Building Estimation Step by Step In Excel Sheet

Dear friend, we work building quantity calculation in manual in a paper, So now going we area in how to Calculate in Excel use a long wall and
short wall method.

This long wall and short wall method is very easy to calculation in the estimation sheet. In this estimation excel sheet easy calution using a
excel formulas. In this article also attached construction cost estimate template excel sheet. so please see that.

Laminates contains plastics and resins. Some resins give off harmful gases. In this article, we calculate step by calculation as below.

Note: Free Download building construction estimate spreadsheet excel download UK, US, Canada, and also India.

Important Point

https://civiljungle.com/building-estimation-step-by-step-in-excel-sheet/ 1/21
1/16/23, 6:56 PM Building Estimation Step by Step In Excel Sheet

Following Quantities Are Building Estimation


Excavation
Footing P.C.C.
Footing R.C.C.
Column up to Plinth Level R.C.C.
Backfilling
Plinth Beam R.C.C.
Grae Slab R.C.C.
Column Up to Slab Level R.C.C.
Brick Masonry
In Side Plaster
Out Side Plaster
Celling Plaster
Slab R.C.C.
In Side Paint
Out Side Pint

Building Estimation
It is processed by predicting the probable cost of a project by calculating material quantity and their costing with help of market rates
before undertaking any construction project.

Or

A building estimator or cost estimator is an individual that quantifies the materials, labor, and equipment needed to complete
a construction project.

Building Estimate Format in Excel, Building Material Calculator Free Download – Download Excel Sheet

Building Estimation and Costing Excel Sheet – Download Excel Sheet

Also, read: How to Find House Construction Cost

1. Excavation
How to Find Excavation as Per Drawing

https://civiljungle.com/building-estimation-step-by-step-in-excel-sheet/ 2/21
1/16/23, 6:56 PM Building Estimation Step by Step In Excel Sheet

Footing excavation work needs sum drawing like Footing location Drawing and Section Drawing. All drawing as per below, please see

Section A-A

https://civiljungle.com/building-estimation-step-by-step-in-excel-sheet/ 3/21
1/16/23, 6:56 PM Building Estimation Step by Step In Excel Sheet

Footing Location

In this plan, 11 footings as per drawing.

Length = 0.6m + 1.0m + 0.6m = 2.20m

Here 0.6 m is working space in footing for both sides.

And,1.0 m = footing size

As per follows table format copy of the building estimate excel sheet.

QUANTITY SHEET

Widht/ Height/
Length
Sr. No. Item Description No. Breadth Depth Quantity Unit
(m)
(m) (m)

Earthwork in Excavation in
1
Foundation:

Footing (1m x 1m) 11 2.200 2.200 1.580 84.12 Cu.m.

Depth From GL = 0.6 + 1 + 0.6

0.6 =Extra For working space

Total Qty= 84.12 Cu.m.

Also, read: What Is Slab Beam / Hidden Beam / Concealed Beam | Advantage and Disadvantage

2. Footing P.C.C.
How to Find Footing P.C.C. as Per Drawing
In this plan, 11 footings as per drawing.

Length = 0.15m + 1.0m + 0.15m = 1.30m

https://civiljungle.com/building-estimation-step-by-step-in-excel-sheet/ 4/21
1/16/23, 6:56 PM Building Estimation Step by Step In Excel Sheet

Here 0.15 m = P.C.C. working space in footing, for both side

And,1.0 m = footing size

QUANTITY SHEET

Widht/ Height/
Length
Sr. No. Item Description No. Breadth Depth Quantity Unit
(m)
(m) (m)

2 Footing P.C.C.

Footing (1m x 1m) 11 1.300 1.300 0.075 1.39 Cu.m.

Thickness = 0.075

D = 0.150 + 1.0 + 0.150

Total Qty= 1.39 Cu.m.

