAAN Week 46 Status


BOBOT Plan
A. PREPARATION 2.47% 50.0%
3 POWER PLAN BUILDING
- Beton K- 300 0.27% 100.0% Delay
- Besi (SNI) 0.08% 100.0% Delay
- Bekisting 0.05% 100.0% Delay
- Grouting tebal 5 cm 0.03% 0.0%
b Tie Beam
- Beton K- 300 0.52% 0.0%
- Besi (SNI) 0.15% 100.0% On Progress
- Bekisting 0.31% 85.7% On Progress
c Pekerjaan Slab tebal 250 mm pada El. 0M000
- Beton K- 300 2.49% 0.0%
- Wiremesh M10 (2 Layer) 0.86% 100.0% On Progress
- Bekisting 0.17% 85.7% On Progress
b Pekerjaan Kolom
- Beton K- 300 0.38% 45.5% Delay
- Besi SNI 0.19% 54.5% Delay
- Bekisting 0.41% 50.0% Delay
c Pekerjaan Tie Beam
- Beton K- 300 0.16% 0.0%
- Besi SNI 0.02% 100.0% On Progress
- Bekisting 0.12% 85.7% On Progress
d Pekerjaan Pondasi Beam (elv.+7.00)
- Beton K- 300 0.18% 0.0%
- Besi SNI 0.72% 0.0%
- Bekisting 0.24% 0.0%
e Pekerjaan Beam Elv. +7.00
- Beton K- 300 0.43% 0.0%
- Besi SNI 1.26% 18.2% On Progress
- Bekisting 0.57% 18.2% On Progress
f Pekerjaan Slab (elv.+7.00)
- Beton K- 300 1.20% 0.0%
- Besi SNI 2.14% 18.2% On Progress
- Bekisting 0.13% 18.2% On Progress
6 Pekerjaan Pondasi ESP
- Beton K- 300 0.09% 100.0% Already Done
- Besi SNI 0.00%
- Bekisting 0.03% 100.0% Already Done
7 Pekerjaan Pondasi CHIMNEY
- Galian 0.00% 100.0% Already Done
- Urugan 0.01% 100.0% Already Done
- Cutting Pile 0.03% 100.0% Already Done
- Beton berulang penutup / pengisi tiang pancang 0.03% 100.0% Already Done
- Beton Lantai Kerja 0.01% 100.0% Already Done
- Beton K- 300 0.15% 100.0% Delay
- Besi SNI 0.67% 100.0% Delay
- Bekisting 0.04% 100.0% Delay
CEMS Analysis Room 0.00%
Pondasi & Sloof 0.00%
- Galian 0.02% 100.0% Already Done
- Urugan 0.01% 100.0% Already Done
- Beton Lantai Kerja 0.00% 100.0% Already Done
- Beton K- 300 0.03% 100.0% Delay
- Besi SNI 0.06% 100.0% Delay
- Bekisting 0.03% 100.0% Delay
Slab thk = 250 mm
- Beton Lantai Kerja 0.02% 100.0% Delay
- Beton K- 300 0.09% 100.0% Delay
Rencana Pekerjaan Civil sampai dengan 18 November 2023
NO ITEM PEKERJAAN Week 46 Status
- Besi SNI 0.14% 100.0% Delay
- Bekisting 0.05% 100.0% Delay
8 Pekerjaan Pondasi Cooling Tower
- Galian 0.24% 100.0% Delay
- Urugan 0.20% 100.0% Delay
- Cutting Pile 0.07% 100.0% Delay
- Beton berulang penutup / pengisi tiang pancang 0.23% 100.0% Delay
- Beton Lantai Kerja 0.10% 100.0% Delay
- Beton K- 300 0.21% 100.0% Delay
- Besi SNI 0.24% 100.0% Delay
- Bekisting 0.11% 100.0% Delay
Pek. Sloof Uk. 300 x 500 mm (Elev. ± 0.000 M)
- Beton K- 300 0.31% 100.0% Delay
- Besi SNI 0.75% 100.0% Delay
- Bekisting 0.39% 100.0% Delay
Pek. Lantai Ruang Pompa - Thk = 150 mm (Elev. ± 0.000 M)
- Beton K- 300 0.38% 100.0% Delay
- Wiremesh M6-150 (2 Layer) 0.69% 100.0% Delay
Pek. Kolom Uk. 600 x 600 mm (From Elev. ± 0.000 up to Elv. 4.50 m)
- Beton K- 300 0.49% 0.0%
- Besi SNI 1.22% 41.7% Delay
- Bekisting 0.51% 25.0% Delay
- Besi SNI 0.59% 41.7% Delay
- Bekisting 0.27% 25.0% Delay
14 Pekerjaan ASH SILO
- Galian 0.03% 100.0% Already Done
- Urugan 0.02% 100.0% Already Done
- Cutting Pile 0.01% 100.0% Already Done
- Beton berulang penutup / pengisi tiang pancang 0.03% 100.0% Delay
- Beton Lantai Kerja 0.01% 100.0% Delay
- Beton K- 300 0.08% 100.0% Delay
- Besi SNI 0.14% 100.0% Delay
- Bekisting 0.08% 100.0% Delay
23 Pekerjaan Slab tebal 250 mm pada El. 0M000 (CHEMICAL TANK)
- Beton Lantai Kerja 0.04% 0.0%
- Beton K- 300 0.00% 50.0% Delay
- Wiremesh M10 (2 Layer) 0.29% 100.0% On progress
42 FUEL STORAGE BUILDING
a Pekerjaan Pondasi & Pedestal
- Galian 0.32% 16.7% Delay
43 OFFICE ADMIN
c Pekerjaan Slab tebal 150 mm pada El. 0M000
- Beton K- 300 0.22% 100.0% On Progress

Rencana Kumulatif 12.00%


Rencana 8.51%
Realisasi 2.30%
Realisasi Kumulatif 5.24%
DeviasiKumulatif -6.76%
Deviasi -6.21%