3. Footing R.C.C.
How to Find Footing R.C.C. as Per Drawing
In this plan, 11 footings as per drawing.

Length = 1.0m = 1.0m

Here Height = 0.450 m

And, 1.0 m = footing size

QUANTITY SHEET

Widht/ Height/
Length
Sr. No. Item Description No. Breadth Depth Quantity Unit
(m)
(m) (m)

3 Footing R.C.C.

Base(1m x 1m) 11 1.000 1.000 0.450 4.95 Cu.m.

Thickness = 0.450

Total Qty= 4.95 Cu.m.

https://civiljungle.com/building-estimation-step-by-step-in-excel-sheet/ 5/21
1/16/23, 6:56 PM Building Estimation Step by Step In Excel Sheet
Also, read: Difference Between CPM and PERT/PERT Vs CPM | What Is CPM & PERT

4. Column up to Plinth Level R.C.C.


How to Find Column up to Plinth Level R.C.C. as Per Drawing

In this plan, 11 footings as per drawing.

Length = 0.230 m, Breadth = 0.230 m

Here Height = 1.05 m

Section A-A

QUANTITY SHEET

https://civiljungle.com/building-estimation-step-by-step-in-excel-sheet/ 6/21
1/16/23, 6:56 PM Building Estimation Step by Step In Excel Sheet

Widht/ Height/
Length
Sr. No. Item Description No. Breadth Depth Quantity Unit
(m)
(m) (m)

Column up to Plinth Level


4
R.C.C.

Column 11 0.230 0.230 1.050 0.61 Cu.m.

Total Qty= 0.61 Cu.m.

5. Backfilling
How to Find Backfilling as Per Drawing
Footing backfilling qty for 11 Qty

Length & Breadth = 2.2 m, Height Footing Bottom to ground level = 1.580 mm

Backfilling = Excavation – Footing P.C.C – Column R.C.C

Plinth Beam Backfilling

Height of backfilling = 0.600 m

Total plinth beam backfilling = Total Area – Plinth beam

QUANTITY SHEET

Widht/ Height/
Length
Sr. No. Item Description No. Breadth Depth Quantity Unit
(m)
(m) (m)

5 BackFilling

5.a Backfilling In Footing

Excavation Area 11 2.200 2.200 1.580 84.12 Cu.m.

Deduction

Footing P.C.C. -11 1.300 1.300 0.075 -1.39 Cu.m.

https://civiljungle.com/building-estimation-step-by-step-in-excel-sheet/ 7/21
1/16/23, 6:56 PM Building Estimation Step by Step In Excel Sheet

Footing R.C.C. -11 1.000 1.000 0.450 -4.95 Cu.m.

Footing Column -11 0.230 0.230 1.050 -0.61 Cu.m.

5.a Total Qty= 77.16 Cu.m.

5.b Plinth Beam Backfilling

Plinth area out to out 1 10.240 7.690 0.600 47.25 Cu.m.

Deduction

L-1 -3 10.240 0.230 0.600 -4.24 Cu.m.

L-2 -4 3.000 0.230 0.600 -1.66 Cu.m.

L-3 -3 4.000 0.230 0.600 -1.66 Cu.m.

L-4 -1 1.500 0.230 0.600 -0.21 Cu.m.

L-5 -1 2.315 0.230 0.600 -0.32 Cu.m.

5.b Total Qty= 39.17 Cu.m.

5.a + 5.b Total Qty= 116.33 Cu.m.

Also, read, Rate Analysis of Brick Masonry

6. Plinth Beam R.C.C.


How to Find Plinth Beam R.C.C. as Per Drawing

https://civiljungle.com/building-estimation-step-by-step-in-excel-sheet/ 8/21
1/16/23, 6:56 PM Building Estimation Step by Step In Excel Sheet

Lintel Beam

As per lintel beam drawing, L-1 = 3 nos., L-2 = 4 nos., L-3 = 3 nos., L- 4 = 1 nos, L-5 = 1 nos of qty and length

and beam size = 0.230 m x 0.600 m

QUANTITY SHEET

Widht/ Height/
Length
Sr. No. Item Description No. Breadth Depth Quantity Unit
(m)
(m) (m)

6 Plinth Beam R.C.C.

Beam (230 mm x 600 mm)

L-1 3 10.240 0.230 0.600 4.24 Cu.m.

L-2 4 3.000 0.230 0.600 1.66 Cu.m.

L-3 3 4.000 0.230 0.600 1.66 Cu.m.

L-4 1 1.500 0.230 0.600 0.21 Cu.m.

L-5 1 2.315 0.230 0.600 0.32 Cu.m.

Total Qty= 0.32 Cu.m.

7. Grae Slab R.C.C.


How to Find Grae Slab RCC as Per Drawing
Grae Slab RCC = ( Total Length x Total Breadth x Thickness ) – Column

Grae Slab RCC = ( 10.240 x 7.690 x 0.100 ) – ( 11 x 0.230 x 0.230 x 0.100)

https://civiljungle.com/building-estimation-step-by-step-in-excel-sheet/ 9/21
1/16/23, 6:56 PM Building Estimation Step by Step In Excel Sheet

Grae Slab RCC = ( 7.87 ) – (0.06)

Grae Slab RCC = 7.82 Cu.m.

QUANTITY SHEET

Widht/ Height/
Length
Sr. No. Item Description No. Breadth Depth Quantity Unit
(m)
(m) (m)

7 Grae Slab R.C.C.

Plinth area out to out 1 10.240 7.690 0.100 7.87 Cu.m.

Deduction

Column -11 0.230 0.230 0.100 -0.06 Cu.m.

Total Qty= 7.82 Cu.m.

8. Column Up to Slab Level R.C.C.


How to Find Grae Slab RCC as Per Drawing
Column Length & Breadth= 0.230 m

Height = Ground Slab – Ground Floor – Slab Beam

Height = 3 – 0 – 0.350 = 2.650 m

QUANTITY SHEET

Widht/ Height/
Length
Sr. No. Item Description No. Breadth Depth Quantity Unit
(m)
(m) (m)

Column Up to Slab Level


8
R.C.C.

Column 11 0.230 0.230 2.650 1.54 Cu.m.

Total Qty= 1.54 Cu.m.

Also, read: What Is Floating Slab| Floating Slab Construction | How to Build a Floating Slab | Advantages & Disadvantages Floating Slabs

9. Brick Masonry
How to Find Brick Masonry as Per Drawing

https://civiljungle.com/building-estimation-step-by-step-in-excel-sheet/ 10/21
1/16/23, 6:56 PM Building Estimation Step by Step In Excel Sheet

Plan

Elevation

https://civiljungle.com/building-estimation-step-by-step-in-excel-sheet/ 11/21
1/16/23, 6:56 PM Building Estimation Step by Step In Excel Sheet

Section

Brick masonry calculation uses a Long wall and Short wall method

All length as per drawing and height = 3.00 m – 0.35 m = 2.65 m.

QUANTITY SHEET

Widht/ Height/
Length
Sr. No. Item Description No. Breadth Depth Quantity Unit
(m)
(m) (m)

9 Brick Masonry

230 mm thick wall Brick


Masonry

Long Wall 3 10.240 0.230 2.650 18.72 Cu.m.

Shot wall-1 3 3.000 0.230 2.650 5.49 Cu.m.

Shot wall-1 1 3.000 0.230 1.200 0.83 Cu.m.

Shot Wall-2 3 4.000 0.230 2.650 7.31 Cu.m.

Deduction

Column -11 0.230 0.230 2.650 -1.54 Cu.m.

Window W -2 2.000 0.230 1.200 -1.10 Cu.m.

Window W1 -2 1.500 0.230 1.200 -0.83 Cu.m.

Window W2 -3 1.200 0.230 1.200 -0.99 Cu.m.

Window W3 -1 1.200 0.230 1.500 -0.41 Cu.m.

Door o -2 1.200 0.230 2.100 -1.16 Cu.m.

Door D -1 1.200 0.230 2.100 -0.58 Cu.m.

Door D1 -1 1.000 0.230 2.100 -0.48 Cu.m.

Door MS -1 2.000 0.230 1.200 -0.55 Cu.m.

Vent -1 0.900 0.230 0.600 -0.12 Cu.m.

Vent V1 -1 0.600 0.230 0.600 -0.08 Cu.m.

https://civiljungle.com/building-estimation-step-by-step-in-excel-sheet/ 12/21
1/16/23, 6:56 PM Building Estimation Step by Step In Excel Sheet

Total Qty 230 mm Thick Wall= 24.49 Cu.m.

115 mm thick wall Brick


Masonry

Bath Room 1 1.500 0.115 2.650 0.46 Cu.m.

Passage wall 1 2.315 0.115 2.650 0.71 Cu.m.

Deduction

Door D2 -2 0.750 0.115 2.100 -0.36 Cu.m.

Parapet Wall

Long Wall 2 10.240 0.115 1.000 2.36 Cu.m.

Shot Wall 2 7.460 0.115 1.000 1.72 Cu.m.

Total Qty 115 mm Thick Wall= 4.87 Cu.m.

10. In Side Plaster


How to Find In Side Plaster as Per Drawing
Sum Note Point for deduction

0.5 sq.m. below section is a full deduction


0.5 sq.m. to 3.0 sq.m. between half deduction in area
3.0 sq.m. above full deduction but add side pattas

QUANTITY SHEET

Widht/ Height/
Length
Sr. No. Item Description No. Breadth Depth Quantity Unit
(m)
(m) (m)

10 In Side Plaster

Bed Room

Long Wall 2 4.000 3.000 24.00 Sq.m.

Shot wall 2 3.000 3.000 18.00 Sq.m.

Deduction

Door D1 -0.5 1.000 2.100 -1.05 Sq.m.

Window W2 -0.5 1.200 1.000 -0.60 Sq.m.

Window W3 -0.5 1.200 1.200 -0.72 Sq.m.

Kitchen + Dining

Long Wall 2 4.000 3.000 24.00 Sq.m.

Shot wall 2 4.000 3.000 24.00 Sq.m.

Deduction

Door O -0.5 1.200 2.100 -1.26 Sq.m.

Window W2 -1 1.200 1.000 -1.20 Sq.m.

Verandah

https://civiljungle.com/building-estimation-step-by-step-in-excel-sheet/ 13/21
1/16/23, 6:56 PM Building Estimation Step by Step In Excel Sheet

Long Wall 2 3.000 3.000 18.00 Sq.m.

Shot wall 1 3.000 3.000 9.00 Sq.m.

Shot wall 1 3.000 1.200 3.60 Sq.m.

Deduction

Door MS -0.5 1.200 1.200 -0.72 Sq.m.

Door D -0.5 1.200 2.100 -1.26 Sq.m.

Window W -0.5 2.000 1.200 -1.20 Sq.m.

DRG. Room

Long Wall 2 5.550 3.000 33.30 Sq.m.

Shot wall 2 4.000 3.000 24.00 Sq.m.

Deduction

Door O -1 1.200 2.100 -2.52 Sq.m.

Door D -0.5 1.200 1.200 -0.72 Sq.m.

Window W -0.5 2.000 1.200 -1.20 Sq.m.

Window W1 -1 1.500 1.200 -1.80 Sq.m.

Bath Room

Long Wall 2 1.500 3.000 9.00 Sq.m.

Shot wall 2 1.200 3.000 7.20 Sq.m.

Deduction

Door D2 -0.5 0.750 2.100 -0.79 Sq.m.

Vent V1 -0.5 0.900 0.600 -0.27 Sq.m.

W.C.

Long Wall 2 1.500 3.000 9.00 Sq.m.

Shot wall 2 1.000 3.000 6.00 Sq.m.

Deduction

Door D2 -0.5 0.750 2.100 -0.79 Sq.m.

Vent -0.5 0.600 0.600 -0.18 Sq.m.

Passage

Long Wall 2 2.320 3.000 13.92 Sq.m.

Shot wall 2 1.390 3.000 8.34 Sq.m.

Deduction

Door D2 -1 0.750 2.100 -1.58 Sq.m.

Door D1 -1 1.000 2.100 -2.10 Sq.m.

Door O -1 1.200 2.100 -2.52 Sq.m.

Total Qty In Side Plaster= 208.89 Sq.m.

https://civiljungle.com/building-estimation-step-by-step-in-excel-sheet/ 14/21
1/16/23, 6:56 PM Building Estimation Step by Step In Excel Sheet

11. Out Side Plaster


How to Find Out Side Plaster as Per Drawing

QUANTITY SHEET

Widht/ Height/
Length
Sr. No. Item Description No. Breadth Depth Quantity Unit
(m)
(m) (m)

11 Out Side Plaster

Front Side 1 4.450 4.775 21.25 Sq.m.

1 3.230 2.180 7.04 Sq.m.

Lintel W 1 2.000 1.300 2.60 Sq.m.

Deduction

Door MS -0.5 1.200 1.200 -0.72 Sq.m.

Window W -0.5 2.000 1.200 -1.20 Sq.m.

Back Side 1 7.690 4.775 36.72 Sq.m.

Lintel W 2 2 1.200 1.300 3.12 Sq.m.

Deduction

Window W 2 -1 1.200 1.000 -1.20 Sq.m.

Right Side 1 10.240 4.775 48.90 Sq.m.

Deduction

Window W -0.5 2.000 1.200 -1.20 Sq.m.

Window W 3 -0.5 1.200 1.200 -0.72 Sq.m.

Vent -0.5 0.600 0.600 -0.18 Sq.m.

Vent V1 -0.5 0.900 0.600 -0.27 Sq.m.

Left Side 1 10.240 4.775 48.90 Sq.m.

Deduction

Window W 1 -1 1.500 1.200 -1.80 Sq.m.

Window W 2 -0.5 1.200 1.000 -0.60 Sq.m.

Parapet Wall

Long Wall 2 10.010 1.115 22.32 Sq.m.

Shot Wall 2 7.460 1.000 14.92 Sq.m.

Total Out Side Plastet Qty = 197.87 Sq.m.

12. Celling Plaster


How to Find Celling Plaster as Per Drawing

QUANTITY SHEET

https://civiljungle.com/building-estimation-step-by-step-in-excel-sheet/ 15/21
1/16/23, 6:56 PM Building Estimation Step by Step In Excel Sheet

Widht/ Height/
Length
Sr. No. Item Description No. Breadth Depth Quantity Unit
(m)
(m) (m)

12 Celling Plaster

Bed Room 1 4.000 3.000 12.00 Sq.m.

Kitchen + Dining 1 4.000 4.000 16.00 Sq.m.

Verandah 1 3.000 3.000 9.00 Sq.m.

DRG. Room 1 5.550 4.000 22.20 Sq.m.

Bath Room 1 1.500 1.200 1.80 Sq.m.

W.C 1 1.500 1.000 1.50 Sq.m.

Passage 1 2.320 1.390 3.22 Sq.m.

Total Out Side Plastet Qty = 65.72 Sq.m.

13. Slab R.C.C.


How to Find In Out Slab R.C.C. as Per Drawing

Slab Beam

https://civiljungle.com/building-estimation-step-by-step-in-excel-sheet/ 16/21
1/16/23, 6:56 PM Building Estimation Step by Step In Excel Sheet

Section

QUANTITY SHEET

Widht/ Height/
Length
Sr. No. Item Description No. Breadth Depth Quantity Unit
(m)
(m) (m)

13 Slab RCC

Slab Area 1 10.240 7.690 0.100 7.87 Cu.m.

S-1 3 10.240 0.230 0.350 2.47 Cu.m.

S-2 4 3.000 0.230 0.350 0.97 Cu.m.

S-3 3 4.000 0.230 0.350 0.97 Cu.m.

S-4 1 1.500 0.230 0.350 0.12 Cu.m.

S-5 1 2.315 0.230 0.350 0.19 Cu.m.

Total RCC Slab Qty= 12.59 Cu.m.

14. In Side Paint


How to Find In Side Paint as Per Drawing

QUANTITY SHEET

Widht/ Height/
Length
Sr. No. Item Description No. Breadth Depth Quantity Unit
(m)
(m) (m)

14 In Side Paint

Bed Room

Long Wall 2 4.000 3.000 24.00 Sq.m.

Shot wall 2 3.000 3.000 18.00 Sq.m.

Bed Room Ceiling 1 4.000 3.000 12.00 Sq.m.

https://civiljungle.com/building-estimation-step-by-step-in-excel-sheet/ 17/21
1/16/23, 6:56 PM Building Estimation Step by Step In Excel Sheet

Deduction

Door D1 -1 1.000 2.100 -2.10 Sq.m.

Window W2 -1 1.200 1.000 -1.20 Sq.m.

Window W3 -1 1.200 1.200 -1.44 Sq.m.

Kitchen + Dining

Long Wall 2 4.000 3.000 24.00 Sq.m.

Shot wall 2 4.000 3.000 24.00 Sq.m.

Kitchen + Dining Celling 1 4.000 4.000 16.00 Sq.m.

Deduction

Door O -1 1.200 2.100 -2.52 Sq.m.

Window W2 -2 1.200 1.000 -2.40 Sq.m.

Verandah

Long Wall 2 3.000 3.000 18.00 Sq.m.

Shot wall 1 3.000 3.000 9.00 Sq.m.

Shot wall 1 3.000 1.200 3.60 Sq.m.

Verandah Celling 1 3.000 3.000 9.00 Sq.m.

Deduction

Door MS -1 1.200 1.200 -1.44 Sq.m.

Door D -1 1.200 2.100 -2.52 Sq.m.

Window W -1 2.000 1.200 -2.40 Sq.m.

DRG. Room

Long Wall 2 5.550 3.000 33.30 Sq.m.

Shot wall 2 4.000 3.000 24.00 Sq.m.

DRG. Room Ceiling 1 5.550 4.000 22.20 Sq.m.

Deduction

Door O -2 1.200 2.100 -5.04 Sq.m.

Door D -1 1.200 1.200 -1.44 Sq.m.

Window W -1 2.000 1.200 -2.40 Sq.m.

Window W1 -2 1.500 1.200 -3.60 Sq.m.

Bath Room

Long Wall 2 1.500 3.000 9.00 Sq.m.

Shot wall 2 1.200 3.000 7.20 Sq.m.

Bath Room Ceiling 1 1.500 1.200 1.80 Sq.m.

Deduction

Door D2 -1 0.750 2.100 -1.58 Sq.m.

Vent V1 -1 0.900 0.600 -0.54 Sq.m.

https://civiljungle.com/building-estimation-step-by-step-in-excel-sheet/ 18/21
1/16/23, 6:56 PM Building Estimation Step by Step In Excel Sheet

W.C.

Long Wall 2 1.500 3.000 9.00 Sq.m.

Shot wall 2 1.000 3.000 6.00 Sq.m.

W.C Celling 1 1.500 1.000 1.50 Sq.m.

Deduction

Door D2 -1 0.750 2.100 -1.58 Sq.m.

Vent -1 0.600 0.600 -0.36 Sq.m.

Passage

Long Wall 2 2.320 3.000 13.92 Sq.m.

Shot wall 2 1.390 3.000 8.34 Sq.m.

Passage Celling 1 2.320 1.390 3.22 Sq.m.

Deduction

Door D2 -2 0.750 2.100 -3.15 Sq.m.

Door D1 -2 1.000 2.100 -4.20 Sq.m.

Door O -2 1.200 2.100 -5.04 Sq.m.

Total Qty In Side Plaster= 252.14 Sq.m.

15. Out Side Pint


How to Find Out Side Plaster as Per Drawing

QUANTITY SHEET

Widht/ Height/
Length
Sr. No. Item Description No. Breadth Depth Quantity Unit
(m)
(m) (m)

15 Out Side Plaster

Front Side 1 4.450 4.775 21.25 Sq.m.

1 3.230 2.180 7.04 Sq.m.

Lintel W 1 2.000 1.300 2.60 Sq.m.

Deduction

Door MS -1 1.200 1.200 -1.44 Sq.m.

Window W -1 2.000 1.200 -2.40 Sq.m.

Back Side 1 7.690 4.775 36.72 Sq.m.

Lintel W 2 2 1.200 1.300 3.12 Sq.m.

Deduction

Window W 2 -1 1.200 1.000 -1.20 Sq.m.

Right Side 1 10.240 4.775 48.90 Sq.m.

Deduction

https://civiljungle.com/building-estimation-step-by-step-in-excel-sheet/ 19/21
1/16/23, 6:56 PM Building Estimation Step by Step In Excel Sheet

Window W -1 2.000 1.200 -2.40 Sq.m.

Window W 3 -1 1.200 1.200 -1.44 Sq.m.

Vent -1 0.600 0.600 -0.36 Sq.m.

Vent V1 -1 0.900 0.600 -0.54 Sq.m.

Left Side 1 10.240 4.775 48.90 Sq.m.

Deduction

Window W 1 -2 1.500 1.200 -3.60 Sq.m.

Window W 2 -1 1.200 1.000 -1.20 Sq.m.

Parapet Wall

Long Wall 2 10.010 1.115 22.32 Sq.m.

Shot Wall 2 7.460 1.000 14.92 Sq.m.

Total Out Side Plastet Qty = 191.18 Sq.m.

FAQ

Building Estimation
A building estimator or cost estimator is an individual that quantifies the materials, labor, and equipment needed to complete
a construction project. Building cost estimating can concern diverse forms of construction from residential properties to hi-rise and
civil works.

Calculated to Estimate
Estimation is used to predict the answer to a calculation.
The estimation uses round numbers in a calculation to make it quicker or easier to get an approximate answer.
For example, if we were to estimate the answer to 11.87 x 4.876. We could use the calculation 10 x 5 = 50.

Estimation of Building
Estimation of A Building With Plan is processed of predicting the probable cost of the project by calculating material quantity and their
costing with help of market rates before undertaking any construction project.

Estimate of Building in Excel


Cost Estimation RCC Building Excel Sheet In order to determine the rate of a particular item, the factors affecting the rate of that item
are studied carefully and then finally a rate is decided for that item. This process of determining the rates of an item is termed as analysis
of rates or rate analysis.

Estimate for Building


Estimation of A Building With Plan is processed of predicting the probable cost of the project by calculating material quantity and their
costing with help of market rates before undertaking any construction project.

Like this post? Share it with your friends!

Suggested Read –

What is BoQ | BoQ Meaning | Advantages of BoQ | What is BoM


https://civiljungle.com/building-estimation-step-by-step-in-excel-sheet/ 20/21
1/16/23, 6:56 PM Building Estimation Step by Step In Excel Sheet

Difference Between One Way Slab and Two Way Slab | What is Slab
What Is Rate Analysis | Rate Analysis of Earth Work, Brick, Concrete and Plaster
What Is Construction Contract | Types of Engineering Contracts | Percentage-Rate Contract
Estimation for Building Works | Centre Line Method | Long and Short Wall or Out and in to in a method
What Is Structural Settlement | Causes For Structural Settlement | What Is Soil Settlement & Foundation Structural Settlement

https://civiljungle.com/building-estimation-step-by-step-in-excel-sheet/ 21/21

You might also like